SEAGOING 

AND    OTHER 

CONCRETE    SHIPS 


OXFORD  TECHNICAL  PUBLICATIONS 


SEAGOING 


AND  OTHER 


CONCRETE  SHIPS 


BY 


N.  K.  FOUGNER,  C.E. 

M.AM.SOC.C.E.,     MEDLEM     NORSK    JNGENIEUR    FORENING, 
ASSOC.INST.N.A. 


LONDON 
HENRY  FROWDE  AND  HODDER  &  STOUGHTON 

THE  LANCET  BUILDING 
1   BEDFORD  STREET,  STRAND,  W.C.2 


- »  * 
.  .*• 


First  published  1922 


PRINTED  IN   GREAT  BRITAIN 

BY  HAZELL,   WATSON   AND   VINEY,   LD. 

LONDON  AND  AYLESBURY. 


PREFACE 

THE  aim  of  the  author  has  been  to  present  a  true  record  of  the 
principal  seagoing  concrete  ships  actually  built  up  to  the  present, 
and  to  analyse  the  merits  of  these  ships  in  comparison  with 
ships  built  of  steel  and  wood. 

The  main  part  of  this  book  is  based  on  personal  experience 
gained  in  the  construction  of  about  thirty  vessels  of  concrete 
during  the  past  five  years.  The  information  referring  to  ships 
built  by  others  has  been  obtained  partly  through  correspondence 
with  the  designers,  builders,  or  owners,  and  partly  from  state- 
ments published  by  them  in  the  engineering  press.  As  far  as 
possible,  facts  have  been  ascertained  from  official  documents, 
and  reference  to  the  source  of  information  is  made  in  each  case 

The  calculations  are  condensed  in  the  Appendix  and  have, 
been  avoided  in  the  general  text  in  order  to  facilitate  the  reading 
for  shipping  people  and  others,  who  will  play  an  important 
part  in  the  further  development  of  the  new  type  of  ships  without 
being  concerned  in  the  technical  side  of  the  question.  The 
usual  methods  of  calculating  displacement,  speed,  etc.,  found 
in  standard  works  on  naval  architecture,  have  been  omitted, 
as  they  are  practically  identical  for  concrete  ships. 

Numerous  technical  papers  and  articles  on  concrete  ships 
have  appeared  in  the  press,  but  unfortunately  the  hopes  or 
opinions  expressed  have  frequently  been  based  on  anticipation 
rather  than  on  actual  experience.  The  result  has  been  a  mass 
of  conflicting  reports  which  have  caused  much  confusion  on 
the  subject. 

If  the  present  book  should  aid  in  clearly  establishing  the 
true  status  of  the  best  type  of  seagoing  concrete  ship  to-day, 
and  thus  form  a  basis  for  further  development,  the  author's 
chief  object  will  be  accomplished. 

N.  K.  F. 


CHBISTIANIA,  1922. 


515600 


CONTENTS 
CHAPTER   I 

PAGE 

INTRODUCTORY 1 

CHAPTER    II 

THE  FIRST  SEAGOING  CONCRETE  SHIP 

Preliminary  Consideration — Government  Permit  —  Assumptions  for 
Calculation  Purposes — Method  of  Construction — Engine  Foundations  and 
Stern  Post — Concreting — Equipment — Launching — Trials — Docking  for 
Inspection — Results  of  Experiment  .......  7 

CHAPTER   III 

M.S.    STIER    AND    M.S.    ASKELAD 

Negotiations  —  M.S.  Stier  —  Strength  Calculations  —  Constructional 
Details  —  Construction  —  Official  Trials  —  M.S.  Askelad  —  Constructional 
Details — Official  Trials — The  First  North  Sea  Trip — Subsequent  Service — 
Summary  of  Results  .  .  .  .  .  .  .  .  .  .19 

CHAPTER   IV 

COMPARISON    OF    SOME    SHIPS    BUILT    TO    CLASS    WITH    THE 
AUTHOR'S    TRIAL    SHIPS 

Classification  of  Concrete  Ships — Comparative  Values  of  Cargo  Carriers 
— American  Concrete  Ships — S.S.  Selma  and  Latham;  S.S.  Cape  Fear  and 
Sapona  ............  41 

CHAPTER    V 

CONCRETE    TUGS,    FLOATING    DOCKS,    LIGHTSHIPS,     AND 

LIGHTERS 

The  First  Concrete  Tug — The  First  Concrete  Floating  Dock— The 
First  Concrete  Lightship — Concrete  Water-carrier — Concrete  Lighters  .  50 

CHAPTER    VI 

SHIPS    BUILT    IN    THE    UNITED    STATES 

The  Faith — U.S.  Shipping  Board  Investigations — The  First  U.S. 
Standard  Concrete  Ship — Ships  actually  completed — Oil-Tankers — Oil- 
Storage  generally  ..........  68 

CHAPTER    VII 

DAMAGES    AND    REPAIRS 

M.S.   Askelad — M.S.   Nicanor— M.S.  Stier— S.S.  Polias        ...       86 

vi  i 


viii  CONTENTS 

CHAPTER    VIII 

COMPARISONS    OF    CONCRETE    SHIPS    WITH    STEEL    SHIPS 

PAGE 

First  Cost — Units  of  Material  and  Labour  per  Ton — Examples  of  Costs 
— Speed— Strength — Running  Expenses — The  Future  of  the  Concrete 
Ship 96 

CHAPTER    IX 

SHIPBUILDING    CONCRETE 

Introductory — Portland  Cement — Water — Aggregate — Impurities  in 
Aggregate — Sand — Light-weight  Aggregate — Proportions  of  Mixture — 
Mixing — Placing  and  Curing — Steam  Curing — Freezing — Vibration,  Pres- 
sure, etc. — Compressive  Strength — Shear  Strength — Bond  Strength — 
Elasticity— Watertightness — Contraction  and  Expansion — Trass  Concrete 
— Action  of  Sea- water — Action  of  Oils.  etc. — Repairs — Fire-resisting 
Power 107 

CHAPTER    X 

STEEL    REINFORCEMENT 
Types— Quality— High-Carbon  Steel 146 

CHAPTER    XI 

CONDITIONS    GOVERNING    STRUCTURAL    DESIGN 
Theory  of  Design — Side  Frames — Bottom  Frames — Centre    Keelson — 
Longitudinal  Strength — Strength  of  Shell  Slab — Watertight   Bulkheads — 
Norwegian  Government  Requirements — Deflection  Test  on  Lighter  .          .      150 

CHAPTER    XII 

GENERAL    METHOD    OF    CONSTRUCTION 

Preliminary  Work — Bottom  Floor  Prepared — Outside  Centring  Com- 
pleted— Bottom  and  Side  Reinforcement  in  Place — Frame  Centring  and 
Reinforcement  in  Place — Deck  Centring  in  Place — Centring  and  Rein- 
forcement Completed — Concreting — Concreting  Finished — Cement  Finish — 
Cement- Gun  Concreting  .  .  .  .  .  .  .  .  .169 

CHAPTER    XIII 

SOME    SPECIAL    METHODS    OF    CONSTRUCTION    AND 
PARTICULAR    SHIPS 

M.S.  R.  P.  Durham — M.S.  Linnea — "  Pre-cast  "  Systems — S.S.  Armistice 
— S.S.  Bartels — Present  Tonnage  of  Concrete  Ships — Author's  Recom- 
mendations ...........  181 

APPENDIX 

STRENGTH    CALCULATIONS    FOR    M.S.    ASKELAD       .          .          .197 

INDEX  212 


SEAGOING 

AND    OTHER 

CONCRETE  SHIPS 

CHAPTER    I 
INTRODUCTORY 

WHEN  a  new  idea  or  invention  is  first  put  into  service  it  is 
naturally  received  with  a  certain  amount  of  antagonism  ;  the 
concrete  ship  is  no  exception  to  this  rule.  The  doubts  still 
abounding  in  regard  to  the  concrete  ship  arise  principally  from 
ignorance  of  what  has  already  been  accomplished  ;  and  in  order 
to  appreciate  what  has  been  accomplished,  and  so  acquire  a 
basis  for  the  formation  of  an  intelligent  opinion  on  the  subject 
of  concrete  ships,  it  is  desirable  to  study,  however  briefly,  the 
development  in  the  use  of  other  shipbuilding  materials. 

From  the  earliest  days  down  to  almost  the  middle  of  the 
nineteenth  century  wood  was  the  material  of  which  ships  were 
built.  The  use  of  wood  was  not  a  matter  of  choice,  for  it  was 
the  only  material  available  ;  and  for  the  ships  built  in  the  days 
before  the  nineteenth  century  wood  was  not  an  unsuitable 
material. 

The  proven  suitability  of  wood,  and  a  natural  tendency  to 
the  use  of  a  buoyant  material  for  a  structure  whose  essential 
quality  is  buoyancy,  probably  retarded  the  consideration  of 
alternative  materials.  But  the  developments  in  shipping 
resulting  from  the  adoption  of  steam  machinery  for  propulsion 
stimulated  the  desire  for  improved  methods  of  constructing 
ships.  The  first  iron  steamer  was  the  Aaron  Manby,  built  in 
London  in  1821,  although  the  first  use  of  iron  as  the  material  for 
a  ship  probably  dates  back  to  1777,  when  an  iron  lighter  was 
built  in  Yorkshire.  The  objections  urged  against  iron  as  the 
material  for  shipbuilding  were  that  iron  was  too  heavy  and 
could  not  float ;  that  iron  was  too  brittle  and,  therefore,  liable 
1 


„«  «.    * 

1U 


2          SEAGOING  AND   OTHER  CONCRETE   SHIPS 

to  severe  damage  in  the  event  of  grounding,  which  damage  would 
be  difficult  to  repair  ;  that  the  bottoms  of  the  ships  would 
become  rapidly  fouled  with  marine  growth  ;  and  that  iron  would 
affect  the  compass  by  creating  magnetic  disturbances. 

The  first  objection  was  soon  ruled  out  ;  iron  ships  not  only 
floated  as  well  as  wood  ships,  but  proved  even  to  be  lighter  than 
wood  ships. 

As  regards  the  second  objection,  there  were  two  historic 
cases  of  grounding  which  caused  this  one  also  to  be  ruled  out. 
The  first  case  is  that  of  the  Garry  Owen,  a  coasting  steamer  built 
at  Birkenhead  in  1834.  On  her  maiden  voyage  the  Garry  Owen 
was  driven  ashore  in  a  gale  in  company  with  a  number  of  wood 
ships.  The  latter  were  all  either  completely  wrecked  or  very 
seriously  damaged ;  the  Garry  Owen  was  undamaged.  The 
second  case  is  that  of  the  Great  Britain,  the  first  Atlantic  liner 
to  be  built  of  iron  and  to  have  a  screw  propeller.  She  was  built 
at  Bristol  in  1843  to  the  design  of  I.  K.  Brunei  and  was  the 
largest  ship  of  her  day.  She  had  been  only  about  a  year  in 
service  when  she  was  run  ashore  on  the  east  coast  of  Ireland, 
where  she  remained  throughout  a  whole  winter  exposed  to  the 
full  force  of  the  sea.  When  refloated  she  was  found  to  be  very 
little  the  worse  for  her  experience.  These  two  cases  did  much 
to  establish  the  reputation  of  iron  as  a  shipbuilding  material. 

The  objections  relating  to  marine  growth  and  magnetic 
disturbance  were  not  found  to  be  serious.  Frequent  cleaning 
and  painting  of  the  under  body  keeps  down  marine  growth  ; 
and  compensation  for  the  magnetic  disturbance  due  to  the  iron 
hull  can  be  made  in  the  compass. 

The  principal  consideration  underlying  the  transition  from 
wood  to  iron  was  structural  strength.  It  was  found  practically 
impossible  to  make  wood  ships  adequately  strong  if  the  length 
approached  300  feet ;  and  this  length  was  not  sufficient  for  the 
shipping  needs  of  the  time.  A  further  consideration  underlying 
the  transition  was  the  difficulty  of  making  a  wood  stern  post 
and  stern  construction  fit  to  withstand  the  forces  developed  by 
a  propeller,  and  this  consideration  became  increasingly  important 
with  increase  in  engine  power.  But  prejudices  are  not  easily 
dispelled.  So  late  as  1861  the  British  Parliament  appropriated 
one  million  pounds  sterling  for  the  purchase  of  timber  for  the 
construction  of  wood  warships. 


INTRODUCTORY  3 

During  the  war  there  was  a  partial  return  to  wood  as  a  ship- 
building material  in  the  United  States.  This  was  brought  about 
by  the  great  desire  for  mercantile  tonnage  and  the  limited  capacity 
of  the  American  steel  works  for  the  production  of  shipbuilding 
material.  The  results  were  not  satisfactory  ;  the  ships  were 
leaky  and  structurally  weak.  No  doubt  the  results  would  not 
have  been  so  bad  had  carefully  selected,  seasoned,  timber  been 
used  instead  of  the  "  green  "  timber  which  was  alone  available. 
But  on  the  whole,  the  programme  of  wood  shipbuilding  merely 
affords  further  justification,  if  any  is  needed,  for  the  transition 
from  wood  to  iron. 

The  next  development  in  shipbuilding  material  was  the 
substitution  of  steel  for  iron,  a  development  in  detail,  however, 
rather  than  in  principle.  The  principal  defects  of  iron  were  its 
unreliable  character  and  its  distinct  grain.  The  former  rendered 
it  almost  impossible  to  guarantee  the  strength  of  any  plate  ; 
the  latter  resulted  in  the  plate  being  stronger  in  one  direction 
than  in  another.  Steel  is  a  very  reliable  material,  and  it  has 
practically  no  grain,  so  that  it  is  equally  strong  in  all  directions  ; 
this  latter  quality  is  of  some  importance  in  a  shipbuilding  material, 
for  there  are  few  points  in  a  ship  where  the  principal  stress  is 
exactly  longitudinal  or  exactly  transverse,  and  there  are  almost 
as  many  directions  of  principal  stress  as  there  are  points  where 
stress  exists.  Steel  has  the  further  great  advantage  over  iron 
of  being  about  25  to  30  per  cent,  stronger.  The  disadvantages 
of  steel  as  compared  to  iron  are  greater  liability  to  corrosion 
and,  in  the  early  days,  increased  cost. 

The  transition  from  iron  to  steel,  though  gradual,  was  not  by 
any  means  such  a  slow  process  as  the  transition  from  wood  to 
iron.  There  were,  of  course,  difficulties  to  be  overcome.  At 
first  the  new  material  was  uneven  in  quality  and,  in  addition, 
the  conditions  under  which  it  could  be  worked  were  different 
from  those  for  iron  ;  these  two  considerations,  separately  and 
in  combination,  account  for  a  large  quantity  of  cracked  and, 
therefore,  discarded  material.  The  difficulty  as  regards  liability 
to  corrosion  was  easily  overcome  ;  this  involves  merely  care 
in  upkeep.  The  greatest  difficulty  was  that  of  cost.  But  the 
difference  in  cost  between  a  steel  and  an  iron  hull  was  not  in  the 
ratio  of  the  cost  per  ton  of  steel  to  the  cost  per  ton  of  iron  ; 
for  the  greater  strength  of  steel  permitted  a  saving  in  weight  of 


4         SEAGOING  AND   OTHER  CONCRETE   SHIPS 

material  amounting  to  about  15  per  cent.  The  increasing  use 
of  steel  consequent  upon  a  recognition  of  its  advantages  brought 
about  a  reduction  in  its  cost,  so  that  within  a  few  years  of  the 
introduction  of  steel  a  steel  hull  was  actually  slightly  cheaper 
than  an  iron  hull ;  nowadays  a  steel  hull  is  very  much  cheaper 
than  an  iron  hull — indeed,  iron  hulls  are  seldom  built. 
.  An  idea  of  the  rate  of  the  transition  from  iron  to  steel  can 
be  obtained  from  the  pages  of  Lloyd's  Register.  In  1883,  when 
iron  shipbuilding  was  at  its  zenith,  860,000  tons  of  iron  ships 
were  built  in  British  yards  ;  by  1888  this  amount  had  decreased 
to  50,000  tons,  and  by  1895  to  10,000  tons.  Steel  ships  were 
first  registered  in  1878,  their  tonnage  amounting  to  4,500  tons. 
In  1880  about  4  per  cent,  of  the  tonnage  built  in  British  yards 
was  of  steel ;  by  1885  this  percentage  had  increased  to  60,  and 
by  1890  to  about  95. 

The  next  development  in  shipbuilding  material  is  the  use 
of  reinforced  concrete.  This  development  is  only  in  its  initial 
stages,  but  in  the  following  chapters  an  outline  of  actual  achieve- 
ment is  given  ;  it  must  be  borne  in  mind  that,  as  indicated 
above,  over  forty  years  elapsed  between  the  first  attempt  at  iron 
shipbuilding  and  the  building  of  the  first  iron  steamer,  and  a 
further  twenty  years  before  iron  was  recognized  as  being  suitable 
for  the  construction  of  seagoing  ships,  whereas  only  four  or 
five  years  have  elapsed  since  the  building  of  the  first  seagoing 
concrete  ship. 

In  the  consideration  of  concrete  as  a  shipbuilding  material 
it  is  not  necessary  to  draw  any  comparisons  with  wood,  for 
wood  as  a  material  for  seagoing  ships  has,  on  the  considerations 
outlined  above,  been  discarded.  In  what  follows,  therefore,  the 
case  for  concrete  is  presented  with  steel  as  the  background. 

An  opinion  commonly  expressed  by  shipping  people  is  that 
concrete  may  be  suitable  for  the  construction  of  lighters  and  such 
small  craft,  but  is  totally  unsuitable  for  seagoing  ships.  The 
author  is,  however,  of  a  different  opinion  and  maintains  that 
concrete  is  even  better  suited  for  the  construction  of  seagoing 
ships  than  of  lighters.  Lighters  must  often  be  of  the  smallest 
possible  dimensions  and  draught  for  a  given  cargo  capacity  ; 
and  their  shell  must  be  particularly  capable  of  withstanding 
local  blows  and  scratches  due  to  rough  handling,  collisions  with 
wharves,  etc.  It  is  in  regard  to  these  requirements  that  concrete 


INTRODUCTORY  5 

compares  least  favourably  with  steel,  as  will  be  indicated  in  the 
following  pages  and  throughout  the  book. 

It  is  common  knowledge  that  concrete  hulls  are  heavier  than 
steel  hulls  of  the  same  outside  dimensions.  This  is  due  to  the 
fact  that  concrete  is  not  so  strong  as  steel  and,  therefore,  if  a 
concrete  hull  and  a  similar  steel  hull  of  the  same  dimensions 
are  to  be  equally  strong,  as  they  ought  to  be,  a  greater  weight  of 
concrete  than  of  steel  must  be  used.  The  author  does  not  believe 
that  concrete  will  ever  be  improved  to  the  extent  that  it  will 
be  equal  to  steel  in  strength  and  elasticity  ;  but  such  an  improve- 
ment is  not  necessary,  since  concrete  has  compensating  advan- 
tages over  steel. 

In  comparisons  between  concrete  and  steel  ships  it  is  neces- 
sary to  assume  as  a  basis  either  equality  of  deadweight  carrying 
capacity  or  equality  of  total  displacement.  All  the  concrete 
ships  built  by  the  author  were  ordered  on  the  basis  of  a 
stipulated  deadweight,  and  it  is  reasonable  to  assume  that 
for  some  time  to  come  this  custom  will  prevail  on  account  of 
the  present  uncertainty  of  the  calculations  of  hull  weight  made 
by  inexperienced  builders.  Considering,  therefore,  a  concrete 
ship  and  a  steel  ship  of  equal  deadweight  carrying  capacity,  it 
is  obvious  that  the  former  will  have  a  greater  total  displacement 
because  of  her  greater  weight  of  hull ;  and  the  greater  displace- 
ment can,  in  general,  only  be  obtained  by  the  adoption  of  larger 
dimensions.  Hence  the  concrete  ship  has  a  greater  cubic  capacity, 
and  a  larger  space  available  for  deck  cargo,  than  the  steel  ship. 
This  is  a  distinct  advantage  in  trades  where  the  cargoes  commonly 
carried  are  light  and  bulky,  measuring  about  70  cubic  feet,  or 
more,  per  ton  weight.  For  example,  by  far  the  greater  propor- 
tion of  the  war  supplies  transported  from  the  United  States  to 
France  were  so  light  in  relation  to  their  bulk  that  the  ships 
carrying  them  were  completely  filled  before  they  had  on  board 
sufficient  weight  to  sink  them  to  their  designed  load  draughts. 
Of  course,  the  increased  capacity  involves  the  disadvantage  of 
increased  harbour  dues,  since  these  are  assessed  on  a  cubic  capacity 
basis. 

The  foregoing  elements  in  the  comparison  between  concrete 
and  steel  can  be  grasped  by  anyone  who  reasons  the  matter  out 
without  any  reference  to  actual  experience  with  concrete.  But 
the  following  facts  are  the  results  of  experience,  experience 


6          SEAGOING  AND   OTHEE   CONCRETE   SHIPS 

gained  by  the  author  from  the  construction  of  about  thirty 
concrete  ships,  and  experience  gained  by  the  owners,  officers, 
and  crew  who  have  run  these  ships  in  overseas  trade  for  some 
years : 

Concrete  ships 

are  cheaper  to  build,  and  cost  less  in  upkeep, 
are    less   subject   to   vibration    from   engines   or   due    to 
"  panting,"  and,  owing  to  the  heavier  hull,  require  less 
ballast  when  "  light,"  and  so  have  easier  movements  in 
rough  seas, 

are  more  quickly  and  more  cheaply  repaired, 
are  fireproof,  are  not  subject  to  corrosion, 
have  better  insulating  properties  for  cargoes"  such  as  ice, 

fruit,  etc., 

and  are  more  easily  kept  clean. 
Steel  ships  have  the  following  advantages  : 
less  weight  of  hull, 
the  shell  is  better  able  to  withstand  local  blows  and  scratches 

resulting  from  rough  handling. 

The  question  of  structural  strength  does  not  enter  into  the 
comparison  since  adequate  strength  can  be  provided  in  either 
material.  The  time  of  construction  is  generally  less  for  concrete 
ships,  but  is  not  less  than  the  war-time  records  achieved  in 
steel  construction.  The  speed  is  practically  the  same  for  ships 
of  equal  deadweight  and  engine  power,  but  this  comparison  is 
much  affected  by  factors  such  as  underwater  shape  and  external 
finish,  whose  influence  may  be  greater  than  that  of  mere  weight. 


CHAPTER    II 
THE   FIRST    SEAGOING    CONCRETE    SHIP 

Preliminary  Consideration — Government  Permit — Assumptions  for  Calcu- 
lation Purposes — Method  of  Construction — Engine  Foundations  and  Stern  Post 
—  Concreting  —  Equipment  —  Launching  —  Trials  —  Docking  for  Inspection — 
Results  of  Experiment. 

Preliminary  Consideration.— The  construction  of  the  Namsenfjord, 
the  first  seagoing  concrete  ship,  was  an  experiment  based  on  the 
favourable  experience  gained  by  the  author  from  the  construc- 
tion of  a  concrete  lighter  in  Manilla  during  his  activity  as  a 
Civil  Engineer  in  the  Far  East. 

In  1910-11  preparatory  investigations  of  the  possibility  of 
constructing  seagoing  concrete  ships  were  begun,  and  the  author's 
first  patents  are  dated  January  1912.  The  building  of  the  first 
seagoing  concrete  ship  was  not,  therefore,  entirely  due  to  the 
world  war  ;  but  lack  of  capital  and  other  circumstances  delayed 
the  realization  of  ideas  fully  worked  out  in  theory  at  an  earlier 
period. 

In  Norway  anyone  is  free  to  build  lighters  of  concrete  or  any 
other  material  without  regard  to  Government  rules  ;  but  the 
construction  of  seagoing  ships  intended  to  carry  a  Norwegian 
crew  and  flag  is  subject  to  the  control  of  the  Department  of 
Shipping. 

In  1916  the  author  forwarded  plans  of  a  seagoing  concrete 
lighter  of  2,700  tons  deadweight  carrying  capacity  to  the  Depart- 
ment of  Shipping.  In  order  to  obtain  expert  opinion  on  the 
proposal  the  Department  referred  the  plans  to  a  specially 
appointed  Technical  Committee. 

The  utmost  doubt  was  freely  expressed  as  to  the  possibility 
of  a  concrete  ship  having  the  necessary  strength  and  elasticity 
to  resist  strains  due  to  heavy  seas  and  to  vibrations  from  the 
engines.  Naval  architects,  concrete  engineers,  and  sailors 
expressed  their  unreserved  opinions,  through  the  press  and 
otherwise,  that  the  whole  idea  was  impossible  and  that  a  seagoing 

i 


8          SEAGOING  AND   OTHER  CONCRETE   SHIPS 

concrete  ship  was  doomed  to  disaster  the  first  time  she  encoun- 
tered rough  weather.  It  was  no  wonder,  therefore,  that  the 
Government  authorities  hesitated  to  grant  a  permit  for  the 
construction  of  such  a  ship. 

Since  no  shipowner  was  found  willing  to  take  the  risk  involved 
in  ordering  the  first  seagoing  concrete  ship,  the  author's  firm 
decided  to  build  the  Namsenfjord  at  their  own  expense  and  for- 


FIG.  1. — M.S.  Namsenfjord,  on  trial  during  August  1917.     The  First  Seagoing 

Concrete  Ship. 

warded  an  application  to  the  Department  of  Shipping  on  22nd 
November  1916  for  the  necessary  permit.  The  reply  from  the 
Department,  dated  9th  December  1916,  was  to  the  effect  that 
a  definite  opinion  could  not  be  given  until  the  proposal  had 
been  investigated  by  the  Technical  Committee  appointed  to 
consider  the  earlier  proposal ;  further,  the  author's  firm  was 
required  to  promise  to  bear  the  expenses  connected  with  the 
investigation. 

The  project  was  discussed  at  a  number  of  conferences  with 


THE   FIRST   SEAGOING   CONCRETE   SHIP  9 

the  Director  of  Shipping  and  his  chief  engineer,  both  of  whom 
gave  it  full  consideration.  Government  officials  closely  watched 
the  practical  experience  gained  daily  with  the  concrete  lighters 
built  by  the  author's  firm  ;  and  detailed  plans  and  calculations 
were  worked  out  for  the  ship.  Meanwhile  the  Technical  Com- 
mittee got  to  work  ;  and  it  was  decided  that  plans  and  calcu- 
lations must  be  approved  by  the  Committee  before  the  ship  could 
be  built. 

Government  Permit. — From  the  elaborate  preparations  being 


FIG.  2. — M.S.  Namsenfjord.     General  Arrangement. 

made  it  appeared  that  the  investigation  of  the  proposal  would 
take  a  long  time  ;  and  so  the  author  asked  the  Chairman  of 
the  Technical  Committee,  Dr.  J.  Bruhn,  to  support  his  applica- 
tion to  the  Government  for  special  permission  to  construct  the 
Namsenfjord  on  his  own  responsibility  without  waiting  for  the 
approval  of  the  Committee.  The  application  was  forwarded  to 
the  Department  of  Shipping  on  9th  March  1917.  The  reply 
from  the  Director  of  Shipping,  dated  31st  March,  granted  the 
desired  permission,  but  stipulated  that  the  ship  should  not  be 
put  into  commission  as  a  cargo  carrier  without  a  permit  from 
the  Department,  that  such  permit  should  be  for  smooth- water 


10        SEAGOING  AND   OTHER  CONCRETE   SHIPS 

service  only,  and  that  it  should  be  given  for  a  short  period  only, 
being  renewed  for  successively  increasing  periods  if  the  per- 
formance of  the  ship  were  satisfactory. 

While  awaiting  hopefully  the  grant  of  the  Government  permit 
for  the  construction  of  the  ship  negotiations  had  been  carried 
on  with  several  shipowners  ;  and  in  January  1917  a  contract  was 
signed  with  Mr.  Anzjon,  of  Namsos,  for  delivering  Namsenfjord 
complete  at  a  price  of  kr.  90,000  (about  £5,000)  ;  Mr.  Anzjon 
intended  to  use  the  ship  for  the  carriage  of  lumber  on  the  coast, 
but  wanted  her  equipped  also  for  the  North  Sea  trade. 

The  main  particulars  of  Namsenfjord  are  : 

Length  over-all,  84  feet ;    breadth,  20  feet  ;    depth,  11-5  feet. 

Cargo  capacity  (deadweight),  about  200  tons. 

Capacity  of  oil  and  fuel  tanks,  5-5  tons. 

Capacity  of  freshwater  tanks,  8-0  tons. 

Engine,  Bolinder  crude  oil  motor,  80  B.H.P. 

Block  coefficient,  0-75. 

Designed  speed,  7J  miles  per  hour. 

Total  crew,  7  men. 

Assumptions  for  Calculation  Purposes. — In  order  to  ensure 
that  the  ship  would  be  sufficiently  strong,  consideration  was 
given  to : 

(a)  Local  stresses,  in  bottom,  sides,  and  deck,  due  to  water- 
pressure  and  to  weights  of  cargo  carried. 

(b)  longitudinal  stresses,  in  bottom,  sides,  and  deck,  due  to 
bending  arising  from  local  inequalities  of  weight  and  buoyancy 
along  the  length  of  the  ship  considered  as  a  girder. 

(c)  Stresses  due  to  vibrations  set  up  by  engines. 

For  calculation  purposes  the  following  assumptions  were 
made  as  regards  permissible  stresses  : 

Concrete  :  to  have  an  ultimate  compressive  strength  of  at 
least  4,000  Ib.  per  sq.  inch  at  28  days,  the  proportions  of  mixture 
and  the  class  of  material  being  determined  from  practical  tests 
before  commencing  the  actual  pouring. 

Permissible  compressive  stress,  1,000  Ib.  per  sq.  inch. 
Permissible  shearing  stress,  120  Ib.  per  sq.  inch. 

Steel  Reinforcement  :  to  be  of  open  hearth,  mild,  medium- 
grade  steel,  of  ordinary  shipbuilding  quality,  having  an  ultimate 


THE   FIRST  SEAGOING  CONCRETE   SHIP 


11 


tensile  strength  of  28  to  32  tons  per  sq.  inch  and  an  elongation 
of  20  per  cent,  in  eight  inches  length. 

Permissible  tensile  stress,   12,000  Ib.  per  sq.  inch. 
Permissible  shearing  stress,  8,000  Ib.  per  sq.  inch. 

The  methods  of  calculation  are  discussed  in  Chapter  XI. 
and  actual  specimen  calculations  are  given  in  the  Appendix. 

The  disposition  and  amount  of  steel  reinforcement  are  shown 
in  Fig.  3.  Rods  of  from  J  to  1J  inch  diameter  were  used,  amount- 
ing in  all  to  10  tons. 


FIG.   3. — Midship  section  of  M.S.  Namsenfjord.     Left  half  through  Hatch;  right 

half  through  Deck. 

Method  of  Construction. — The  actual  construction  of  the  hull 
was  carried  out  in  accordance  with  a  system  devised  by  the 
author,  using  a  perforated  metal  lath  instead  of  wood  forms 
for  the  sides,  deck,  transverse  bulkheads,  interior  water  tanks, 
etc.  Wood  centring  was,  however,  used  for  frames  and  deck 
beams.  The  metal  lath  was  stiffened  and  supported  by  the 
wood  boxes  for  frames  and  beams.  The  main  reinforcing  bars 
were  tied  to  the  metal  mesh.  One  layer  of  mesh  was  placed 
near  each  surface  of  vertical  plating,  and  concrete  was  poured 
between  ;  the  two  surfaces  were  afterwards  finished  with  cement 
mortar. 


12       SEAGOING  AND  OTHER  CONCRETE   SHIPS 

Engine  Foundations  and  Stern  Post. — The  most  important 
and  difficult  details  were  the  engine  foundations  and  the  stern 
post  with  rudder  attached.  Upon  the  satisfactory  solution  of 
the  problems  involved  in  the  design  of  these  elements  depended 
largely  the  ability  of  the  concrete  ship  to  resist  the  strains  due 
to  vibrations  of  the  engines.  It  was  hoped  that  the  concrete 
ship  would  show  less  vibration  than  a  steel  ship  ;  should  this 


FIG.  4. — Namsenfjord  from  aft,  July  1917.     The  lower  wood  fender  has  now 
been  removed  as  it  was  found  unnecessary. 

not  be  the  case  the  result  might  be  disastrous  for  the  mechanically 
propelled  concrete  ship. 

The  engine  foundation  consists  of  two  heavy  girders,  parallel 
to  the  centre-line  of  the  ship  and  connecting  five  transverse 
frames.  The  stiffness  of  these  girders  ensures  that  the  loads 
due  to  engine  vibration  will  be  properly  distributed  over  the 
transverse  frames  and  bottom  slab.  The  engine  bed-plate  was 
of  cast  iron,  with  holes  for  eight  1J  inch  holding-down  bolts  ; 
openings  were  arranged  in  the  concrete  foundation  girders  to 


*st  •* 


14        SEAGOING  AND  OTHER  CONCRETE   SHIPS 

give  access  to  the  bolt-heads.  It  was  considered  preferable  to 
arrange  wood  packing  between  the  engine  bed-plate  and  the 
concrete  girders  rather  than  to  secure  the  bed-plate  to  the 
concrete  direct.  The  purpose  of  the  packing  is  to  relieve,  to 
some  extent,  the  load  on  the  holding-down  bolts.  The  wood 
packing  was  of  oak,  seven  inches  thick  ;  in  later  ships,  however, 
the  thickness  has  been  reduced  to  two  inches.  Heavy  steel 
reinforcement  was  placed  near  the  tops  of  the  foundation  girders 
and  carried  down  at  the  ends  to  the  bottom  slab  and  transverse 
frames  for  anchorage.  Steel  washers  were  arranged  under  the 
holding-down  bolt-heads,  and  the  holes  in  the  girder  were  filled 
in  with  cement  mortar  after  the  bolts  were  placed.  The  arrange- 
ment has  proved  satisfactory,  no  trouble  having  been  experienced 
up  to  date. 

From  Fig.  5  it  can  be  seen  that  there  is  an  interior  stern 
post  of  concrete  constructed  as  part  of  the  concrete  hull.  To 
the  concrete  stern  post  is  attached  a  wrought-iron  post  of  rect- 
angular section  having  a  bearing  for  the  propeller  and  a  vertical 
post  for  the  rudder.  The  wrought-iron  post  is  secured  to  the 
concrete  post  by  17  anchor  bolts  15-18  inches  long  and  f  inch 
diameter  with  hooked  ends  ;  these  bolts  were  screwed  into  the 
wrought-iron  post  on  port  and  starboard  sides  alternately  and 
had  their  heads  clenched.  In  addition,  steel  plates  eight  inches 
wide  were  riveted  to  the  wrought-iron  post  to  form  a  channel 
section  enveloping  the  end  of  the  concrete.  The  stern  tube  is 
of  cast  iron,  and  is  screwed  into  the  wrought-iron  post. 

Concreting. — Before  concrete  was  poured  all  the  steel  rein- 
forcement in  bottom,  frames,  and  deck  was  placed  in  position. 
Particulars  of  the  mixtures  used  are  given  in  Chapter  IX.  The 
bottom,  sides,  and  deck  were  concreted  in  a  continuous  operation. 
Thereafter  the  transverse  bulkheads,  internal  walls  for  water 
tanks,  galley,  lamp-room,  etc.,  were  built  by  plastering  cement 
mortar  on  a  metal  mesh  with  an  auxiliary  reinforcement  of 
round  bars  horizontally  and  vertically.  Steel  dowels  were 
inserted  in  bottom  and  side  frames  while  these  were  being  con- 
creted and  recesses  provided  for  the  anchorage  of  the  transverse 
bulkheads  to  the  hull ;  this  arrangement  has  proved  satisfactory 
as  there  have  been  no  cracks  observed  between  the  bulkheads 
and  the  frames. 

Equipment. — The  deckhouses  were  made  of   wood.     Outside 


THE   FIRST  SEAGOING  CONCRETE   SHIP          15 

fenders  and  bilge  keels  of  oak  were  bolted  to  the  concrete  hull, 
|  inch  diameter  bolts  having  been  embedded  in  the  concrete 
beforehand.  The  hatch  coamings  were  protected  against  chipping 
by  steel  beams  of  channel  section  along  the  upper  edges,  the 
webs  of  the  channels  being  upwards.  Wood  ceiling  2J  inches 
thick  was  fitted  on  top  of  the  inner  bottom,  and  wood  sparring 
along  the  faces  of  the  transverse  frames  ;  see  Fig.  3. 

Officers'  quarters,  galley,  etc.,  were  located  in  the  deckhouse, 
and  the  crew's  quarters  under  the  deck  forward.  A  5  H.P. 
motor  winch  was  arranged  on  deck  near  the  main  hatch,  and 
the  remaining  equipment  was  similar  to  that  on  any  other  ship 
of  the  size.  In  order  to  save  weight  open  rails  were  fitted  along 
the  sides  rather  than  bulwarks. 

Launching. — The  ship  was  built  on  a  platform  consisting  of 
removable  shuttering  which  acted  as  forms  for  the  bottom. 
The  platform  was  fitted  on  rollers,  and  when  the  hull  was  prac- 
tically finished  the  platform,  together  with  the  ship,  was  pulled 
by  an  electric  winch  on  to  a  steel  launching  car.  When  the  ship 
was  on  the  launching  car  the  propeller,  shaft,  and  rudder  were 
shipped,  and  everything  was  ready  for  the  launch  on  25th  July. 

The  first  attempt  at  launching  was  unsuccessful  owing  to  the 
car  jumping  the  track,  due  to  the  flanges  of  the  wheels  being 
shorn  off.  The  second  attempt  was  also  a  failure  owing  to 
settlement  of  the  foundation  piles  of  the  slipway  after  the 
launching  car  and  ship  had  been  lifted  back  into  place.  Applica- 
tion was  then  made  for  the  use  of  the  floating  crane  belonging 
to  the  Norwegian  Navy.  The  crane  was  anchored  alongside  the 
slipway,  three  wire  strops  were  placed  round  the  ship,  and  the 
Namsenfjord  was  lifted  in  the  air  and  lowered  into  the  water  on 
the  morning  of  2nd  August  1917. 

Trials. — A  couple  of  days  after  launching  the  machinery  was 
installed,  and  on  5th  August  the  engine  was  tried  while  the  ship 
was  tied  to  the  wharf.  Everything  went  well  and  on  the  follow- 
ing day  a  private  trial  was  made  by  the  author  on  the  Sound 
at  Moss. 

On  8th  August  the  Namsenfjord  went  on  her  official  trial 
with  the  Director  of  Shipping,  his  Chief  Engineer,  and  several 
consultants  on  board.  A  southerly  gale  was  blowing  in  the 
Christianiafjord  which  set  up  a  heavy  sea  and  so  gave  a  good 
opportunity  to  test  the  ship  for  seaworthiness,  strength,  and 


16        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

general  behaviour.  The  ship  was  light  during  the  trial,  which 
lasted  four  hours  and  was  entirely  successful.  The  pilot  in 
charge  expressed  his  great  satisfaction  with  the  ship,  particularly 
in  regard  to  her  easy  movements,  slight  vibration,  and  steady 
steering  when  going  into  a  head  wind  and  a  heavy  sea.  The 
average  speed  was  7J  miles  per  hour  ;  it  was  found  later  that 
the  speed  when  loaded  was  rather  over  7  miles  per  hour.  After 
the  first  few  moments  there  was  no  nervousness  on  board  in 
regard  to  the  seaworthiness  of  the  ship  ;  and  the  confidence 
gained  will  be  appreciated  when  it  is  realized  that  the  permit 
for  the  construction  stipulated  that  the  trials  should  take  place 
in  "  enclosed  waters  where  waves  are  entirely  shut  out." 

Docking  for  Inspection.  — Official  comments  were  received 
from  the  Director  of  Shipping  as  a  result  of  his  inspection  during 
the  trial.  Equipment  and  life-saving  apparatus  were  slightly 
improved.  But  before  a  certificate  for  coasting  service  could 
be  granted  various  trial  trips  with  cargoes  of  stone,  sand,  or 
lumber  had  to  be  made. 

On  31st  August  the  Namsenfjord  received  her  first  cargo,  of 
flour,  at  Moss  and  delivered  it  at  Skien.  A  couple  of  minor 
leaks  were  discovered  during  the  loading,  and  when  the  ship 
returned  the  Director  of  Shipping  ordered  her  to  be  docked  for 
inspection.  On  10th  September  the  ship  was  inspected  by  the 
Director  of  Shipping  and  assistants  and  by  the  Concrete  Ship 
Committee.  The  report  of  the  Committee  stated  that  the 
inner  bottom  hindered  inspection,  also  that  some  fine  hair- 
cracks  of  the  usual  type  appeared  in  the  concrete,  but  that 
these  were  only  in  the  surface  and  were  not  considered  to 
jeopardize  the  strength  of  the  ship.  Leaks  in  the  fore  peak  and 
crew's  quarters  were  made  tight  and  the  peak  tank  tested  under 
water-pressure  ;  the  leaks  were  due  to  faulty  work  when  placing 
bolts  for  the  oak  fenders  on  the  stem. 

Subsequent  to  the  inspection  the  ship  made  several  trips  with 
cargoes  between  Moss  and  Drammen.  On  6th  October  an 
official  Certificate  of  Seaworthiness  was  issued,  and  a  load-line 
assigned  ;  the  certificate  was  valid  for  one  month. 

During  the  war  there  was  a  shortage  of  fuel  oil  in  Norway, 
and  the  Namsenfjord,  like  other  motor-ships,  was  forced  to  lie  up 
for  a  while  until  oil  bunkers  were  again  procurable,  when  the 
ship  was  put  into  the  coasting  trade  in  southern  Norway  and 


THE  FIRST  SEAGOING  CONCRETE  SHIP          17 

afterwards  to  Namsos.     At  present  she  is  carrying  lumber  on 
the  northern  coast  of  Norway. 

The  following  weights  were  noted  when  the  ship  was  com- 
pleted : 

Tons. 

Weight  of  hull 134 

equipment  ....        32 
engine  .          .          .          .          8 

Light  displacement       .          .          .          .174 
Deadweight  .          .          .          .          .182 

Load  displacement        .          .          .          .356 


Results  of  Experiment. — Generally  speaking  the  Namsenfjord 
was  a  successful  experiment.  She  proved  that  the  problem  of 
building  a  seagoing  concrete  ship  propelled  by  engines  was  a 
practical  proposition. 

It  is  obvious  that  in  a  first  attempt  of  this  kind  experience  is 
gained  from  which  details  can  be  improved  and  errors  avoided 
in  subsequent  ships  ;  the  following  are  typical  instances  : 

(a)  Deckhouses  of  wood  are  not  satisfactory,  since  the  joint 
between  the  concrete  coaming  and  the  wood  wall  is  never  tight. 
Outside  walls  should  therefore  be  of  concrete. 

(b)  Steel  capping  on  the  top  of  the  hatch  coaming,    as  in 
Namsenfjord,   is  expensive  and  difficult  to  fit ;    wood  capping 
should  be  used. 

(c)  The  corners   of  the  main  hatch  should  be  rounded  or 
bevelled  and  specially  reinforced.     No  weakness  was  shown  on 
Namsenfjord,   but  this  is  an  exposed  detail  on  all  ships,   and 
sharp  corners  should  be  avoided  in  concrete  construction. 

(d)  A  double  bottom  should  not  be  arranged,  at  least  in  small 
and  moderate-size  ships,  since  it  increases  weight,  complicates 
piping,  and  hinders  inspection  of  the  outer  bottom. 

(e)  Wood  packing  should  be  fitted  between  the  engine  bed- 
plate and  the  concrete  foundation  girders  ;    this  may  be  about 
two  inches  thick,    that  is,    considerably  less  than   adopted  in 
Namsenfjord. 

(/)  Double  metal  mesh  for  walls  is  not  desirable  ;   it  is  better 
to  use  only  one  layer  of  metal  mesh,  the  concrete  mortar  being 
plastered  on  up  to  three  inches  in  thickness.     Additional  rein- 
2 


18        SEAGOING  AND   OTHER   CONCRETE    SHIPS 

forcement  of  round  or  square  bars  may  be  wired  to  the  mesh 
as  required. 

(g)  Gravel,  even  of  |  inch  size,  should  not  be  used  in  concrete 
or  mortar  for  vertical  walls  in  small  ships  ;  it  prevents  the 
mortar  from  properly  surrounding  the  steel  reinforcement,  and 
frequently  jumps  out  when  mortar  is  thrown  from  a  trowel  on 
to  a  metal  mesh.  Since  concrete  containing  gravel  is,  however, 
stronger  and  cheaper  than  mortar  containing  only  cement  and 
sand,  it  should  be  used  in  bottom  and  deck  where  the  concrete 
is  poured  over  surfaces  which  are  nearly  level. 


CHAPTER    III 
M.S.    8TIER    AND    M.S.  A8KELAD 

Negotiations — M.S.  Stier— Strength  Calculations — Constructional  Details — 
Construction — Official  Trials — M.S.  Askelad — Constructional  Details — Official 
Trials — The  First  North  Sea  Trip — Subsequent  Service — Summary  of  Results. 

Negotiations. — During   the   spring   of    1917   the   author   had   a 
number   of  interviews   with  the  Director   of   Shipping   on  the 
subject  of  the  construction  of  further  seagoing  concrete  ships, 
and  requested  permission  to  proceed  without  waiting  on  the 
investigations    of   the    Technical    Committee    which    had    been" 
appointed  by  the  Department  of  Shipping.     The  matter  was 
raised  with  the  Prime  Minister  and  eventually,  following  upon 
a  conference  called  together  by  the  Minister  of  Shipping  and 
Commerce  at  which  the  Director  of  Shipping,  the  members  of 
the  Technical  Committee,  and  the  author,  amongst  others,  were 
present,  permission  was  granted  for  the  construction  of  one  ship 
of    600   tons    deadweight   carrying   capacity   and    one    ship    of 
1,000   tons   deadweight   carrying  capacity.     The   permits   were 
granted   on   condition   that   the   author   assumed   all   financial 
responsibility,   and  it  was  stipulated  that  the  ships  should   be 
designed  to  have  20  per  cent,  more  strength  than  the  author 
would  ordinarily  consider  sufficient  on  the  basis  of  his  calcula- 
tions, and  that  they  should  be  particularly  well  equipped  with 
pumps  and  life-saving  appliances  ;    it  was  stipulated  also  that 
the  ships  should  be  tested  in  smooth  water  before  proceeding 
to  sea,  and  that  they  should  make  several  trips  on  the  open 
sea  accompanied  by  escorting  ships  before  being  granted  per- 
mission  to   enter   the   North   Sea   and   Coasting   Trades.     The 
Technical  Committee  Accepted  no  responsibility  for  the  behaviour 
of  the  ships,  but  desired  to  be  kept  informed  as  to  the  experience 
gained  with  them. 

The   permits   for   the   construction   having    been    obtained, 
negotiations  were  commenced  with  a  view  to  finding  purchasers 

19 


20        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

for  the  ships.  As  in  the  case  of  the  Namsenfjord  this  was  not 
an  easy  matter,  as  there  were  prejudices  to  be  overcome.  But 
on  8th  May  1917  a  contract  was  completed  with  Mr.  Gunnar 
Brekke,  of  Christiania,  for  the  1,000-ton  ship,  and  on  23rd  May 
a  contract  was  completed  with  Mr.  G.  M.  Bryde,  of  Christiania, 
for  the  600-ton  ship.  For  each  ship  a  fixed  price  was  arranged 
for  the  reinforced  concrete  hull  ;  all  other  work,  including  the 
machinery  installation,  was  to  be  carried  out  on  the  basis  of 
actual  cost  plus  a  percentage  for  profit.  For  the  1,000-ton 
ship  the  fixed  price  for  the  hull  was  kr.  200,000  (about  £11,000)  ; 
for  the  600-ton  ship  the  corresponding  price  was  kr.  118,000 
(about  £6,500). 

M.S.  "  Stier."  —  This  ship  is  a  cargo  carrier  of  the  flush-deck 
type  ;   the  main  particulars  are  : 

Length  over-aU      .....  145'  0" 

Length  between  perpendiculars        .          .  140'  0" 
Breadth  over  concrete   .          .          .          .         27'  6" 

Depth  ......         15'  9" 

Contract  deadweight  (including  bunkers)  600  tons 

Capacity  of  oil  fuel  tanks      ...  20  tons 
Capacity  of  freshwater  tanks           .          .         5  tons 

Engine,  Bolinder  crude  oil  motor  .          .  320  B.H.P. 
Block  coefficient    .          .          .          .          .         0-77 

Tonnage,  gross       .....  462-03 

nett          .....  258-44 


Capacities  of  holds  : 

Fore  hold  .....     15,010  16,341 

After  hold           .          .          .          .14,608  16,027 

Hatches      .....       1,560  1,590 


31,178          33,958 

The  general  arrangement  is  shown  in  Fig.  6.  It  was  originally 
intended  to  build  a  double  bottom,  but  as  the  result  of  experi- 
ence with  the  Namsenfjord  this  intention  was  discarded.  Water 
ballast  amounting  to  40  tons  can  be  carried  in  the  fore  peak  ; 
the  after  peak  can  be  used  as  a  trimming  tank.  The  forecastle 
is  raised  about  four  feet  above  the  main  deck,  and  has  concrete 
bulwarks.  Open  rails  are  fitted  at  the  ship's  sides  between  the 


M.S.    STIER  AND   M.S.   ASKELAD 


21 


forecastle  and  the  steel  bulwarks  arranged  in  way  of  the  deck- 
house aft.  The  deckhouse  contains  accommodation  for  the 
officers  and  crew,  11  men  in  all.  The  fuel  and  lubricating  oil 
are  carried  in  three  steel  tanks.  The  fresh  water  is  carried  in 
concrete  tanks  arranged  in  way  of  the  engine-room. 

Strength  Calculations.  — In  the  building  permit  granted  by 
the  Government  it  was  stipulated  that  the  ship  should  be  designed 
to  have  20  per  cent,  more  strength  than  the  author  would 
ordinarily  consider  sufficient.  In  order  to  determine  the  standard 
of  strength  the  author  worked  out  according  to  the  rules  of 


FIG.   6. — M.S.  Stier,  600  tons  deadweight.     Capacity  Plan. 

Norske  Veritas  the  sizes  of  frames,  beams,  etc.,  for  a  steel  ship 
of  the  same  type  and  dimensions  as  Stier.  For  these  members 
of  the  structure  moments  of  inertia  and  resistance  were  calculated 
in  the  ordinary  manner.  These  calculated  values  were  then 
increased  by  20  per  cent,  and  the  resulting  figures  used  as  the 
standards  of  strength  for  the  reinforced  concrete  members.  In 
calculating  the  strengths  of  the  reinforced  concrete  members 
the  permissible  working  stresses  were  taken  to  be  15,000  Ib.  per 
sq.  inch,  tension  in  steel,  and  750  Ib.  per  sq.  inch,  compression 
in  concrete.  The  methods  of  making  these  calculations  are 
discussed  in  Chapter  XI. 


22        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

The  desire  was,  of  course,  to  build  the  ships  as  light  as  possible  ; 
but  it  was  appreciated  that  nothing  could  be  more  harmful  to 
the  development  of  concrete  shipbuilding  than  lack  of  strength 
in  the  first  ships. 

Constructional    Details.  —  The    structural    arrangements    are 


FIG.  7. — M.S.  Stier  on  official  trial,  7th  May  1918. 

indicated  in  Fig.    8.     The  sizes  of  the  main  members   are  as 
follow  : 

Item.  Depth.          Width. 

Deck  beams      ....         8"-12"     X  6" 
Side  frames  .       11"-14J"  x  6" 


18"-24" 

28" 
3  J' '-4" 


x  sy 

X  8J' 


Bottom  frames 

Keelson    .... 

Deck  slabs 

Side  slabs          .  .          .          .         4"-4J" 

Bottom  slabs    ....  4" 

The  frame  spacing  is  4'  0". 

The  bottom  frames  are  wider  than  the  side  frames  ;    the 
extra  width  was  added  on  one  side  in  order  to  simplify  the 


M.S.    8TIER  AND   M.S.   A8KELAD 


23 


centring.  The  side  slabs  were  increased  in  thickness  in  the 
regions  of  the  quarter  lengths  where  the  maximum  shear  was 
expected.  The  deck  slabs  were  increased  in  thickness  towards 
the  sides. 

A  longitudinal  stringer,   of  concrete   14J"  X  4",  is  arranged 


LONG  ITU  D.     SECTION 
NEAR.      K.E.EL5ON 


FIG.  8. — M.S.  Stier.     Midship  Section. 

above  the  bilge  at  the  top  of  the  wood  flooring.  The  bilge  keels 
are  of  concrete,  of  triangular  section  7"  X  1"  rounded  to  about 
3"  at  the  outside  ;  the  steel  for  these  was  placed  before  the 
hull  was  concreted,  but  the  concreting  was  done  after  the  bottom 
forms  were  removed. 

The  hatch  coamings  are  of  concrete  29"  X  8",  heavily  rein- 


24        SEAGOING  AND   OTHER  CONCRETE   SHIPS 


forced,  and  run  continuously  from  the  fore  hatch  to  the  deck- 
house  aft.      The  tops   of  the   coamings   are  protected  by  oak 


capping  5"  thick.     Between  the  hatches  the  deck  is  raised  to 
near  the  top  of  the  coaming. 

The  steel  reinforcement  is  of  round  rods  J"  to  1J"  diameter, 
the  size  and  disposition  of  the  principal  bars  being  shown  in  Fig.  8. 


M.S.    STIES  AND   M.S.   ASKELAD 


25 


The  longitudinal  reinforcing  rods  are  not  spliced  by  welding 
or  directly  connected  in  any  other  way.  The  rods  are  merely 
placed  alongside  each  other  with  the  ends  overlapping  for  a 
length  of  24  diameters  ;  a  90  degree  hook,  five  diameters  long, 
is  made  at  each  end  of  each  rod.  In  this  manner  it  is  arranged 
that  the  tensile  forces  shall  be  transmitted  by  means  of  the 
bond  between  the  concrete  and  the  steel.  The  overlaps  of  the 
rods  are  distributed  uniformly  throughout  the  ship.  The  rods 
are  spaced  about  one  diameter  apart  (in  the  overlap)  in  order 
to  allow  of  sufficient  concrete  being  poured  between  them. 


TRAN5V.     SECTION      NEAR.    BULKHEAD 
LOOKING    FORWARD 

FIG.   10. — M.S.  Stier.     Engine-room  Arrangement. 

In  all,  58  tons  of  steel  were  used  in  the  construction  of  M.S. 
Stier. 

The  arrangement  of  stern  post  is  similar  to  that  in  the 
Namsenfjord,  only  heavier  ;  it  is  shown  in  Fig.  9. 

The  arrangement  of  the  engine  seating  is  also  shown  in  Fig.  9, 
and  follows  the  lines  of  that  in  the  Namsenfjord,  except  that  in 
the  Stier  the  oak  packing  under  the  bed-plate  is  only  two  inches 
thick. 

The  arrangement  of  the  engine-room  is  shown  in  Fig.  10. 
The  freshwater  tanks  are  of  concrete,  and  on  top  is  arranged  a 
steel  fuel  storage  tank.  On  the  starboard  side,  mounted  on 
concrete  bearers,  are  another  steel  fuel  storage  tank,  a  daily 
use  fuel  tank,  and  a  lubricating  oil  tank.  On  the  port  side  is 


26        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

a  5  B.H.P.  motor  pump  connected  to  all  the  pipe  lines  ;    the 
repair  bench  and  tools  are  also  arranged  on  the  port  side. 

An  oak  fender,  5"  X  1",  is  fitted  around  the  hull  at  the  deck 
level.  A  similar  fender,  protected  by  J"  steel  plate,  is  bolted 
to  the  concrete  stem. 

The  walls  of  the  engine  casing,  also  the  walls  of  galley,  w.c., 
and  lamp-room  are  of  concrete. 

The  navigating  bridge  has  wood  planking  on  steel  beams. 

A  5  B.H.P.  motor  winch  of  1J  tons  lifting  capacity  is  fitted 
at  each  hatch.  The  capstan  is  arranged  for  hand-power,  but 
can  be  driven  by  a  messenger  chain  from  the  forward  winch. 
The  steering  gear  is  arranged  for  hand-power  only.  The  bollards 
and  fairleads  are  secured  to  the  deck  by  heavy  bolts  having 
steel  washers  underneath.  The  deck  is  increased  in  thickness 
under  all  fittings. 

The  chain  pipes  are  of  cast  iron,  and  the  concrete  sides  are 
increased  in  thickness  and  have  additional  reinforcement  where 
the  chain  pipes  come  through.  In  order  to  provide  against 
abrasion  by  the  anchors  an  outside  finish  of  cement  and  iron 
powder,  one  inch  thick,  was  applied  from  the  stem  to  a  short 
distance  abaft  the  chain  pipes  ;  this  can  be  seen  in  Fig.  7.  The 
extra  cement  finish  was  found  to  be  unnecessary  and  has  not 
been  adopted  in  later  ships. 

Construction.  — The  Stier  was  constructed  on  a  platform  of 
wood  sheeting  supported  on  timbers  across  the  launching  ways. 
Double  centring  was  used.  For  the  exterior  centring  vertical 
templates  shaped  to  the  lines  of  the  ship  were  erected  on  the 
wood  platform,  the  spacing  being  generally  about  three  feet, 
but  closer  than  this  towards  the  ends  of  the  ship.  The  centring 
was  of  f"  boards  nailed  to  these  templates. 

Before  the  concreting  was  started  all  the  reinforcement  was 
in  position,  also  all  the  centring  with  the  exception  of  the  inside 
forms  for  the  side  slabs,  which  were  left  open  to  facilitate  con- 
creting. As  the  concrete  worked  upwards  the  interior  centring 
was  put  in  place  ;  thus  the  concrete  was  worked  around  the 
reinforcement  at  every  level. 

The  mixture  of  the  concrete  was  approximately 

1  part  cement  :  1  f  parts  sand  :  f  part  gravel. 
This  showed  an  average  ultimate  compressive  strength  of  about 
4,500  Ib.  per  sq.  inch  at  28  days. 


M.S.    8TIER  AND   M.S.   ASKELAD  27 

The  ship  was  successfully  launched  on  llth  March  1918, 
and  was  ready  for  trial  seven  weeks  later. 

Official  Trials.  — On  7th  May  M.S.  Stier  went  through  her 
first  official  trial,  which  was  successful. 

After  preliminary  trips  in  the  Christianiafjord  the  ship  went 
to  Skien  and  on  with  a  cargo  of  saltpetre  to  Stavanger  and 
Bergen,  thence  to  Aalesund,  and  back  with  a  cargo  of  limestone 
to  Fredrikshald.  This  was  a  heavy  cargo  and  the  ship  en- 
countered a  severe  gale  with  a  -rough  sea  at  the  exposed  part  of 
the  coast.  According  to  statements  by  the  captain  and  pilot 
the  weather  was  so  rough  that  other  ships  of  similar  size  refused 
to  put  to  sea.  This  trip  was,  therefore,  a  decisive  test  of  the 
seaworthiness  and  strength  of  the  ship. 

From  the  report,  covering  a  month,  of  the  Government 
Inspector  who  accompanied  the  ship  it  appears  that  the  pumps 
were  not  used  at  all,  as  the  ship  proved  to  be  absolutely  tight. 

Following  on  these  trials  the  ship  was  docked  on  7th  June 
at  Moss  Verft  for  official  inspection  by  the  Director  of  Shipping, 
the  Chairman  of  the  Technical  Committee  on  Concrete  Ships, 
the  consultants  of  the  owners,  and  other  officials.  The  ship 
was  found  to  be  in  excellent  condition  without  any  signs  of 
weakness  in  the  concrete  hull,  and  a  certificate  of  seaworthi- 
ness was,  therefore,  issued  by  the  Director  of  Shipping  for 
one  year. 

The  speed  of  the  Stier  is  8  knots  loaded  and  about  8-6  knots 
light. 

M.S.  "  Askelad." — This  ship  is  a  cargo  carrier  of  the  flush- 
deck  type  ;  the  main  particulars  are  : 

Length  over-all      .          .          .          .176'  0" 

Length  between  perpendiculars        .  170'  0" 

Breadth  over  concrete   .          .          .  31'  0" 

Depth 19'  0" 

Contract    deadweight    (including 

bunkers)           ....  1,000  tons 

Capacity  of  oil  fuel  tanks       .          .  30  tons 

Capacity  of  freshwater  tanks           .  7  tons 
Engines,     two    Bolinder    crude    oil 

motors 320  B.H.P.  total 

Block  coefficient  0-77 


28        SEAGOING  AND   OTHER   CONCRETE  SHIPS 

Tonnage,  gross       .          .          .          .      758-88 
nett        ....      422-55 
Capacities  of  holds  : 

Bale.  Grain, 

cub.  ft.  cub.  ft. 

Fore  hold             .          .          .              22,600  25,000 

After  hold           .          .          .               21,600  24,000 

Hatches                                                     1,800  1,800 


46,000          50,800 

The  general  arrangement  of  the  ship  is  shown  in  Fig.  11. 
The  deckhouse,  containing  accommodation  for  13  men,  has  the 
external  walls  of  concrete  and  the  internal  divisions  of  wood 
The  roof  of  the  house,  forming  the  navigating  bridge,  is  of 
wood  on  steel  beams.  The  fore-peak  ballast  tank  is  of  60  tons 
capacity. 

The  actual  strength  calculations  are  given  in  the  Appendix, 
and  they  are  discussed  in  Chapter  XI. 

Constructional  Details.  —  The  structural  arrangements  are 
indicated  in  Fig.  12.  The  sizes  of  the  main  members  are  as 
follow  : 

Item.  Depth.       Width. 

Deck  beams      .          .          .          .  12"       X  6J" 

Side  frames       .          .          .          .  13"- 17"  X  6J" 

Bottom  frames           .          .          .  22"-28"  X  10" 

Keelson 32"        x  11" 

Deck  slabs        ....  3J"-4J" 

Side  slabs          ....  4"-4J"-5i"-6" 

Bottom  slabs  4" 
The  frame  spacing  is  4'  0". 

The  structural  arrangements  are  generally  similar  to  those 
in  the  Stier. 

The  reinforcement  is  arranged  in  a  similar  manner  to  that 
in  the  Stier ;  square  "  rib  "  bars  were,  however,  used  exten- 
sively. In  all,  105  tons  of  steel  were  used. 

The  arrangement  of  the  stern  post  is  very  simple,  on  account 
of  the  ship  having  twin  screws.  The  propeller  brackets  are 
riveted  to  a  vertical  I-beam  embedded  in  the  concrete  stern  post. 
The  rudder  post  is  of  cast  steel  with  flanges  riveted  on,  and  is 


uJ 
u 


Q 
O 


t 

Q 


g 
^r 


00 


Ik 


"en, 


29 


30        SEAGOING  AND   OTHER  "CONCRETE    SHIPS 

secured  in  the  same  manner  as  the  slorn  post  in  Namsenfjord. 
Details  of  these  arrangements  are  shown  in  Fig.  13. 

The  stern  tubes  are  of  cast  steel,  lined  with  cast  iron,  with 


%"<>  NEAR. 

'OUTER.  FACE. 


REINFORCEMENT    IN  SIDES 
SEEN     FROM     OUTSIDE. 


REINFORCEMENT    IN    BOTTOM 

5EEN    FROM   ABOVE.  IN  KEE.LSON 

HI"-!/ 


BOTH  WAYS 


FIG.   12.—  M.S.  Askelad.     Half  Midship  Section. 


flanges  to  take  anchor  bolts  ;  longitudinal  ribs  are  arranged 
on  the  tubes  to  provide  additional  anchorage.  Casings  of  steel 
plate  for  the  protection  of  the  propeller  shafts  are  fitted  between 
the  propeller  brackets  and  the  stern  tubes.  Lubrication  is 
provided  for  the  inner  ends  of  the  tubes. 


M.S.    STIER  AND   M.S.    ASKELAD 


31 


The  engine  seatings  are  similar  to  those  in  the  Stier,  but  on  a 
smaller  scale  because  of  the  lower  power  of  each  engine  as  com- 
pared with  that  in  the  Stier. 


The  arrangement  of  the  engine-room  is  shown  in  Fig.  13. 
The  freshwater  tanks  are  of  concrete,  and  on  top  are  the  oil  fuel 
storage  tanks,  of  steel.  The  daily  use  tank  and  the  lubricating 


32 


M.S.    STIER  AND   M.S.   A8KELAD  33 

oil  tank  are  arranged  at  the  sides  ;  these  also  are  of  steel.  The 
motor  pump  is  of  5  B.H.P. 

The  deck  machinery  and  fittings,  also  the  fenders,  are  similar 
to  those  on  the  Stier. 

The  arrangement  of  centring  and  the  general  method  of 
construction  were  the  same  as  for  the  Stier.  The  mixture  of 
the  concrete  was  not  constant ;  an  average  was 

1  part  cement  :  1-8  parts  sand  :  0-7  part  gravel 

This  showed  an  ultimate  crushing  strength  of  more  than  4,000  Ib. 
per  sq.  inch  at  28  days. 

No  extra  finish  with  iron  powder  was  applied  in  way  of  the 
chain  pipes  ;  the  ships'  sides  were  increased  in  thickness  about 
1 J  inches  on  the  inside  and  additional  reinforcement  fitted. 

The  Askelad  was  launched  on  8th  June  1917  ;  but  at  that 
date  she  was  called  Oddfrid. 

Official  Trials. — On  21st  August  M.S.  Askelad  went  through 
her  first  official  trial,  which  was  successful.  The  vibration  was 
less  than  in  the  Stier,  which  had  the  same  power,  but  concen- 
trated in  one  engine.  It  was  noted  also  with  satisfaction  that 
the  ship  made  nearly  as  good  a  speed  as  the  Stier  though  having 
75  per  cent,  more  cargo  capacity. 

The  Askelad  carried  out  a  number  of  trials  with  different 
kinds  of  cargoes  on  the  coasts  of  Norway.  The  trials  were 
perfectly  satisfactory  in  so  far  as  the  concrete  construction  was 
concerned,  but  minor  troubles  were  experienced  with  the  engines 
and  various  improvements  in  deck  fittings  and  equipment  sug- 
gested themselves.  During  the  month  of  November  heavy 
weather  was  encountered  by  the  ship  in  the  course  of  her  trials  ; 
on  one  day  a  heavy  sea,  which  broke  over  the  ship,  stove  in 
the  cover  of  the  fore  hatch.  Reports  sent  in  by  the  captain 
and  by  the  Government  Inspector  who  was  on  board  the  ship 
during  these  trial  trips  were  perfectly  satisfactory,  and  both 
call  attention  to  the  fact  that  it  was  not  necessary  to  use  the 
pumps  at  all  during  any  of  the  rough  weather. 

Following  on  these  trial  runs  the  Askelad  was  docked  at  the 

end  of  November  for  an  official  inspection.     The  concrete  hull 

was  found  to  be  entirely  satisfactory,  and  so  on  10th  December 

1918  the  Director  of  Shipping  issued  a  certificate  of  seaworthiness 

3 


34 


M.S.   STIEti  AND  M.S.   ASKELAD 


35 


for  M.S.  Askelad  for  one  year,  permitting  the  ship  to  engage  in 
North  Sea  and  Baltic  trading. 

Before  the  Askelad  was  completed  the  author  had  been 
engaged  in  negotiations  with  the  Government  with  a  view  to 
obtaining  a  permit  for  a  trans- Atlantic  voyage.  The  Minister 
of  Shipping  and  Commerce  requested,  however,  that  the  matter 
be  left  over  until  the  ship  had  carried  out  trials  with  different 
cargoes  and  had  crossed  the  North  Sea.  Unfortunately,  by  the 


FIG.  16.— M.S.  Askelad  with  Staal-Beton  19,  the  First  Concrete  Tug,  alongside. 

time  the  various  trials  had  been  carried  out  the  owners  had 
fixed  up  a  number  of  charters  for  the  ship  which  ruled  out  the 
possibility  of  an  Atlantic  trip. 

The  First  North  Sea  Trip. — On  llth  December  1918  the 
Askelad  sailed  from  Christiania  for  Rouen,  where  she  arrived 
on  the  23rd  December.  The  cargo  was  6,941  bales  of  wood  pulp, 
weighing  normally  892  tons,  but  actually  more,  as  the  bales  had 
been  lying  exposed  since  the  month  of  June  and  were  wet  through. 
On  the  passage  the  ship  had  three  days  of  very  stormy  weather — 


36        SEAGOING  AND   OTHER  CONCRETE   SHIPS 

a  westerly  gale  with  a  heavy  sea — and  a  few  bales  of  the  deck 
cargo  were  washed  overboard.  This  was  the  first  crossing  of 
the  North  Sea  by  a  concrete  ship. 

Subsequent  Service. — After  her  first  trip  across  the  North 
Sea  the  Askelad  was  engaged  trading  with  all  kinds  of  cargoes 
to  various  Norwegian,  British,  Dutch,  and  Swedish  harbours. 
Occasional  trips  were  made  in  the  Baltic,  where  the  ice  proved 
troublesome.  During  the  period  of  speculation  in  shipping  the 
ship  changed  hands  several  times,  always  at  a  profit  to  the  last 
owner.  On  the  conclusion  of  one  of  these  transactions  the  new 
owners  asked  for  a  report  on  the  ship  from  the  Captain,  who  had 
been  with  the  ship  since  she  was  built  ;  the  Captain  testified  to 


FIG.   17. — M.S.  AsJc.elad,  on  trial,  llth  August  1918. 

her  general  seaworthiness,  to  her  steering  qualities,  and  to  her 
low  cost  of  upkeep.  Fig.  18  will  indicate  that  the  Askelad  was 
put  to  hard  service  ;  it  shows  her  at  Gravesend  with  a  cargo, 
including  deck  load,  of  wood  pulp.  The  weather  on  the  trip 
across  the  North  Sea  from  Gothenburg  was  very  bad  and  the 
deck  cargo  was  shifted,  bending  and  tearing  up  some  of  the  rails 
and  stanchions  on  the  deck.  A  further  indication  of  the  hard 
service  performed  by  the  Askelad  is  given  in  Chapter  VII. 

On  9th  September  1919  the  Askelad  was  again  docked  for 
an  official  inspection.  Cracks  were  discovered  in  four  deck 
beams,  and  they  were  chiselled  open  for  inspection  ;  they  were 
found  to  be  only  J"-l"  deep,  and  were  merely  filled  up  again 
with  cement.  The  concrete  of  the  hull  was  hammered  all  over, 


38        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

and  the  bottom  in  the  engine-room  was  cleaned  of  oil,  scraped, 
and  chiselled  open  in  places  for  inspection  ;  there  were  no  signs 
of  the  concrete  being  attacked  by  oil  nor  was  any  sign  of  weak- 
ness found.  Accordingly  a  certificate  of  seaworthiness  was  issued 
for  a  further  year. 

The  following  data  for  Askelad  are  of  interest : 

Tons. 

Weight  of  reinforced  concrete  hull  .  733 

„           equipment         .          .  .  120 

„           machinery         .          .  .  31 

Displacement,  light             .          .  .  884 

Deadweight,  freeboard  2'  6J"    .  .  1,036 

Displacement,  loaded         .          .  .  1,920 

The  freeboard  of  2'  6J"  required  by  the  Director  of  Shipping 
is  only  temporary  ;  it  is  3  J"  more  than  would  be  required  for 
a  steel  ship  of  the  same  type  and  dimensions  as  Askelad.  During 
her  official  trials  the  Askelad  was  actually  loaded  down  to  a  free- 
board of  2'  3",  and  carried  a  cargo  of  1,050  tons  ;  making  an 
addition  for  bunkers,  fresh  water,  provisions,  etc.,  the  dead- 
weight with  2'  3"  freeboard  amounts  to  about  1,090  tons. 

The  Askelad  is  continuously  engaged  in  Baltic,  North  Sea. 
and  Channel  trade,  the  owners  being  Messrs.  A.  I.  Langfeldt  & 
Co.,  Christiansand. 

It  is  difficult  to  obtain  information  about  the  Stier,  now 
known  as  the  Aliakmon,  for  she  was  sold  to  Greece,  first  to  E.  D. 
Papayannis  and  then  to  another  owner ;  at  present  she  is 
employed  in  Mediterranean  and  Red  Sea  service.  The  last 
Norwegian  captain  of  the  Stier,  who  was  also  for  a  time  captain 
of  the  Namsenfjord,  has  reported  very  favourably  on  her,  calling 
attention  particularly  to  the  low  cost  of  upkeep. 

Summary  of  Results. — These  trial  ships  have  now  been  con- 
tinuously in  service  for  fully  three  years,  and  the  experience 
gained  with  them  demonstrates  that  concrete  ships  possess 
valuable  qualities  with  which  they  were  not  originally  credited. 
Two  features  are,  above  all  others,  necessary  for  seagoing  ships 
built  of  any  material :  Strength  and  Watertightness.  These  are 
of  prime  importance.  All  the  other  qualities — cost,  deadweight 
capacity,  speed,  running  expense,  cost  of  upkeep — are  matters  of 
secondary  importance,  frequently  affected  by  local  considerations. 


M.S.    STIER   AND   M.S.    ASKELAD  39 

Until  the  Stier  and  the  Askelad  (together  with  the  Namsen- 
fjord)  proved  that  the  seagoing  concrete  ship  possessed  in  full 
measure  the  above  qualities  of  prime  importance  they  were 
thought  to  be  impossible  of  attainment  with  concrete  as  the 
material  of  construction.  A  summary  of  the  results  of  experience 
as  regards  the  "  prime  "  qualities,  and  also  the  "  secondary  " 
qualities,  is  given  below. 

Strength.  — Both  ships  showed  that  the  strength  of  the  concrete 
hull  was  ample.  In  fact,  the  author  believes  that  the  strength 
as  calculated  by  his  methods  could  be  reduced  by  20  per  cent, 
without  danger  of  weakness  ;  if  this  were  carried  out  it  would 
put  concrete  ships  on  an  equality  with  steel  ships  in  the  matter 
of  strength. 

Watertightness. — Both  ships  have  proved  to  be  absolutely 
watertight,  and  are  in  this  respect  superior  to  wood  ships  and 
even  to  many  steel  ships. 

Cost.  M.S.    Stier 

Concrete  hull  only,  without  fittings 

of  any  kind  .  .  .  .  Kr.  118,000  (£6,500) 

All  equipment,  engines,  deck 
machinery,  etc.,  including  in- 
stallation .  .  .  .  Kr.  415,000  (£22,800) 

Total  cost  .          .      Kr.  533,000  (£29,300) 

M.S.    Askelad 

Concrete  hull  only,  without  fittings 

of  any  kind  .  .  .  .  Kr.  200,000  (£11,000) 

AJ1  equipment,  engines,  deck 
machinery,  etc.,  including  in- 
stallation .  .  .  .  Kr.  493,000  (£27,000) 

Total  cost  .          .      Kr.  693,000  (£38,000) 

Cost  per  ton  of  deadweight  : 

Stier          =  Kr.  888  (£49) 
Askelad          =  Kr.  660  (£36) 

The  cost  of  construction  varied  greatly  during  the  war,  and 
so  comparisons  with  costs  for  steel  and  for  wood  ships  can  be 
made  only  between  ships  built  in  the  same  country.  To  the 
best  of  the  author's  knowledge  the  Askelad  was  the  cheapest 


40        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

ship  per  ton  of  deadweight  for  her  size  and  type  built  in  Norway 
during  the  period  1917-20. 

Deadweight  Capacity. — M.S.  Stier  carries  just  the  deadweight 
stipulated  in  the  contract,  namely  600  tons  ;  but  M.S.  Askelad 
carries  1,050  tons,  that  is,  5  per  cent,  more  than  required  by 
the  contract. 

It  should  be  remembered  that,  owing  to  the  increased  size 
of  ship  as  compared  with  a  steel  ship  of  the  same  deadweight, 
the  concrete  ship  has  a  greater  cubic  capacity  per  ton  of  dead- 
weight than  a  steel  ship. 

Speed. — The  Stier  made  8-6  knots  light  and  8-0  knots  loaded 
on  her  trials.  Later  she  showed  a  better  speed.  The  Askelad 
made  a  slightly  better  speed  than  the  Stier,  in  spite  of  her  much 
larger  cargo  capacity.  The  Askelad' s  speed  is  equal  to  that  of 
a  steel  ship  of  the  same  deadweight  carrying  capacity  and  engine 
power.  This  is  contrary  to  expectation  in  view  of  the  heavy 
concrete  hull ;  but  it  can  be  accounted  for  in  part  by  the  smooth- 
ness of  the  concrete  hull — there  are  no  projecting  rivet  heads  or 
overlaps  of  plating — and  the  reduced  skin  friction. 

Running  Expenses  and  Upkeep. — The  same  crew  and  engine 
power  are  employed  in  a  concrete  ship  as  in  a  steel  ship  of  the 
same  cargo  capacity,  and  so  there  is  no  difference  in  the  costs  of 
fuel  and  wages.  The  trial  ships  were  not  painted  either  inside 
or  out,  except  with  coal  tar  or  antifouling  composition  on  the 
bottom  below  the  waterline  to  prevent  marine  growth.  (Experi- 
ence showed  that  it  was  desirable  to  apply  the  antifouling  com- 
position direct  to  the  concrete,  when  the  surface  became  "  as  hard 
as  glass  "  and  lasted  very  well.)  There  was,  therefore,  a  saving 
in  this  respect.  Further,  the  low  first  cost  of  the  ships  as  com- 
pared with  steel  ships  resulted  in  reduced  "  charges  "  for  interest 
on  capital  and  for  depreciation  ;  also  it  was  proved  that  the  costs 
of  repairs  required  by  collisions  or  groundings  were  very  low. 

As  far  as  the  hulls  are  concerned  there  were  many  details 
in  which  improvements  could  have  been  effected.  But  as  the 
slight  defects  noted  were  matters  of  arrangement  or  design, 
and  were  not  in  any  way  due  to  the  material  of  construction, 
they  need  not  be  discussed  here.  As  indicating  a  defect  arising 
out  of  the  material  of  construction,  it  may  be  mentioned  that  it 
was  found  necessary  to  fit  panelling  on  the  inside  walls  of  concrete 
deckhouses  used  for  living-rooms. 


CHAPTER  IV 

COMPARISON  OF  SOME  SHIPS  BUILT  TO  CLASS  WITH 
THE  AUTHOR'S   TRIAL   SHIPS 

Classification  of   Concrete   Ships — Comparative  Values  of  Cargo   Carriers — 
American  Concrete  Ships— S.S.  Selma  and  Latham  ;    S.S.  Cape  Fear  and  Sapona. 

Classification  of  Concrete  Ships.  — Concrete  ships  were  first 
recognized  by  classification  societies  in  September  1917,  when 
Lloyd's  Register  of  Shipping  approved  plans  submitted  by  the 
author  for  several  types  of  seagoing  concrete  motor-ships  and 
barges,  which  were  granted  the  Class  "  Al  for  Scandinavian 
Coasting  Service,"  "Subject  to  annual  survey"  and  subject 
to  the  notation  "  Experimental  "  being  made  in  the  Register 
Book.  At  about  the  same  time  the  Norwegian  Veritas  were 
preparing  their  "  Provisional  Rules  for  Classification  of  Concrete 
Ships."  This  recognition  was  of  the  first  importance  and  was 
partly  due  to  the  success  of  M.S.  Namsenjjord,  which  a  month 
previously  by  practical  demonstration  had  furnished  indisputable 
proof  of  the  strength  and  seaworthiness  of  the  Seagoing  Concrete 
Ship. 

Class  is  to  a  ship  what  a  report  of  good  name  and  standing 
in  the  community  is  to  a  man,  and  it  was  very  important  for 
the  new  type  of  ship  to  secure  even  a  modified  form  of  class  at 
this  early  date.  About  twenty-five  million  tons  of  shipping,  or 
one-half  of  the  world's  entire  tonnage,  have  been  built  according 
to  the  rules  of  Lloyd's  Register  of  Shipping,  and  of  the  remainder 
by  far  the  largest  portion  has  been  built  to  class  in  other  institu- 
tions. Obviously  the  first  rules  for  classification  of  concrete 
ships  could  only  be  of  provisional  character,  pending  further 
practical  experience,  and  they  were  naturally  conservative  and 
"  on  the  safe  side."  On  the  other  hand,  economy  of  materials 
and  labour  in  construction  is  of  the  utmost  importance  for  the 
future  development  of  concrete  ships  in  competition  with  steel 
ships  ;  by  economizing  in  the  material  worked  into  a  ship  the 

41 


42        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

deadweight  carrying  capacity  is  increased,  and  by  economizing 
in  labour  and  materials  the  first  cost  is  kept  down.  The  problem 
is,  therefore,  to  determine  how  little  material  may  be  put  into 
a  ship  without  the  finished  product  showing  signs  of  weakness. 
Having  this  important  point  firmly  in  mind  the  object  of  this 
chapter  is  to  prove  that  concrete  ships  can  safely  be  constructed 


FIG.  19. — M.S.  Patent,  600  tons  deadweight,  built  to  Class  A  1  "Experimental" 
in  Norwegian  Veritas.  The  ship  is  partly  covered  with  ice  while  docking  in 
Christiania. 

much  lighter — with  less  expenditure  of  materials  and  labour — 
than  as  required  at  present  by  classification  societies. 

Comparative  Values  of  Cargo   Carriers. — The  principal  factors 
determining  the  commercial  value  of  a  cargo  carrier  are  : 

Carrying  capacity. 

Speed. 

First  cost. 

Running  expenses. 


CONCRETE  SHIPS   BUILT   TO   CLASS 


43 


For  ships  of  the  same  dimensions  and  outside  shape,  and 
with  the  same  engine  power,  the  speed  and  running  expenses  are 
the  same  and  need  not  be  considered  in  this  comparison.  But 
comparisons  of  carrying  capacities  for  two  different  sizes  of  ships 
are  given  below  ;  they  are  drawn  between  trial  ships  built  by 
the  author's  firm  and  similar  ships  built  by  the  author's  firm 
under  the  regulations  of  the  Norwegian  Veritas  Classification 
Society  : 


Trial  ship    Classed  ship 
Stier.             Patent. 

Trial  ship    Glassed  ship 
Askelad.        Concrete. 

Length  over-all        .... 

145'0"     145'  0* 

176'0"       176'0" 

,,       between  perpendiculars 

140'  0"     140'  0" 

170'  0"       170'  0" 

Breadth            

27'  6"       27'  6" 

31'  0"         31'  0" 

Depth     

15'  9"       15'  9" 

19'  0"         19'  0" 

Freeboard,  loaded    . 

2'  0£"       2'  OJ" 

2'  6J"         2'  1\" 

Block  coefficient 

0-77         0-77 

0-77            0-77 

Cargo  capacity,    /grain     . 

33,960     33,960 

50,800        50,800 

cubic  feet          \bale 

31,180     31,180 

46,000        46,000 

Displacement  in  tons,  light 

565          572 

884         940-5 

Deadweight  in  tons 

610          603 

1,036         972-5 

Displacement  in  tons,  loaded 

1,175       1,175 

1,920          1,913 

Reinforcement  in  hull,  tons 

58             68 

105              120 

Concrete  in  hull,  tons 

394          391 

628             666-5 

Weight  of  hull,  tons 

452          459 

733             786-5 

Engines  (Bolinder  motors),  B.H.P.     . 

320          320 

320             320 

Singlescrew.  Singlescrew. 

Twin  screw.    Twin  screw. 

Speed  in  knots,  light          .           . 

8-6           9-0 

8-6             8-0 

,,            ,,         loaded 

8-0           8-25 

8-0             7-5 

The  slight  differences  in  speed  are  probably  due  to  internal 
causes  in  the  machinery  ;  all  the  ships  built  by  the  author's 
firm  have  shown  increased  speed  after  they  have  been  in  service 
for  a  time. 

The  table  shows  that  the  trial  ships  are  lighter  than  ships  of 
exactly  the  same  dimensions  and  outside  shape  built  to  class. 
And  it  must  be  borne  in  mind  that  the  trial  ships  have  been  proved 
to  possess  ample  strength. 

Turning  now  to  the  question  of  first  cost,  it  was  found  that 
the  unit  costs  of  construction  for  M.S.  Concrete  were  : 

1-0  ton  of  concrete  complete  in  place  and  launched        .   £14     8s. 
1-0       ,,      reinforcement     ,,  ,,  „  „  .   £47  15s. 

These  unit  costs  include  all  materials  and  labour  for  wood 
forms,  scaffolding,  mixing,  handling  and  placing  of  concrete, 
handling  and  placing  of  steel,  also  all  overhead  charges. 


44        SEAGOING  AND   OTHER  CONCRETE   SHIPS 

They  were  worked  out  from  the  actual  cost  figures  obtained 
after  the  construction  was  finished.  The  buying  prices  were, 
for  steel  £32  per  ton  and  for  Portland  cement  £1  7s.  6d. 
per  barrel  delivered  at  the  yard.  The  prices  are  high  owing 
to  war  conditions. 

M.S.  Concrete  and  M.S.  Askelad  were  sister  ships  in  every 
respect  but  the  detail  design  of  the  concrete  hulls  ;  and  as 
shown  in  the  table  above,  the  differences  in  design  involved  in 
the  Concrete  additional  weights  of  38-5  tons  of  concrete  and 


FIG.  20. — M.S.   Concrete,  972-5  tons  deadweight,  built  to  Class  A  1    "  Experi- 
mental "  in  the  Norwegian  Veritas. 

15-0  tons  of  steel.  Adopting  the  unit  costs  given  above  the 
excess  first  cost  of  the  Concrete  as  compared  with  the  Askelad 
amounts  to  : 

38-5  tons  of  concrete  at  £14  Ss.  =  £554 

15-0  tons  of  reinforcement  at  £47  15s.  =  £716 


Total      =  £1,270 

The  cost  of  M.S.  Concrete  complete,  including  engines  and 
equipment,  was  £46  per  ton  deadweight  ;  and,  as  given  above, 
the  deadweight  carrying  capacity  of  the  Concrete  is  63-5  tons 


CONCRETE   SHIPS   BUILT   TO   CLASS  45 

less    than   that   of   the   Askdad.     Expressing   the   reduction  in 
deadweight  in  pounds  sterling  the  amount  is  : 

63-5  tons  at  £46  per  ton  =  £2,921, 

which  may  be  taken  either  as  a  reduction  in  selling  value  or  as 
an  increase  in  first  cost.  Hence  the  total  increased  cost  of  the 
Concrete  as  compared  with  the  Askelad,  an  increase  brought  about 
by  the  classification  requirements  embodied  in  the  Concrete 
amounts  to  £1,270  +  £2,921  =  £4,191.  The  total  cost  of  M.S'. 
Concrete  complete  was  about  £45,000,  so  that  the  increased  first 
cost  amounts  to  9  J  per  cent,  per  ton  deadweight. 

The  increased  first  cost  brought  about  by  classification 
requirements  is  emphasized  if  the  cost  of  the  naked  hull  alone  is 
considered  ;  and  the  differences  between  the  Concrete  and  the 
Askelad  are  only  in  the  hulls — in  machinery  and  equipment  the 
two  ships  are  exactly  alike. 

The  total  cost  of  the  hull  of  M.S.  Concrete  was  £15,000,  which 
represents  £15  8s.  per  ton  deadweight.  On  this  figure  the 
increased  first  cost  corresponding  to  the  reduction  in  deadweight 
amounts  to  63-5  tons  at  £15  Ss.  per  ton,  that  is,  £978.  The  total 
increased  first  cost  of  the  naked  hull  is,  then,  £1,270  -f-  £978 
=  £2,248.  Hence  the  concrete  hull  built  to  class  shows  an  increased 
first  cost  o/15  per  cent,  as  compared  with  a  hull  built  to  the  author's 
design. 

It  should  be  mentioned,  too,  that  the  Concrete  was  built 
exceptionally  light  because  the  Norwegian  Veritas  consented  to 
some  modifications  in  their  provisional  rules  on  account  of  the 
author's  experience  in  building  concrete  ships.  The  difference 
in  favour  of  the  author's  design  is,  therefore,  not  so  pronounced 
as  in  the  examples  given  below,  which  refer  to  ships  built  to 
class  by  others. 

American  Concrete  Ships. — As  further  examples  for  comparison 
are  selected  two  types  of  seagoing  concrete  ships  built  by  the 
U.S.  Shipping  Board — Emergency  Fleet  Corporation — which 
in  January  1918  organized  a  special  Concrete  Ship  Section 
to  deal  with  the  new  type  of  ship.  The  author  is  indebted  to 
the  Engineers  in  charge  of  this  department  for  various  technical 
particulars  of  the  ships.  The  information  as  to  the  actual 
carrying  capacities  of,  and  experience  with,  the  finished  ships 
was  obtained  from  the  American  Fuel  Oil  and  Transportation 


46        SEAGOING  AND   OTHER  CONCRETE   SHIPS 

Company,  Inc.,  of  New  York  City,  who  at  present  own  and 
operate  two  of  the  largest  ships.  The  information  as  to  the 
costs  of  the  completed  ships  is  taken  from  the  reports  of  the 
special  "  Committee  on  Reinforced  Concrete  Barges  and  Ships," 
presented  to  the  conventions  of  the  American  Concrete  Institute 
at  Chicago  in  1920  and  1921.  The  prices  are  for  the  present 
comparison  calculated  per  ton  actual  deadweight: 

All  the  ships  were  built  to  class  in  the  "  American  Bureau  of 
Shipping,"  where  they  received  "Experimental  Class."  The 
author  does  not  know  how  far  the  classification  society  influenced 
the  designs,  but  during  a  visit  to  Washington  at  the  time  the 
designs  were  commenced  he  received  the  impression  that  nearly 
all  the  details  of  the  concrete  hulls  were  fixed  by  the  designers, 
while  representatives  of  Lloyd's  Register  and  of  the  American 
Bureau  of  Shipping  were  consulted  on  matters  of  naval  archi- 
tecture. 

It  is  unfortunate  that  the  two  types  of  ships  have  always 
been  characterized  as  being  respectively  of  7, 500  tons  deadweight 
capacity  and  3,500  tons  deadweight  capacity.  The  original 
estimates  showed  considerably  smaller  figures,  and  the  actual 
carrying  capacities  are  respectively:  6,380  tons  deadweight  and 
3,078  tons  deadweight. 

A  special  light-weight  aggregate  concrete  (see  Chapter  IX)  was 
used  in  building  these  ships,  and  it  is  difficult  to  say  whether 
the  increased  weights  of  hulls  as  compared  with  the  estimated 
figures  were  due  to  increased  unit  weight  per  cubic  foot  of  concrete 
— originally  estimated  at  107  Ib.  per  cub.  ft.  excluding  reinforce- 
ment— or  if  larger  quantities  of  concrete  were  used  in  the  hulls 
than  shown  on  the  plans. 

The  gravel  concrete  used  in  the  construction  of  the  author's 
trial  ships  weighed  140  Ib.  per  cub.  ft.  excluding  reinforcement. 
It  was  to  be  expected,  therefore,  that  ships  built  of  the  special 
light-weight  concrete  would  have  greater  deadweight  carrying 
capacity  in  relation  to  the  weight  of  hull  than  the  trial  ships. 
But  as  is  shown  below,  this  is  not  the  case  ;  on  the  contrary,  the 
concrete  hull  of  M.S.  Askelad  is  much  lighter  per  ton  deadweight. 

S.S.  "Selma"  and  "Latham";  S.S.  ««,  Cape  Fear"  and 
"  Sapona." — The  first  type  of  U.S.  concrete  ship  is  represented 
by  the  oil-tankers  S.S.  Selma  and  Latham,  owned  by  the  American 
Fuel  Oil  and  Transportation  Company,  Inc.  They  are  described 


CONCRETE    SHIPS   BUILT   TO   CLASS 


47 


in  Chapter  VI.  The  second  type  is  represented  by  the  cargo 
carriers  S.S.  Cape  Fear  and  Sapona,,  also  described  (see  pp. 
72-77)  in  Chapter  VI.  These  ships  have  the  same  freeboards  as 
steel  ships  of  corresponding  types  ;  and  in  making  comparisons 
of  carrying  capacity,  the  same  condition  should  apply  to  M.S. 
Askelad.  The  demand  for  extra  freeboard  made  by  the  Nor- 
wegian Director  of  Shipping  is  no  longer  justified ;  Lloyd's  Register 
of  Shipping,  for  example,  does  not  demand  extra  freeboard  for 
concrete  ships  as  compared  with  steel  ships  of  the  same  type. 
The  freeboard  for  M.S.  Askelad  should  therefore  be  taken  at 
2'  3",  as  has  been  done  in  the  comparison  below. 

None  of  the  ships  have  shown  unseaworthiness  or  lack  of 
strength  ;  the  carrying  capacities  may,  therefore,  be  compared 
without  any  qualification  of  a  technical  nature  : 


Oil-Tankers  SeZma 
and  Latham,  of 
light-weight  con- 
crete 420'  x  53' 
X  35'  6",  free- 
board 9'  0*. 

Cargo  Carriers 
Cape  fear  and 
Sapona,  of  light- 
weight concrete 
268'  X  46'  x  28'  3", 
freeboard  4'  3". 

Cargo  Carrier 
Askelad  Trial  Ship, 
of  gravel  concrete 
ITO'xSl'xIQ'O", 
freeboard  2'  3*. 

Loaded  displacement,  tons 
Actual  deadweight,  tons 
Deadweight 

13,040 

6,380 

0-489 
5,537 
1-16 

6,310 

3,078 

0-488 
2,843 
1-08 

1,960 
1,076 

0-549 
733 
1-47 

Loaded  displacement 
Weight  of  concrete  hull,  tons 
Deadweight 

Weight  ot  concrete  hull 

The  above  shows  that  the  relative  advantage  of  the  author's 
design,  demonstrated  by  M.S.  Askelad,  is  12-J-  per  cent,  increased 
deadweight  in  relation  to  loaded  displacement,  or  31  per  cent, 
increased  deadweight  in  relation  to  weight  of  concrete  hull. 

It  may  be  argued  that  the  Askelad  is  a  motor-ship,  while  the 
others  are  steamers,  with  considerably  heavier  machinery,  thus 
reducing  the  deadweight.  This  is  true,  but  then  it  must  be 
remembered  that  the  American  ships  are  built  of  light-weight 
concrete,  weighing  between  107  and  120  Ib.  per  cub.  ft.,  while 
the  Askelad  is  built  of  ordinary  gravel  concrete  weighing  140  Ib. 
per  cub.  ft.  Had  the  same  volume  of  light-weight  concrete  been 
used  in  building  the  Askelad,  the  weight  of  hull  would  have 

120 

been  628  X      -  =  538  tons,  a  reduction  of  90  tons,  which  would 
140 

have  given  the  trial  ship  a  corresponding  increase  of  deadweight 
capacity. 


48        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

The  weight  of  Steel  Reinforcement  in  the  author's  trial  ships 
was  equal  to  9|  per  cent,  of  the  deadweight  capacity.  In  the 
U.S.  Shipping  Board's  cargo  carriers  it  amounted  to  13J  per 
cent,  and  in  the  oil-tankers  21  per  cent,  of  the  deadweight  capacity, 
or  respectively  about  36  and  115  per  cent,  more  reinforcement  per 
ton  deadweight  than  in  the  trial  ship. 

The  amount  of  concrete  used  in  building  the  hull  of  the 
Askelad  was  0-343  cubic  yards  per  ton  deadweight,  while  the 
amounts  in  the  U.S.  Shipping  Board's  cargo  carriers  arid  oil 
tankers  work  out  at,  respectively,  0-548  cubic  yards  and  0-457 
cubic  yards  per  ton  deadweight,  assuming  that  the  light  weight 
concrete  used  in  these  ships  really  weighed  120  Ib.  per  cub.  ft. 
(average),  as  stated  in  the  final  report,  21st  January  1921,  of 
the  Committee  on  Concrete  Barges  and  Ships.  This  shows  that 
respectively  60  and  39  per  cent,  more  concrete  was  used  per  ton 
deadweight  to  build  the  hulls  of  the  classified  ships  than  in  the 
author's  trial  ship. 

From  Mr.  R.  J.  Wig's  paper,  "Methods  of  Construction  of 
Concrete  Ships,"  published  in  the  Proceedings  of  the  Fifteenth 
Annual  Convention  of  the  American  Concrete  Institute,  vol.  xv, 
1919;  pp.  276-7,  it  appears  that  the  buying  price  of  the  chief 
materials  in  Hull  No.  1715 — an  oil-tanker  of  the  same  type  as 
the  Selma  and  Latham,  built  in  Mobile,  Ala. — came  to  about 
£18  105.  ($89)  per  ton  of  2,240  Ib.  for  the  steel,  and  about 
13  shillings  ($3-12)  per  barrel  of  Portland  cement  delivered  at 
the  yard.  The  corresponding  prices  of  materials  used  in  building 
the  author's  trial  ships  were  much  higher,  viz.  about  £28  per 
ton  of  steel  reinforcement  and  about  £1  5s.  per  barrel  of  Portland 
cement.  Lumber  for  making  the  wood  forms  and  scaffolding 
was  about  20  per  cent,  cheaper  in  the  construction  of  the 
American  oil-tanker  than  in  the  author's  trial  ships.  But  wages 
were  approximately  40  per  cent,  higher  in  the  United  States 
than  in  Norway  at  that  date  (1918).  At  present  they  are  prac- 
tically the  same  in  most  trades.  It  becomes  interesting,  then, 
to  compare  the  actual  first  costs  of  the  ships  complete. 

In  the  reports  of  the  Committee  on  Reinforced  Concrete 
Barges  and  Ships  the  prices  are  stated  as  being  $210-300  per 
ton  deadweight  for  the  cargo  ships,  and  about  $200-280  per 
ton  deadweight  for  the  oil-tankers,  with  the  important  proviso 
that  these  prices  refer  to  the  purely  nominal  deadweight  capacities, 


CONCRETE  SHIPS  BUILT  TO  CLASS      49 

and  not  to  the  actual  capacities.  Taking  average  figures  from 
the  above  prices,  and  varying  them  in  accordance  with  the 
relation  between  the  nominal  deadweight  and  the  actual  dead- 
weight, the  costs  per  ton  deadweight  are  : 

Cargo  carriers,  3,078  tons  deadweight, 

similar  to  Cape  Fear  and  Sapona  .  .  ( $290)  £60 

Oil-tankers,  6,380  tons  deadweight,  similar 

to  Selma  and  Latham.  .  .  .  ($282)  £58 

Trial  ship  Askelad,  1,076  tons  deadweight  £35 

In  the  above  considerations,  where  unfavourable  facts  as 
regards  carrying  capacities  and  prices  have  been  proved  against 
concrete  ships  built  to  class,  there  has  been  no  desire  on  the 
part  of  the  author  to  criticize  the  designers,  who  have  worked 
under  the  strain  of  war  conditions  and  have  been  subject  to  handi- 
caps which  are  not  present  when  private  enterprise  takes  the 
initiative  and  assumes  the  whole  risk.  Nor  has  there  been  any 
intention  of  presenting  the  superior  points  of  the  author's  design 
in  an  extreme  manner  ;  for  example,  no  allowance  has  been 
made  for  the  well-known  fact  that  smaller  vessels  always  are 
more  expensive  in  construction,  and  therefore  command  a  higher 
market  price  per  ton  deadweight,  than  larger  ships. 

More  than  60,000  tons  deadweight  of  seagoing  concrete  ships 
of  the  above-mentioned  types  were  actually  constructed  by 
the  U.S.  Shipping  Board.  Reports  on  this  tonnage  will  be 
made  known  to  the  profession  in  all  parts  of  the  world  ;  and  it 
is  therefore  necessary  to  point  out  as  strongly  as  possible  that 
concrete  ships  have  been  built  successfully  at  a  much  lower  cost 
than  these,  with  much  lighter  weights  of  hull,  and  with  at  least  the 
same,  if  not  greater,  strength. 


CHAPTER   V 

CONCRETE  TUGS,  FLOATING  DOCKS,  LIGHTSHIPS,  AND 

LIGHTERS 

The  First  Concrete  Tug — The  First  Concrete  Floating  Dock — The  First 
Concrete  Lightship — Concrete  Water-Carrier — Concrete  Lighters. 

The  First  Concrete  Tug. — There  is  one  type  of  ship  in  which 
cargo  capacity  is  of  practically  no  importance,  and  in  which  a 
heavy  weight  of  hull  is  an  advantage  rather  than  otherwise  ; 
that  type  is  the  seagoing  or  harbour  tug,  provided  with  powerful 
machinery  in  order  to  tow  or  assist  other  ships,  and  made  strong 
enough  to  withstand  the  rough  usage  entailed  by  such  service. 

A  tug  must  be  seaworthy  and  easy  to  handle  in  all  circum- 
stances since  she  is  frequently  called  upon  to  put  to  sea  in  weather 
bad  enough  to  keep  larger  ships  in  harbour.  The  commercial 
value  of  a  tug  depends  primarily  on  the  type  and  power  of  the 
engines,  the  fuel  consumption,  and  the  equipment  for  salvage 
work,  etc.,  while  the  size  of  hull  is  of  secondary  importance. 
It  may  be  assumed  that  the  steel  hull  of  an  ordinary  cargo  carrier 
costs  about  40  per  cent,  of  the  total  cost  of  the  ship,  whereas 
the  hull  of  a  tug  costs  only  about  25  per  cent,  of  the  total. 
Accordingly  the  saving  in  first  cost  obtained  by  the  use  of  concrete 
for  the  hull  of  a  tug  is  relatively  less  than  for  a  cargo  carrier. 
There  are,  however,  other  advantages  to  be  gained  by  building 
tugs  of  concrete  ;  they  may  be  stated  as  follows  : 

1.  The  towing  force  is  superior  to  that  of  a  steel  tug  of  equal 
engine  power,  particularly  if  equipped  with  internal-combustion 
engines. 

2.  The  life  of  the  engines  is  increased  and  repairs  and  upkeep 
expenses  decreased,   due  to  their  being  mounted  in  more  rigid 
hulls  less  subject  to  vibration. 

3.  The  first  cost,  running  expenses  and  costs  of  repairs,  are 
reduced. 

Staal-Beton  19,  the  first  concrete  tug,  was  built  by  the  author's 
firm  for  private  use,  and  was  neither  classed  by  a  Registration 

50 


FIRST  CONCRETE   TUG  51 

Society  nor  built  under  a  Government  permit  ;  but  the  authorities 
knew  of  the  construction  and  tacitly  agreed,  reserving,  however, 
the  right  to  condemn  the  ship  if  she  did  not  pass  tests  of  sea- 
worthiness and  strength.  Fortunately  the  trials  of  the  tug  were 
perfectly  satisfactory,  and  she  has  now  given  continuous  good 
service  for  nearly  four  years.  There  have  not  been  the  smallest 
repairs  carried  out  on  either  hull  or  engine  during  this  time. 


CREW'S       QUARTERS 


FIG.  21. — Tug  Staal-Bzton  19.     General  Arrangement. 

In  the  winter  the  tug  is  used  for  ice- breaking  in  the  harbour  at 
Moss  and  in  the  Sound. 

Definite  proof  of  the  advantages  of  concrete  tugs  can  come 
only  from  experience  ;  but  Staal-Beton  19  is  providing  that 
proof,  and  justifying  expectations.  With  regard  to  the  three 
points  mentioned  above  : 

1.  The  superior  towing  force  is  due  to  the  greater  weight  and 
momentum  of  the  concrete  hull ;  once  the  initial  inertia  has  been 
overcome  a  steadier  pull  is  maintained  on  the  tow-rope  in  a 
rough  sea.  It  must  be  borne  in  mind  that  the  resistance  of  the 


FIG.  22. — Tug  Staal-Beton  19.     Ready  for  Launching,   17th  October  1917. 


FIG.  23. — Tug  Staal-Beton  19.     On  trial  outside  Christiania,  October  1917. 

52 


FIRST   CONCRETE   TUG 


53 


tug  itself  is  almost  negligible  in  comparison  with  the  resistance 
on  the  tow-rope  ;  and  many  elements  enter  into  the  tow-rope 
resistance — size  and  number  of  ships  in  tow  and  their  steering 
qualities,  towing  speed,  currents,  wind,  length  of  tow-rope. 


FIG.  24. — Tug  Staal-Beton  19  breaking  ice  in  the  Sound  at  Moss. 

2.  After  nearly  four  years  of  continuous  service  the  engines 
in  Staal-Beton  19  are  in  perfect  condition  and  have  never  been 
repaired  nor  even  had  the  foundation  bolts  tightened  up.  The 
opinions  of  marine  engineers  who  have  had  experience  in  concrete 
ships  must,  until  comparative  figures  can  be  obtained,  be  accepted 


54        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

as  further  testimony  in  support  of  the  claim  advanced  for  longer 
life  of  engines. 

3.  The  costs  of  the  Staal-Beton  19  were,  in  round  figures  : 
hull  £800,  engines  £1,100,  equipment  and  installation  £1,300, 
total  £3,200.  The  cost  of  the  hull  was  found  to  be  less  than 
ascertained  costs  of  similar  steel  hulls  of  the  same  date. 

Fig.  24  shows  Staal-Beton  19  breaking  ice  eight  to  ten  inches 
thick  without  difficulty.  There  has  been  much  discussion  in 
technical  circles  on  the  ability  of  concrete  to  withstand  ice  or 
even  sea- water,  and  various  writers  have  referred,  as  examples, 
to  badly  made  concrete  piers,  etc.,  disintegrating,  or  fracturing, 
with  serious  consequences.  But  from  a  personal  examination 
of  Staal-Beton  19  the  author  can  state  that  after  three  or  four 
winters  in  service,  partly  as  an  ice-breaker,  there  are  no  signs 
whatever  of  abrasion  or  wear  on  the  concrete  bows.  The  hull  is  in 
perfect  condition  everywhere.  Neither  repair,  painting,  nor 
cement  brushing  has  been  done  on  the  surface,  which  is  in  its 
original  state,  without  any  protection  or  covering.  The  author 
believes  that  Staal-Beton  19  is  a  conclusive  example  of  the  power 
of  resistance  of  shipbuilding  concrete  to  the  attacks  of  ice. 

The  main  particulars  of  Staal-Beton  19  are  : 

Length  between  perpendiculars           .  48'  0" 

Breadth 12' 0" 

Depth" r  r 

Block  coefficient       .  .  .  .  .      0-62 

Engines,  Bolinder  motor  .  .  .                50  B.H.P. 

Weight  of  reinforcement  in  hull  .  .        5  tons 

,,          concrete  ,,  .  35     „ 

.,          equipment  .  .  .  .      15     ,, 

,,          engines    .  .  .  .                  4     ,, 

Light  displacement  .  .  .  .      59     ,, 

The  detail  design  did  not  present  any  special  difficulties,  for 
there  was  no  need  to  save  weight  on  the  concrete  hull  and  all 
dimensions  could  be  made  ample,  namely  : 

Deck  slabs  .  .  .     2J" 

Side  slabs  .  .  .  .3" 

„        at  bilges  .                5" 

Bottom  slabs  .  .                3J" 

Deck  beams  .  .  .      5"  X  V' 

Side  frames  .  .  .      5"  X  8" 

Bottom  frames  .  .  .      7"  X  10",  12",  and  16" 
Keelson                                        8"  X  12" 


FIRST   CONCRETE   TUG 


55 


The  reinforcement  in  the  deck,  side,  and  bottom  slabs  con- 
sists of  a  "  rib  "  lath  near  the  outside  and  J"  and  I"  round  bars, 


W4>N 

% 

» 


(k"^-6"O.C.  BENT  UP  FROM 
DECK       PLAN. 


SECTIONS     THROUGH     BOTTOM     AT     KEELSON 


SECTIONS     THROUGH        FRAMES. 


N 

NEAR.  BOTH  rftCE5 

(STAGGERED) 


REINFORCEMENT     IN    F*RAME5     2f   BULK1HEADS. 
FIG.   25. — Tug  Staal-Beton  19.     Longitudinal  Section,  Deck,  and  Frames. 

spaced  from  3"  to  12",  staggered  near  both  surfaces.     The  side 
frames  are  reinforced  with  two  J"  rods  near  the  inside  face  and 


56        SEAGOING  AND   OTHER  CONCRETE   SHIPS 

two  J"  rods  near  the  outside,  tied  with  iV  stirrups  5"  apart.  The 
bottom  frames  have  the  same  reinforcement  with  an  additional 
I"  rod  near  the  top.  The  keelson  is  reinforced  with  three  £" 
rods  near  top  and  bottom  ;  it  is  divided  from  the  fore  end  of 
the  engine  foundation  to  the  stern,  forming  a  shaft  tunnel 
through  the  hold. 

Two  oak  fenders  were  originally  bolted  round  the  sides,  as 
shown  in  the  illustrations  ;  but  the  lower  one  was  removed  after 
the  first  trials.  The  stem  is  protected  by  a  5"  X  6"  oak  fender 
faced  with  a  f"  steel  flat  bar.  The  towing  hook,  sliding  on  a 
steel  arc,  is  attached  to  the  concrete  hatch  coaming  around  the 
engine-room. 

The  First  Concrete  Floating  Dock.  — Many  years  before 
seagoing  concrete  ships  became  an  accomplished  fact,  the  question 
of  constructing  floating  docks  of  concrete  had  been  considered 
by  the  author,  and  Fig.  26  shows  the  first  concrete  floating  dock 
ever  built.  It  was  ordered  by  A.  S.  Maritim,  yacht  and  motor- 
boat  builders  at  Bestum,  near  Christiania.  Since  the  dock  was 
intended  to  take  only  light  pleasure  craft  a  lifting  capacity  of 
75  tons  was  considered  sufficient ;  during  trials  before  delivery 
to  the  owners  it  lifted  90  tons.  After  the  first  year  of  service 
Messrs.  Maritim,  on  their  own  initiative,  expressed  the  following 
opinion  on  the  dock  : 

"  BESTUM  PH.  CHKISTIANIA. 

10  May  1918. 

"It  is  a  pleasure  for  us  to  advise  you  herewith  that  the 
concrete  floating  dock,  which  you  built  for  us  last  year,  is  working 
just  as  satisfactorily  now  as  last  year,  although  it  has  been 
frozen  in  the  ice  during  the  entire  winter  ;  and  the  dock  has 
suffered  no  damage  whatsoever,  in  spite  of  the  fact  that  the  ice 
was  never  cut  up  around  the  floating  dock. 

"  Respectfully  yours, 

A.  S.  MARITIM, 

(s.)  Alf  Bryde, 
Managing  Director." 

It  should  be  added  that  subsequent  experience  to  date  has 
been  equally  satisfactory,  and  that  the  dock  every  winter  is 
frozen  in  ice  several  feet  thick,  in  the  Bay  of  Bestumkilen,  near 
Christiania,  where  it  is  stationed.  The  ice  exerts  heavy  pressure 


CONCRETE   FLOATING  DOCK 


57 


against  the  sides  ;  and  it  is  difficult  to  say  whether  steel  and 
wood  docks  would  stand  the  strain  as  well,  since  it  is  customary 
to  cut  the  ice  around  them. 

The  dimensions  of  the  dock  are  : 

ft.    in. 
Inside  breadth        .          .          .          .          .  25     0 

Outside  breadth 36     0 

Length 80     0 

Depth  of  pontoon  .          .          .          .          .          .46 

Total  depth  of  sidewalls  .          .          .          .      20     0 


£* 


Reinforcement.  Concrete. 

FIG.  26. — Cross  Section  of  the  first  Concrete  Floating  Dock. 

The  pontoon  is  divided  by  two  longitudinal  and  two  transverse 
watertight  bulkheads  into  nine  compartments,  each  with  a 
separate  pipe-line  to  the  pumping  chamber.  Access  is  provided 
to  each  compartment  by  manholes  with  watertight  covers.  The 
bottom  frames  are  spaced  4'  apart ;  they  are  of  solid  concrete 
3"  thick,  provided  with  manholes  and  openings  near  top  and 
bottom  for  air  and  water,  except  in  those  acting  as  watertight 
bulkheads.  Fig.  26  shows  a  cross  section  of  the  dock.  The 
longitudinal  bulkheads  and  top  and  bottom  slabs  of  the  pontoon 
are  all  2f"  thick.  The  outer  and  inner  walls  of  the  side  wings 
are  2J"  thick,  and  the  top  slab  3"  thick.  The  reinforcement  is 


58        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

very  light.  In  the  slabs  it  is  of  lath  with  J"  and  -£s"  round  bars  ; 
the  vertical  frames  are  reinforced  with  f"  to  f"  round  bars. 

Wood  forms  were  only  used  in  construction  of  interior  frames 
in  wings  and  pontoon.  All  the  slabs  were  plastered  on  "  rib  " 
and  "  Hy.  rib  "  lath  except  the  bottom  slab,  which  was  poured 
directly  on  the"  wood  platform  supporting  the  dock. 

The  pump-house  is  located  on  top  of  one  wing,  directly  over 
the  pumping  chamber,  where  a  centrifugal  pump  capable  of 
emptying  the  dock  in  an  hour  is  fitted.  A  five  horse-power 
electric  motor  drives  the  pump,  current  being  supplied  from  the 
shore  by  cable.  All  the  valves  are  controlled  from  the  pump- 
house,  where  a  pendulum  indicates  the  direction  in  which  the 
dock  is  trimming  and  so  the  routine  in  which  the  valves  should 
be  operated.  Four  sluice  valves  on  the  outside  walls  of  the 
dock  allow  of  it  being  filled,  and  lowered,  very  rapidly.  The 
pipe-lines  are  made  of  concrete,  poured  around  five-inch  terra- 
cotta pipes  ;  but  this  construction  is  heavy  and  not  altogether 
satisfactory.  Iron  pipes  permit  of  easier  access  to  bends  and 
connexions.  The  keel  blocks  are  of  wood,  four  feet  apart. 

When  the  plans  were  being  drawn  out  for  the  dock  there 
had  been  no  experience  accumulated  relating  to  floating  craft 
of  concrete  other  than  lighters.  It  was  therefore  natural  that 
the  design  should  be  "on  the  safe  side,"  and  the  dock  is  con- 
siderably heavier  than  it  need  have  been  ;  the  weights  are  : 

Tons. 

Reinforcement  in  hull  ...        20 

Concrete  in  hull  .          .  .          .          .170 

Outfit,  pumps,  and  motor  ...        20 

Light  displacement       .  .          .          .210 

Lifting  capacity  .  .          .          .90 

Loaded  displacement  .          .          .      300 

The  weights  of  concrete  and  steel  amount,  respectively,  to 
about  190  and  22  per  cent,  of  the  lifting  capacity.  These  are 
too  high,  even  for  small  docks.  Designs  have  been  prepared  by 
the  author  for  docks  of  4,000  tons  and  8,000  tons  lifting  capacity, 
and  these  show  the  following  calculated  weights  : 

4,000  tons  8,000  tons 

Lifting  Capacity.         Lifting  Capacity. 

Weight  of  concrete  in  hull  3,800  tons  7,000  tons 

steel  450  800 


59 


60        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

In  relation  to  the  lifting  capacities  these  weights  are,  respec- 
tively, 95  per  cent,  and  88  per  cent,  for  concrete,  and  11  per 
cent,  and  10  per  cent*  for  steel,  showing  that  the  cost  per  ton 
of  lifting  capacity  decreases  as  the  size  of  dock  increases. 

There  is  perhaps  no  kind  of  floating  craft  more  exposed  to 
corrosion  than  the  pontoon  of  a  floating  dock,  which  is  con- 
tinually being  filled  with,  and  emptied  of,  salt  water.  The 
numerous  interior  bulkheads  offer  extensive  surface  for  attack, 
and  repairs  are  expensive  on  account  of  the  difficulty  of  docking 
large  floating  docks.  The  best  material  for  the  construction  of 
such  craft  is  shipbuilding  concrete  ;  the  advantages  and  dis- 
advantages in  comparison  to  wood  or  steel  can  briefly  be  summed 
up  as  follows  : 

1.  The  first  cost  of  concrete  docks  is  considerably  lower ;  broadly 
speaking,  it  comes  to  about  60  to  70  per  cent,  of  steel  docks. 

2.  The  upkeep  expenses  of  concrete  docks  are  practically  nil ; 
while  those  for   steel   docks   are   considerable,    because   of  the 
liability  to  corrosion  inside  and  out. 

3.  Repairs  are  much  cheaper  for  concrete  docks.     There  are 
no  bottom  plates  to  renew,  and  practically  all  local  damage  below 
the  water-line  can  be  repaired  by  the  assistance  of  divers,  without 
the  necessity  of  docking. 

4.  Water  tightness    and    fireproofness    of    concrete    docks    are 
superior  to  those  of  either  steel  or  wood  docks. 

The  disadvantages  of  concrete  docks  are  : 

1.  Increased  size  for  the  same  lifting  capacity.  This  is 
important  only  if  space  is  limited  where  the  dock  is  to  be  located, 
or  if  the  depth  of  water  does  not  permit  of  increased  depth  of 
pontoon. 

Greater  liability  to  local  damage  from  collisions  with  ships  if 
the  concrete  surface  is  not  protected  by  fenders. 

Neither  of  these  objections  is  serious,  and  local  conditions 
will  frequently  reduce  both  to  a  minimum.  The  author  firmly 
believes  that  within  the  next  two  or  three  generations  all  floating 
docks  will  be  built  of  shipbuilding  concrete,  just  as  at  present 
excavated  dry  docks  are  lined  with  concrete. 

The  First  Concrete  Lightship. — Another  stationary  type  of 
floating  craft  which  is  built  to  greater  advantage  of  concrete 
than  of  steel  or  wood  is  the  Lightship.  The  demand  for  such 
ships  is  very  limited,  particularly  in  Norway,  where  deep  water 


FIRST  CONCRETE   LIGHTSHIP 


61 


is  found  everywhere  close  in  to  the  shore,  and  lighthouses  erected 
011  islands  give  good  service.  When  the  Director  of  Lighthouses 
decided  to  station  a  lightship  at  a  subaqueous  rock  in  the 
approach  to  Christiania — the  Ildjemsflu — concrete  was  selected 
as  the  most  suitable  material,  and  the  author's  firm  was  requested 
to  build  the  ship.  While  having  the  distinction  of  being  the 
only  lightship  in  Norway  and  the  first  ever  built  of  concrete 
the  Ildjernsflu  presented  no  difficulties  of  design,  and  details  are 
not  of  special  interest.  Fig.  28  shows  the  ship  after  two  years 


Fio.  28. — The  first  Concrete  Lightship — Ildjernsflu — stationed  at  the  approach 
to  Christiania  since  1918. 

of  service  ;  she  was  completed  in  1917,  except  for  the  machinery, 
and  was  stationed  at  the  rock  in  the  following  year. 

The  ship  has  given  entirely  satisfactory  service  in  spite  of 
exposure  to  more  severe  strains  than  originally  anticipated. 
The  Director  of  Lighthouses  has  given  the  author  the  following 
information  on  the  matter  : 

"  The  rounded  form,  smooth  surface,  and  flat  bottom  of  the 
vessel  serves  its  purpose  of  enabling  the  lightship  to  rise  on 
the  ice  jams,  and  no  ill  effects  can  be  seen  from  the  ice.  The 
hull  is  made  rather  too  short  and  rose  almost  on  end  in  rough 
seas.  Since  the  chain  was  fixed  to  a  loop  through  the  chain  pipes 
at  the  bow,  a  terrific  pounding  was  caused  against  the  ship's 


62        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

bottom  when  rising  on  the  seas.  In  November  last  year  during 
a  very  severe  gale  the  vessel  broke  its  moorings  by  snapping 
both  anchor  bolts,  each  2"  diam.,  fastened  in  the  rock,  and 
drifted  in  through  the  harbour,  where  she  was  rescued  before 
any  damage  was  done  to  the  concrete  hull.  When  being  re- 
stationed  at  Ildjernsflu  a  strong  loop  of  hemp  cable  was  carried 
around  the  aft  end  and  attached  nearly  at  the  centre  of  the 
ship  (as  on  tugs),  and  the  chain  was  fastened  to  this  loop.  The 
arrangement  has  been  satisfactory,  and  has  greatly  eased  the 
heavy  pounding  from  waves  on  the  ship's  bottom  and  the  strain 
on  the  moorings." 

The  ship  is  quite  small,  having  the  following  dimensions  : 

ft.     in. 

Length  between  perpendiculars  .      42     0. 

Breadth 18     0 

Depth 90 

The  materials  in  the  hull  were  6  tons  of  reinforcement  and 
52  tons  of  concrete,  making  the  total  weight  of  the  naked  hull 
58  tons.  Machinery  was  installed  for  supplying  power  and 
compressed  air  to  the  sirens  and  the  light.  Cabins  were  fitted 
up  for  the  keeper  and  his  family,  and  large  supply  tanks  for 
fresh  water  were  built  of  concrete  against  the  ship's  side.  The 
remaining  space  was  taken  up  by  store-rooms  for  fuel,  food,  etc. 
The  advantages  obtained  by  building  lightships  of  concrete 
compared  to  steel  are  : 

Lower  first  cost  and  upkeep,  perfect  watertightness  and 
better  insulation  against  cold  and  heat  for  the  crew.  A  concrete 
lightship  once  moored  at  its  station  should — barring  severe 
accidents — never  need  to  be  removed  for  docking  or  survey. 
The  Ildjernsflu  is  painted  a  bright  red,  and  most  ships  passing 
by  probably  have  no  idea  that  she  is  built  of  concrete. 

Concrete  Water  Carrier. — This  ship  is  also  very  small,  the 
dimensions  being  60'  0"  X  18'  0"  X  7'  6",  and  she  carries  about 
75  tons  of  fresh  water.  The  engine  is  a  38  H.P.  Scandia  motor, 
giving  a  speed  of  5  miles  an  hour.  The  hold  is  divided  up  by 
portable  wood  bulkheads  longitudinally  and  transversely  to 
prevent  the  water  moving  about  too  freely.  When  these  are 
taken  away  the  boat  is  used  to  carry  ordinary  cargo. 

As  regards  carrying  water,  it  will  probably  be  admitted  that 


CONCRETE  WATER   CARRIER 


63 


concrete  is  much  cleaner,  and  easier  to  keep  clean,  than  either 
wood  or  steel ;  and  it  should  be  recorded  that  no  influx  of  salt 
water  has  ever  affected  the  freshwater  cargo  in  Bjorvika, 
although  at  the  time  of  her  construction  many  engineers  had 
serious  doubts  as  to  the  possibility  of  making  concrete  perfectly 
watertight. 

Concrete  Lighters.  —In  Chapter  I  it  has  been  stated  that, 
contrary  to  an  almost  universal  impression,  shipbuilding  con- 
crete is  not  utilized  to  its  best  advantage  when  used  for  con- 
structing lighters.  And  yet  a  considerable  number  of  such 
craft  have  been  built  in  different  countries  at  various  periods, 


FIG.   29. — Concrete  Water  Carrier   Bjorvika,  built  for  harbour  service  in   1917. 

dating  back  twenty-five  years  or  more.  It  is  even  claimed  that 
a  small  row-boat  of  concrete  was  built  in  1854  by  Lambot,  and 
exhibited  by  him  at  the  World's  Fair  in  Paris  that  year.  The 
author  has  given  the  problem  considerable  attention  during  the 
past  twelve  or  fourteen  years,  and  has  built  numerous  lighters 
of  different  types  and  sizes.  The  first  one  was  constructed  in 
Manilla,  the  others  in  Norway. 

During  the  past  few  years  many  misleading  and  incorrect 
statements  have  appeared  in  the  technical  and  public  press 
about  concrete  lighters.  Frequently  the  writers  have  been 
entirely  ignorant  of  the  subject :  some  have  been  theoretical 
enthusiasts,  whose  designs  on  paper  were  the  sole  foundation  for 


64        SEAGOING  AND   OTHER  CONCRETE   SHIPS 

their  extravagant  claims  ;  others  have  condemned  the  whole 
idea  of  using  concrete  for  any  kind  of  floating  craft,  merely  from 
unsatisfactory  experience  with  perhaps  one  or  two  concrete 
lighters. 

Conditions  differ  greatly  in  different  countries  and  there  is 
no  material  of  construction,  wood,  steel,  or  concrete,  which  is 
best  under  all  conditions  of  service.  On  the  large  rivers  in  the 
forest  regions  of  Russia  and  Siberia  wood  lighters — sometimes 
of  a  temporary,  raft-like  character — are  built  at  a  trifling  cost 
to  transport  native  produce  down  the  river,  where  they  are 


FIG.  30.— Standard  type  of  100  tons  deadweight  Concrete  Lighter.     The  first 
built  in  Norway,  August  1916. 

knocked  apart  and  the  materials  sold  at  the  end  of  the  journey. 
Obviously  in  such  a  trade  neither  steel  nor  concrete  can  compete 
with  wood.  On  the  inland  canals  of  Europe  and  America,  where 
locks  and  waterways  are  frequently  limited  in  dimensions,  and 
the  lighters  always  move  in  entirely  enclosed  waters,  steel  boats 
of  extremely  light  construction  are  the  most  efficient  cargo 
carriers,  owing  to  their  very  light  weight  and  draught.  Further, 
in  the  districts  intersected  by  these  canals  steel  lighters  can  be 
built  very  cheaply.  Where  there  is  plenty  of  water,  and  the 
cargoes  are  light  in  relation  to  their  bulk,  like  lumber,  for  example, 
and  conditions  do  not  impose  frequent  collisions  with  docks, 


CONCRETE   LIGHTERS  AND   BARGES 


65 


concrete  lighters  may  be  most  suitable  on  account  of  their  low 
first  cost  and  upkeep  expenses. 

Concrete  lighters  have  given  also  good  harbour  service.  The 
author's  firm  constructed  in  1916  two  lighters  of  the  type  illus- 
trated in  Fig.  30  for  A.S.  Laegterkompaniet,  the  largest  lighter 
owners  in  Christiania.  These  owners  have  testified  (in  a  letter 
dated  21st  February  1917)  to  the  good  service  given  by  these 


FIG.  31. — Open   Concrete   Barge,    60  tons   deadweight,   for   river   and   harbour 

service. 

two  lighters  ;  they  have  recorded  that  the  lighters  have  been 
frozen  up  for  several  weeks,  and  that  they  have  been  towed 
through  the  ice  in  Christiania  harbour,  without  apparently 
suffering  any  damage. 

These  standard  type  lighters  are  of  light  construction,  the 
average  thickness  of  the  deck,  side,  and  bottom  slabs  being 
2£  inches.  The  frames  are  9"  X  4",  spaced  5  feet  apart ;  the 
transverse  frame  at  amidships  is  heavier  than  the  others  and  is 
carried  across  the  hatch  in  an  arc,  forming  a  support  for  the 
5 


66        SEAGOING  AND   OTHER  CONCRETE   SHIPS 

hatch  covers.  There  are  two  transverse  bulkheads,  2  inches 
thick,  having  a  cargo  hold  between  them  48'  0"  long  ;  the  cargo 
hatch  is  40'  0"  X  12'  6".  Wood  centring  was  used  only  for  the 
platform  on  which  the  bottom  rested,  and  for  the  interior 
frames  ;  the  concrete  in  the  side  and  deck  slabs  was  plastered  on 
a  stiff  metal  lath  to  which  was  secured  additional  reinforcement 
in  the  form  of  round  bars. 

The  author's  firm  has  built  also  some  250-ton  lighters  of  similar 
design  to  the  100-ton  lighter,  and  a  very  small  type  of  open  river 
barge,  shaped  like  a  box,  with  a  pointed  stem  ;  one  of  the  latter 
is  illustrated  in  Fig.  31.  This  figure  shows  also  a  couple  of 
concrete  mooring  buoys,  of  which  several  have  been  built ;  they 
are  giving  satisfactory  service  and  have  not  been  pumped  out 
since  they  were  placed  in  position  four  or  five  years  ago. 

The  particulars  of  the  lighters  and  the  barge  are  : 

250-ton  100-ton         60-ton 

Lighter.          Lighter.          Barge. 

Length  between  perpendiculars         .      80'  0"  64'  0"  47'  0" 

Breadth  (maximum)  .  .  .20'  0"  IS'  6"  15'  0" 
Depth  .  .  .  .  .11'$*  7'  6"  5' 6" 

Weight  of  reinforcement,  tons  .10  5  2 

concrete  „  .      122  49  25 

hull  „  .      132  54  27 

outfit  13  63 

Light  displacement  ,,  .145  60  30 

Deadweight  „  .250  100  54 

Loaded  displacement  „  .395  160  84 

Block  coefficient     ....     0*84  0*80  0'935 

Cost  in  1916  ....     £1,750  £450  £260 

More  than  a  dozen  lighters  of  these  types  have  been  built 
and  are  now  in  service  in  various  parts  of  Norway  and  Sweden. 

The  various  elements  involved  in  a  comparison  between 
concrete  lighters  and  steel  or  wood  lighters  are  discussed  below  : 

First  cost  is  nearly  always  highest  for  steel  and  lowest  for 
wood,  with  concrete  between  ;  but  in  localities  where  wood  for 
shipbuilding  purposes  is  difficult  to  obtain  concrete  may  prove 
cheaper  than  wood. 

Upkeep  expenses  are  larger  for  both  steel  and  wood. 

Repairs  cost  more  for  both  steel  and  wood  ;  but  since  concrete 


CONCRETE   LIGHTERS  AND   BARGES  67 

is  more  liable  to  local  damage  on  the  surface  than  steel  or  wood, 
the  greater  frequency  of  repairs  may  even  up  the  balance. 

The  lifetime  will  probably  be  longer  for  concrete  than  for 
either  steel  or  wood,  but  there  is  not  a  long  enough  experience 
of  concrete  craft  to  provide  data  for  a  definite  conclusion  ;  it 
should,  however,  certainly  be  the  case  in  tropical  countries, 
where  wood  hulls  are  liable  to  destruction  by  insects  and  steel 
hulls  to  destruction  from  corrosion. 

Strength  is  a  matter  of  design  and  can  be  made  sufficient 
with  any  of  the  materials  of  construction. 

Cargo  capacity  in  cubic  feet  per  ton  of  deadweight  carried  is 
greater  for  concrete  than  for  steel  or  wood.  This  is  due  to  the 
greater  weight  of  concrete,  requiring  the  provision  of  a  larger 
hull  for  a  given  deadweight  carrying  capacity.  This  is  an 
advantage  if  light  cargoes  are  to  be  carried,  but  a  disadvantage 
if  dimensions  are  restricted,  as  by  locks,  etc. 

Speed. — Experience  has  shown  that  in  spite  of  the  greater 
weight  of  concrete  lighters  they  do  not  require  appreciably 
greater  towing  power  than  steel  or  wood  lighters  of  equal  dead- 
weight capacity. 

Watertightness  is  a  necessity  for  all  lighters  ;  with  the  passage 
of  years  wood  lighters  often  open  up  at  the  seams  and  become 
leaky,  whereas  concrete  lighters  generally  become  perfectly  tight, 
even  if  they  leak  slightly  immediately  after  being  launched. 

The  fire-resisting  qualities  of  concrete  are  better  than  those 
of  steel  or  wood. 

Liability  to  marine  growth  is  about  the  same  for  the  three 
materials  ;  but  concrete  is  easier  to  clean  because  of  the  absence 
of  rivets  or  seams. 

The  time  required  for  construction  is  roughly  the  same  for  the 
three  materials  ;  but  in  out-of-the-way  places  concrete  lighters 
are  easier  to  construct  because  less  equipment  and  skilled  labour 
are  required,  and  all  the  materials  are  easily  handled  without 
the  use  of  cranes  or  machinery. 


CHAPTER   VI 
SHIPS   BUILT  IN   THE   UNITED   STATES 

The  Faith — U.S.  Shipping  Board  Investigations — The  First  U.S.  Standard 
Concrete  Ship — Ships  actually  completed — Oil-Tankers — Oil-Storage  generally. 

The  "  Faith." — One  ship  stands  out  prominently  in  the  develop- 
ment of  seagoing  concrete  ships,  the  Faith,  built  by  the  San 
Francisco  Shipbuilding  Co.  at  Redwood  City,  Cal.  This  was  the 
first  seagoing  ship  built  in  America  of  the  new  material ;  and  at 
the  time  of  her  completion  she  was  by  far  the  largest  concrete 
ship  in  the  world.  To  Mr.  W.  Leslie  Comyn,  president  of  the 
shipbuilding  company,  and  to  Messrs.  Allan  MacDonald  and 
Victor  Poss,  the  engineers  who  designed  the  ship,  great  credit  is 
due  for  their  splendid  and  successful  achievement. 

Construction  was  started  in  September  1917  on  the  meadow 
bank  of  a  narrow  estuary,  where  the  ship  was  launched  on 
March  14th,  1918.  A  couple  of  construction  sheds  were  all  that 
remained  to  indicate  that  a  large  ship  had  been  constructed  in 
the  place  ;  the  usual  heavy  cranes  and  equipment  of  a  shipyard 
were  conspicuous  only  by  their  absence. 

The  main  particulars  of  the  Faith  are  : 

Length  between  perpendiculars     .          .  320'  0" 

Breadth 44'  6" 

Depth 3<y  0" 

Freeboard,  loaded        .          .          .  6'  0" 

Load  displacement       ....  8, 150  tons 
Block  coefficient           .          .          .          .0-835 

Engines,  triple  expansion  type      .          .  1,700  I.H.P. 

Speed         ......  about  10  knots 

The  designed  deadweight  capacity  was  5,000  tons  ;  and  it  has 
been  stated  that  the  actual  deadweight  capacity  is  4,500  tons. 
The  latter  figure  would  correspond  to  a  "  light  "  weight  of  3,650 
tons  and  a  concrete  hull  weight  of  2,700  tons.  On  the  other 

68 


SHIPS  BUILT  IN  THE  UNITED  STATES 


69 


hand,  it  has  been  stated  also  that  the  hull  includes  520  tons  of 
reinforcement  and  1,500  cubic  yards  of  concrete  ;  at  138  Ib. 
per  cubic  foot  the  weight  of  concrete  would  be  2,495  tons,  which 
with  the  steel  would  give  a  hull  weight  of  3,015  tons  and  a 
deadweight  capacity  of  4,185  tons,  and  not  4,500  tons  as  given 
above.  The  author  does  not  know  which  of  these  deadweight 
figures  is  correct.  But  according  as  the  higher  or  lower  figure 
is  taken  the  relation  of  the  deadweight  capacity  to  the  loaded 


FIG.  32. — S.S.  Faith.     Ready  for  the  launch. 

displacement  is  55-2  per  cent,  or  51-3  per  cent.  Both  of  these 
percentages  are  higher  than  those  obtained  in  the  concrete  ships 
built  by  the  U.S.  Shipping  Board,  even  though  these  were  built 
of  light-weight  concrete. 

The  estimated  cost  of  the  Faith  was  $300,000  to  $400,000; 
the  actual  cost  was  $750,000. 

The  Faith  is  constructed  with  longitudinal  framing  between 
heavy  transverse  frames  spaced  16  feet  apart.  Deformed  bars 
provided'with  lugs  were  used  in  order  to  obtain  the  best  possible 


70        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

band  between  concrete  and  steel.  The  side  and  bottom  slabs 
are  4"  to  4J"  thick,  reinforced  diagonally  ;  the  shelter  deck  slabs 
are  3"  to  3J"  thick.  The  poop,  bridge,  forecastle,  and  main 
decks  are  of  wood,  as  is  also  the  ceiling  on  the  floors  in  the  cargo 
holds.  There  are  seven  watertight  bulkheads  of  concrete. 

The  Faith  was  launched  six  weeks  after  the  pouring  of  the 
concrete  was  started,  and  the  builders  were  so  satisfied  with 
the  launch  that  it  was  considered  unnecessary  to  give  the  hull 
a  trans- Pacific  towing  trial  as  originally  intended.  The  installa- 
tion of  the  machinery  was  therefore  started  right  away,  and  a 
couple  of  months  later  the  ship  was  completed  and  ready  for 
her  first  trip.  She  made  journeys  with  different  cargoes  to 
Vancouver,  Tacoma,  Honolulu,  Chile,  and  through  the  Panama 
Canal  to  New  York,  arriving  there  in  November  1918,  after 
having  travelled  some  12,000  to  15,000  miles.  While  in  New 
York  the  ship  was  inspected  by  many  engineers  and  shipping 
men,  who  all  declared  her  to  be  perfectly  sound  and  seaworthy. 
Some  minor  details  on  deck  might  have  been  improved,  such  as 
the  attachment  of  the  wood  deckhouses  and  the  winches.  A 
slight  leakage  of  fuel  oil  from  the  concrete  tank  forward  of  the 
engine-room  bulkhead  had  occurred  as  the  result  of  a  light  oil 
being  used  on  one  journey  ;  this  was  remedied  by  steaming  out 
the  tank  and  covering  the  inner  surface  with  spar  varnish,  and 
it  is  understood  that  no  further  percolation  of  oil  has  taken  place. 
The  ship  was  perfectly  watertight  ;  and  there  was  no  sweating 
in  the  holds.  In  rough  seas  she  exhibited  the  easy  movements 
and  lack  of  machinery  vibration  which  are  characteristic  of 
concrete  ships.  It  has  been  stated  that  cracks  have  occurred 
in  the  concrete  deck  as  the  result  of  longitudinal  strain  ;  if  this 
were  so,  they  seem  to  have  been  of  minor  importance  and  only 
in  the  upper  surface,  which  now  is  covered  with  an  inch  of  asphalt. 

During  the  spring  of  1919  the  Faith  arrived  in  London,  being 
the  first  concrete  ship  to  cross  the  Atlantic.  Subsequently, 
the  ship  was  sold  to  Italian  owners  and  is  at  present  trading  in 
European  waters. 

Mr.  W.  Leslie  Comyn,  builder  and  first  owner  of  the  Faith, 
whose  energy,  courage,  and  financial  backing  made  the  con- 
struction possible,  is  a  business  man,  not  an  engineer  ;  but  he 
knew  that  wood  ships  built  of  green  lumber  were  foredoomed 
to  failure,  and  he  realized  the  difficulties  involved  in  the  building 


SHIPS   BUILT  IN   THE   UNITED   STATES 


71 


of  steel  ships  on  the  West  Coast,  separated  from  the  rolling  mills 
by  almost  the  width  of  a  continent  whose  railways  were  suffering 
from  war-time  conditions.  When,  however,  he  proposed  the 
construction  of  concrete  ships  to  the  U.S.  Shipping  Board  he 
received  at  first  no  support.  There  is  no  need  to  dwell  on  the 
difficulties  he  encountered.  But  it  may  be  mentioned  that  in 
1920  the  American  Concrete  Institute  awarded  him  a  special 
medal  for  his  meritorious  work. 


FIG.  33. — S.S.  Faith  going  through  the  Panama  Canal. 

U.S.  Shipping  Board  Investigations.  — The  U.S.  Shipping 
Board  was  organized  to  meet  the  enormous  demand  for  tonnage 
at  the  time  when  America  entered  the  war.  The  large  majority 
of  the  ships  constructed  by  the  Board  were  of  steel,  but  several 
hundred  wood  ships  and  a  dozen  concrete  ships  were  also 
constructed. 

During  the  summer  of  1917  numerous  suggestions  as  to  the 
building  of  concrete  ships  were  made  to  the  Board  by  the  author 
through  his  brother,  Hermann  Fougner,  C.E.,  and  others,  but 
with  no  immediate  results.  In  October,  after  the  Namsenfjord 
had  demonstrated  by  actual  trials  the  possibilities  of  the  seagoing 
concrete  ship,  the  author  crossed  to  the  United  States  and  had 


72        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

several  conferences  with  leading  members  of  the  Board  ;  it  was 
suggested  that  the  Board  should  purchase  a  concrete  ship  then 
under  construction  in  Norway  by  the  author's  firm.  By  the 
new  year  the  suggestions  and  conferences  had  borne  fruit  to  the 
extent  that  it  was  decided  to  institute  a  concrete  ship  section  to 
investigate  the  whole  position  in  regard  to  concrete  ships. 

The  Concrete  Ship  Section  of  the  Board  was  organized  by 
Mr.  R.  J.  Wig,  who  was  first  the  Chief  Engineer  and  latterly  the 
Head  ;  it  was  staffed  by  expert  concrete  engineers  from  all  over 
the  country.  Very  elaborate  theoretical  investigations  were 
carried  out,  and  also  extensive  laboratory  experiments  and 
tests  of  structural  details  of  the  proposed  ships.  The  tests  were 
of  a  magnitude  beyond  the  resources  of  the  private  concrete 
shipbuilder.  For  example,  a  5,000-ton  machine  was  used  for 
testing  full-size  specimens  of  bottom  frames  ;  particulars  of 
experiments  and  tests  can  be  obtained  in  "  Structural  Laboratory 
Investigations  in  Reinforced  Concrete  made  by  Concrete  Ship 
Section,  Emergency  Fleet  Corporation,"  by  Mr.  W.  A.  Slater, 
in  the  Proceedings  of  the  American  Concrete  Institute  for  1919. 

Following  upon  the  investigations  and  tests  a  "  Special 
Report  ...  on  the  Advisability  of  Constructing  Concrete  Ships  " 
was  presented  by  Mr.  Wig  to  Mr.  E.  N.  Hurley,  the  Chairman  of 
the  Board,  on  5th  April  1918.  In  the  Report  it  was  stated  that 
the  concrete  ship  could  be  built  structurally  equal  to  any  steel 
ship  ;  that  the  concrete  ship  would  be  durable  for  several  years  ; 
that  the  cost  of  the  concrete  ship  complete  would  be  from  $100 
to  $125  per  ton  deadweight  ;  that  the  construction  of  concrete 
hulls  would  not  interfere  with  the  existing  Shipping  Board 
programme  for  the  building  of  steel  and  wood  ships ;  and  that,  if 
operations  were  started  at  once,  approximately  560,000  deadweight 
tons  of  concrete  ships  could  be  completed  by  the  end  of  1918. 

On  9th  April  1918  the  Chairman  of  the  Shipping  Board  sub- 
mitted to  the  Treasury  an  estimate  of  appropriation  covering 
an  emergency  fund  for  concrete  ships,  and  on  12th  April  it  was 
approved  and  authorized  by  President  Wilson. 

The  First  U.S.  Standard  Concrete  Ship.  — Appended  to  the 
report  of  5th  April  1918  was  a  description  of  the  proposed  ship 
whose  plans  had  been  fully  worked  out  by  the  Concrete  Ship 
Section,  and  which  provided  the  basis  for  the  estimate  of  the 
tonnage  which  could  be  constructed  by  the  end  of  1918.  The 


SHIPS  BUILT  IN  THE  UNITED  STATES 


73 


main  particulars  of  the  design,  and  the  estimated  weights,  were 
given  as  : 

Length  between  perpendiculars         .          .  268'  0" 

Breadth 46'  0" 

Depth  .......  28'  3" 

Draught         ......  23'  6" 

Weight  of  hull        .....  2,500  tons 

„          equipment  and  outfit        .          .         191 
„         propelling  machinery        .          .        206     ,, 
Margin  .          .          .          .          .  75     „ 

Light  displacement          ....      2,972  tons 

Weight  of  reserve  feed              .          .          .  80 

ordnance         .          .          .          .  23  „ 

fuel 300  „ 

stores 40  „ 

cargo      .                              .          .  2,760  „ 

Total  deadweight  ....      3,203     „ 

Load  displacement  .          .          .  6,175     „ 

Deadweight 
Load  displacement 

The  Cape  Fear  and  Sapona,  referred  to  in  Chapter  IV,  p.  46, 
are  of  this  class  ;  accordingly  the  actual  deadweight  capacity 
worked  out  at  about  3,078  tons,  and  the  cost  per  ton  deadweight 
at  about  $290. 

The  general  arrangement,  including  number  and  positions  of 
bulkheads,  was  very  similar  to  that  of  the  wood  standard  ship 
of  the  same  dimensions  ;  the  propelling  machinery  also  was 
similar  to  that  of  the  wood  standard  ship. 

Calculations  of  the  structural  strength  gave  the  following 
results  : 


Condition  of  Ship. 

Maximum 
Bending 
Moment. 

Maximum  Fibre  Stress. 

Maximum 
Fibre  Stress  in 
Concrete. 

Deck 
Reinforcement. 

Keel 
Reinforcement  . 

ft.  tons 

tons/in.2  ten. 

tons/in.2  comp. 

lb/in.2 

Ship  without  cargo,  hogging 

25,175 

5-53 

2-80 

728 

Ship  fully  loaded,  hogging  . 

37,000 

5-63 

2-95 

766 

comp. 

ten. 

Ship  without  cargo,  sagging 

14,400 

2-63 

1-28 

270 

Ship  light   but   with   cargo 

in  forward  hold  for  trim- 

ming purposes,  sagging    . 

11,960 

•2-19 

1-07 

210 

Ship  fully  loaded,  sagging   . 

9,400 

1-72 

0-84 

70 

74        SEAGOING  AND    OTHER   CONCRETE   SHIPS 

For  a  steel  ship  of  the  same  size  and  type  the  maximum  tensile 
stress,  for  the  conditions  for  calculation  used  above,  would  be 
from  5  to  8  tons  per  square  inch.  In  addition  to  the  "  structural  " 
stress  there  is  a  stress  due  to  bending  of  the  plating  between 
frames  due  to  water-pressure  ;  this  local  stress  is  seldom  taken 
into  account  in  steel  ships,  but  was  calculated  for  the  268  feet 
concrete  ship  and  was  found  to  add. about  3  tons  per  square  inch 
to  the  tensile  stress  in  the  reinforcement. 

The  strength  of  the  transverse  frames  was  investigated  for 
various  conditions  of  loading  and  various  immersions  of  the  ship, 


FIG.  34. — S.S.  Polias.     Built  for  the  U.S.  Shipping  Board  by  the  Fougner  Con 
crete  Shipbuilding  Co.,   New  York,   October   1919. 

upright  and  inclined.     The  maximum  permissible  stress  in  the 
steel  was  taken  at  15,000  Ib.  per  square  inch. 

The  bulkheads  were  designed  to  carry  a  head  of  water  up  to 
the  deck  on  either  side.  For  the  collision  bulkhead  and  the  aft 
peak  bulkhead  the  maximum  permissible  stresses  were  taken 
at  1,500  Ib.  per  square  inch  compression  on  concrete  and 
16,000  Ib.  per  square  inch  tension  on  steel ;  for  the  engine-room 
bulkheads  the  maximum  permissible  stress  on  the  steel  was  taken 
to  be  20,000  Ib.  per  square  inch.  In  the  design  of  bulkheads  for 
steel  ships  it  is  common  practice  to  use  a  permissible  stress  of 
22,000  to  23,000  Ib.  per  square  inch. 


SHIPS  BUILT  IN  THE  UNITED   STATES 


75 


The  deck  was  designed  to  carry  a  five  feet  head  of  water  ; 
this  was  in  excess  of  the  loading  assumed  for  the  steel  standard 
ships  then  being  built  for  the  Board. 

Ships  actually  Completed. — The  policy  of  the  Shipping  Board 
involved  the  concrete- ship- builder  preparing  his  yard  before 
commencing  actual  ship  construction.  As  things  happened, 
this  was  not  a  sound  policy.  There  was  a  large  number  of  yards 
turning  out  wood  ships,  ships  whose  success  was,  at  that  time, 
problematical  and  whose  failure  is,  now,  definite.  It  would  have 


JMfe 


FIG,   35,— S.S.  Selma. 


Built  for  the  U.S.  Shipping  Board  by  the  Fred.  T.  Ley 
Co.,  Mobile,  Ala. 


been  reasonable  to  place  one  or  two  of  these  yards  at  the  disposal 
of  the  Concrete  Ship  Section  so  that  one  or  two  trial  ships  could 
have  been  built  and  put  through  tests  at  a  very  early  stage  in 
the  programme,  with  decided  benefits  to  the  programme  as  a 
whole  in  the  way  of  indicating  possible  economies  of  time  and 
money.  Had  the  Concrete  Ship  Programme  not  been  kept 
entirely  as  a  thing  apart  from  the  Wood  Ship  Programme  it  is 
possible  that  by  the  spring  of  1919  a  large  fleet  of  seagoing 
concrete  ships  would  have  been  ready  for  service,  instead  of,  as 
was  actually  the  case,  the  first  ship  being  launched  in  December 


76       SEAGOING  AND   OTHER  CONCRETE  SHIPS 

1918  and  completed  in  October  1919.  The  estimate  of  the 
Concrete  Ship  Section  was  that,  without  interfering  with  the 
programme  of  wood  ship  construction,  about  560,000  deadweight 
tons  could  be  constructed  by  the  end  o"f  1918. 

The  Armistice  brought  the  Government  shipbuilding  pro- 
gramme to  a  sudden  termination.  Only  ships  whose  construction 
had  reached  a  certain  stage  were  completed  ;  the  result  was  that 
the  Concrete  Ship  Programme  was  reduced  to  the  following 
twelve  ships  : 

Name.  Dimensions.  Deadweight. 

Tons. 

Polias,  cargo  carrier    .          .      268'  0"  X  46'  0"  X  26'  6"       2,460 

Atlantus         „  .          .      250'  0"  X  43'  6"  X  26'  9"       2,542 

Cape  Fear      „  .          .      268'  0"  X  46'  0"  X  28'  3"       3,078 

Sapona  „  . 

Selma,  oil-tanker  .       '   .      420'  0"  X  54'  0"  X  36'  0"       6,380 

Latham          „  . 

Palo  Alto       „  . 

Peralta  „  . 

Cuyamaca      „ 

SanPasqual,, 


Dinsmore       „  . 

With  the  exception  of  the  Polias  and  Atlantus  the  ships 
completed  were  all  of  the  standard  type.  Most  of  the  ships 
were  of  the  so-called  7,500-ton  type.  This  type  was  designed 
after  the  3,500-ton  type,  it  having  been  decided  that  the  latter 
type  was  too  small  ;  the  change  in  policy  involved  a  delay  in 
the  building  programme.  The  cargo  carriers  were  delivered 
between  October  1919  and  January  1920,  and  the  oil-tankers, 
except  the  Moffit  and  Dinsmore,  between  May  and  September 
1920. 

The  Polias  was  constructed  by  the  Fougner  Shipbuilding  Co. 
(incorporated  by  the  author)  of  New  York  ;  the  order  was  given 
by  the  Concrete  Ship  Section  in  February  1918,  and  was  to  be 
followed  by  five  more.  The  design  was  prepared  by  the  Fougner 
Co.,  but  was  revised  in  various  details  by  the  Shipping  Board  and 
the  structural  design  was  subject  to  the  requirements  of  Lloyd's 
Register  ;  it  was  based  on  the  design  of  the  wood  standard  ship, 
so  that  similar  machinery,  equipment,  and  fittings  could  be  used. 


SHIPS  BUILT  IN  THE   UNITED   STATES  77 

The  superstructure  and  all  decks  were  of  concrete,  and  the  whole 
design  was  worked  out  more  heavily  in  details  than  was  originally 
anticipated.  There  is  no  doubt  that  much  steel  and  concrete 
could  have  been  saved  in  the  frames,  longitudinals,  and  super- 
structure. The  average  thicknesses  of  the  shell  and  deck  slabs 
were,  respectively,  5"  and  4|"  ;  these  do  not  appear  excessive  for 
a  ship  of  the  size,  but  would  probably  have  been  adequate  in 
association  with  a  five  feet  frame-spacing  instead  of  the  four  feet 
spacing  actually  used.  The  side  frames  were  8"  thick  by  24" 
average  depth.  The  deck  was  carried  by  two  continuous  girders 
forming  the  hatch  coamings  and  supported  by  widely  spaced 
pillars  of  9"  diameter  steel  pipe  filled  with  concrete. 

The  side  slabs  were  reinforced  with  two  layers  of  J"  square 
bars,  arranged  diagonally  in  both  directions.  The  deck  and 
bottom  slabs  had  a  layer  of  f"  square  bars  diagonally  each  way 
in  the  middle,  also  the  heavy  longitudinal  reinforcement,  of  1" 
square  bars,  near  the  upper  and  lower  faces.  The  frames  were 
reinforced  with  1J"  square  bars  near  the  inner  and  outer  faces 
and  the  keelsons  with  1J"  square  bars  near  the  tops. 

Had  "  light-weight  "  concrete,  as  described  in  Chapter  IX, 
been  used  about  400  tons  of  weight  of  concrete  would  have  been 
saved,  and  the  deadweight  carrying  capacity  correspondingly 
increased.  A  further  saving  of  weight  could  have  been  obtained 
by  making  the  keelsons  and  bottom  frames  of  T  section,  instead 
of  rectangular  section  ;  but  this  saving  would  have  been  achieved 
at  the  expense  of  increased  cost  for  centring.  Engineering  News- 
Record,  for  12th  December  1918,  contains  considerable  detailed 
information  on  the  structure  of  the  Polias  ;  but  the  ship's  name 
is  not  given  as  she  had  not  then  been  named. 

The  Polias  was  run  on  a  reef  off  Rockport,  Maine,  early  in 
1920  and  has  been  abandoned.  Particulars  of  the  damage  to 
the  ship  are  given  in  Chapter  VII. 

The  Cape  Fear  was  sunk  in  a  collision  with  S.S.  City  of  Atlanta 
in  Narragansett  Bay  during  October  1920  ;  she  lies  in  about 
125  fathoms  between  Castle  Hill  and  Rose  Island. 

Hence  there  remain,  in  all,  not  more  than  ten  seagoing 
concrete  ships  of  the  Shipping  Board  Programme  ;  there  may, 
in  fact,  only  be  eight  ships,  for  there  is  no  definite  information 
as  to  the  completion  of  the  Moffit  and  Dinsmore,  both  of  which 
had  accidents  during  launching. 


78        SEAGOING  AND  OTHER   CONCRETE   SHIPS 

The  Selma  and  Latham  have  been  in  the  service  of  the 
American  Fuel  Oil  and  Transportation  Co.,  who  informed  the 
author,  in  July  and  October  1920,  that  they  have  been  fine  steady 
ships  in  rough  weather,  entirely  oil-proof  and  watertight.  Both 
ships  have  grounded  against  the  harbour  jetty  at  Tampico,  and 
the  owners  estimate  that  the  costs  of  the  repairs  were  only  half 
what  would  have  been  incurred  by  steel  ships. 

The  Atlantus  was  until  recently  chartered  by  the  Clyde 
Steamship  Co.,  who  found  her  entirely  seaworthy,  but  rather 
heavy  ;  she  was  not  remunerative  in  the  service  where  she  was 
engaged,  due  principally  to  the  drop  in  freight  rates  and  the  high 
operating  expenses.  She  is  now  laid  up,  as  are  also  the  Sapona 
and  Peralta,  together  with  hundreds  of  steel  ships  owned  by  the 
Shipping  Board. 

The  Palo  Alto  is  believed  to  be  chartered  by  the  American 
Fuel  Oil  and  Transportation  Co.,  and  the  Cuyamaca  and  San 
Pasqual  by  the  France  and  Canada  Oil  Transportation  Co. 

From  the  above  brief  record  it  is  evident  that  very  little 
practical  experience  has  been  gained  from  these  concrete  ships  ; 
and  it  remains  for  the  future  to  prove  their  merits.  But  the 
author  desires  to  point  out  that  even  experience  of  these  ships 
will  not  be  by  any  means  decisive  for  the  future  of  concrete 
ships.  These  ships  constitute  only  a  link  in  the  chain  of  develop- 
ment, nothing  more.  Had  circumstances  permitted  their  designers 
and  builders  to  revise  and  improve  on  subsequent  ships,  there  is 
no  doubt  that  the  subsequent  ships  would  have  been  better  ships, 
both  cheaper  and  lighter. 

Further  information  on  the  U.  S.  Concrete  Ships,  also  informa- 
tion on  the  yards  in  which  they  were  built,  can  be  obtained  in 
the  Proceedings  of  the  American  Concrete  Institute  for  1919.  For 
example,  Mr.  J.  Glaettli,  jun.,  has  contributed  "  Problems  in  the 
Design  of  Reinforced  Concrete  Ships  "  ;  Mr.  R.  J.  Wig  has 
written  on  "  Methods  of  Construction  of  Concrete  Ships "  ; 
and  Mr.  A.  L.  Bush,  who  succeeded  Mr.  Wig  as  head  of  the 
Concrete  Ship  Section  of  the  Shipping  Board,  has  contributed 
"  Layout  and  Equipment  of  the  Government  Concrete  Ship- 
yards." These  papers  were,  however,  written  before  any  of  the 
ships  were  completed,  and  estimates  of  carrying  capacities,  costs, 
etc.,  given  in  them  require  modification  to  bring  them  into 
accordance  with  actual  facts. 


BUILT  IN  THE   UNITED   STATES  70 

Oil-tankers. — The  first  concrete  oil-carriers  ever  constructed 
were  built  in  the  spring  of  1918  by  the  Fougner  Concrete  Ship- 
building Co.  for  the  Standard  Oil  Co.,  of  New  York.  In  all  six 
ships  were  built,  comprising  three  harbour  barges  for  carrying 
oil  in  bulk  in  the  hull  compartments  and  in  cases  on  deck,  two 
canal  barges,  one  to  carry  oil  in  bulk  and  the  other  to  carry  asphalt 
in  cylindrical  steel  tanks,  and  a  hulk  for  the  storage  of  oil  in 
cases  and  in  barrels.  Investigations  during  the  last  few  years 
have  shown  that  the  common  grades  of  fuel  oils  can  be  retained 
safely  in  concrete  vessels,  without  leakage  or  injury  to  the  con- 
crete ;  but  before  carrying  out  the  contract  with  the  Standard 
Oil  Co.  the  Fougner  Co.  made  numerous  experiments  in  order 
to  confirm,  and  extend,  the  then  available  information  on  the 
matter. 

The  first  harbour  barge,  Socony  200,  is  98'  0"  by  31'  0"  by 
9'  6"  and  carries  about  400  tons  deadweight ;  the  general  arrange- 
ment is  shown  in  Fig.  36. 

Socony  200  is  of  similar  type  to  the  ordinary  New  York 
Harbour  deck  scow.  The  hull  is  divided  internally  by  four 
transverse  and  three  longitudinal  bulkheads,  all  oiltight  except 
the  centre  longitudinal  bulkhead,  which  is  pierced  by  large 
openings.  Only  the  three  central  compartments  are  arranged 
for  the  carriage  of  oil.  The  deck  is  of  concrete,  covered  with 
spruce  flooring  laid  on  nailing  strips.  Manholes  are  provided 
for  access  to  all  compartments.  Equipment  for  towing  and  for 
handling  cargo,  the  quarters  for  the  crew,  and  the  deck  fittings, 
etc.,  are  the  same  as  usually  arranged  by  the  Standard  Oil  Co. 
on  barges  of  the  size  and  type.  The  sides  of  the  barge  are  pro- 
tected by  three  horizontal  fenders,  6"  by  8",  of  white  oak  ;  between 
these,  at  the  ends  and  the  most  exposed  places  on  the  sides,  are 
fitted  solid  planking  of  pine,  as  can  be  seen  on  Fig.  37.  The 
pump-room  is  aft  under  the  deckhouse. 

The  two  other  harbour  barges  are  of  the  same  type  as  Socony 
200,  but  are  each  of  700  tons  deadweight. 

The  canal  barges  Socony  201  and  Socony  50  are  132'  0"  by 
12'  0"  by  12'  4",  and  carry  about  550  tons  deadweight  each. 
The  first  was  launched  in  November  1918  and  the  second  in 
January  1919.  Both  have  the  pump-room  amidships  and  the 
crew's  quarters  aft.  Socony  201,  which  carries  oil  in  bulk  in  the 
hull,  is  divided  by  six  transverse  and  one  longitudinal  bulkhead  ; 


'«# 


_-TQ.— 


o. 


> 


z 
o 

s 


2 
§ 

0) 

O 

+3 

W) 

1 
1 

TS 

a 

^ 


O 

7 


Z 

2   B 


o  ° 


80 


SHIPS   BUILT  IN  THE   UNITED   STATES 


81 


access  to  the  compartments  is  obtained  through  trunks  on  the 
deck.  Outside  fenders  are  fitted  as  on  Socony  200.  The  equip- 
ment and  pumping  plant  were  supplied  by  the  Standard  Oil  Co. 
These  barges  have  given  satisfactory  service  ;  but  they  have 
been  subject  to  minor  damages  through  rough  handling.  There 
is  no  kind  of  craft  which  receives  harder  usage  than  the  New 
York  Harbour  barge,  which  is  constantly  bumping  against  other 
barges,  and  against  tugs  and  wharves.  The  author  is  of  the 


FIG.  ST.— Socony  200.     The  Launch,  July  1918. 

opinion  that  concrete  is  not  at  present  suitable  for  such  craft ; 
but  the  great  advantage  of  the  fire-resisting  property  of  concrete, 
and  the  easy  upkeep  of  the  tanks,  are  points  in  favour  of  the  use 
of  concrete  for  oil  barges. 

The  oil  storage  hulk,  whose  general  arrangement  is  shown  in 
Fig.  39,  is  152'  9"  by  35'  8"  by  13'  3",  and  carries  1,200  tons  of 
oil  in  cases  or  barrels  on  deck  in  the  concrete  superstructure. 
The  hull  is  divided  into  watertight  compartments  by  four 
transverse  bulkheads  and  one  longitudinal  bulkhead,  with 
additional  subdivision  in  the  ends.  Two  open  longitudinal 
6 


82        SEAGOING  AND   OTHER  CONCRETE    SHIPS 

bulkheads  are  fitted  for  structural  reasons.  The  average  thickness 
of  the  sides,  bottom,  and  deck  is  3  inches.  The  walls  and  roof 
of  deckhouse  are  2  J"  thick  ;  a  concrete  fire  wall,  4"  thick,  encloses 
the  deckhouse  to  a  height  of  27  inches.  Above  the  fire  wall  are 
fireproof  sliding  doors  and  windows.  The  fittings  are  all  of  the 
Standard  Oil  Co.'s  usual  type.  Fenders  are  fitted  as  on  the 
barges. 

The  oil  storage  hulk  shown  in  Fig.  39  has  been  inspected  by 
a  member  of  the  Special  Committee  on  Concrete  Ships  and  Barges 


FIG.  38. — Socony  201.     550  tons  deadweight. 

of  the  American  Concrete  Institute ;  see  report  dated  21st  January 
1921.  .It  was  found  that  the  concrete  was  in  excellent  condition  ; 
some  cracks  were  discernible,  but  there  was  practically  no  leakage, 
and  the  barge  appeared  to  be  doing  its  work  satisfactorily. 

Oil  Storage  generally.  —  Until  recently  there  was  no  great 
demand  for  oil  stations,  for  the  good  reason  that  ships  burning 
oil  were  few  and  far  between.  Before  the  war  less  than  one  per 
C3nt.  of  the  world's  mercantile  tonnage  used  oil  fuel.  The  case 
is  different  now.  According  to  Lloyd's  Register,  in  1919-20 
eighteen  per  cent,  of  the  world's  mercantile  tonnage  used  oil 
fuel,  either  under  boilers  or  in  internal  combustion  engines  ; 


tc 

!c 

z 

Mp 

5 

5 

£L 

QL 

/^°i 

F\ 

POO 

—  ' 

—  T—  I"  1 

1 

O 

1 

j 

o  L       ! 

-»-  ^Q 

r     " 

Q              2H 

" 

£ 

1              0 

,__. 

i 

,       z 

£ 

O               I 

^  3 

...^_ 

—  r— 

b""!" 

o 

0 

o 

(1  * 

u  ± 

—  —  L     •! 

\^_Vi 

^ 

LLJ 


D 


z 

O 


•a 


Z  *'• 
O  " 
h  ^ 


. 

0 


84        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

in  1918-19  the  percentage  of  tonnage  using  oil  fuel  was  twelve. 
Of  the  total  tonnage  classed  in  1919-20,  47  per  cent,  was  arranged 
for  the  use  of  oil  fuel. 

In  view  of  the  development  in  the  use  of  oil  fuel  it  is  obvious 
that  oil  bunkering  stations  will  be  required  in  most  ports  ;  and 
owing  to  the  great  value  of  harbour  frontage  the  cost  of  shore 
stations  with  land  tanks  will  generally  be  prohibitive.  Hence, 
the  author  firmly  believes  that  within  the  next  ten  years  hundreds 
of  floating  oil  stations  of  the  type  shown  in  Fig.  39  will  be  in 
service.  For  this  type  of  craft  shipbuilding  concrete  is  un- 
questionably a  better  material  of  construction  than  any  other 
known  to-day ;  concrete  shows  up  to  advantage  on  the  scores 
of  cheapness,  durability,  low  upkeep  expenses,  and  safety  against 
fire  risks.  For  oil  hulks  the  question  of  fire  risk  is  of  the  utmost 
importance  ;  it  requires  no  great  imagination  to  conceive  what 
would  happen  if  hundreds  of  tons  of  flaming  oil  were  to  float  about 
in  a  harbour.  Neither  wood  nor  steel  is  fireproof,  but  concrete 
is.  And  by  storing  bulk  oil  only  in  inside  compartments  additional 
safety  against  the  risk  of  burning  oil  escaping  is  obtained. 

Craft  of  the  type  shown  in  Fig.  39  can  be  almost  box-like  in 
exterior  shape  and,  with  intelligent  supervision,  can  be  constructed 
by  local  labour  anywhere  in  the  world  ;  and  they  will  generally 
be  built  most  cheaply  at,  or  close  to,  the  place  where  they  are 
to  be  stationed.  Sand,  gravel,  and  in  most  countries  Portland 
cement  and  some  lumber,  can  be  procured  locally  or  shipped 
only  from  a  short  distance.  The  steel  will  generally  be  the  most 
difficult  element  to  obtain,  but  that  amounts  to  only  about  a 
fourth  of  the  steel  required  to  build  a  similar  ship  of  steel. 

Concrete  oil  containers  on  land  may  be  somewhat  outside 
the  scope  of  this  work,  but  many  features  are  closely  related  to 
those  of  the  floating  oil-tankers.  The  author  is  aware  that  the 
cylindrical  steel  tanks  above  ground  frequently  used  by  oil 
companies  may  in  certain  localities  be  quite  as  cheap  in  first 
cost  as  concrete,  or  even  cheaper.  But  the  matter  does  not 
end  there.  Very  often  it  is  necessary  to  arrange  the  fuel  oil 
reservoir  under  ground.  Concrete  is  then  better  suited  to  resist 
hydrostatic  or  earth  pressures,  has  greater  weight  against  upward 
pressure,  is  a  better  non-conductor  of  heat  and  cold,  lightning 
and  electrolysis,  does  not  rust,  and  is  fireproof.  Most  of  these 
points  are  also  in  favour  of  concrete  oil  tanks  above  ground. 


SHIPS  BUILT  IN  THE   UNITED   STATES  85 

In  this  connexion  some  interesting  papers  are  published  in 
the  Proceedings  of  the  American  Concrete  Institute,  vol.  xv. 
1919  :  "  The  Design  of  Reinforced  Concrete  Fuel-Oil  Reservoirs," 
by  H.  B.  Andrews  ;  "  Tests  of  Concrete  Tanks  for  Oil  Storage," 
by  J.  C.  Pearson  and  G.  A.  Smith  ;  "  The  Fire  Hazard  of  Fuel 
Oil,"  by  J.  W.  Lord. 


CHAPTER  VII 
DAMAGES  AND   REPAIRS 

M.S.  Askelad — M.S.  Nicanor— M.S.  Stier—S.S.  Polios. 

M.S.  Askelad.  —  At  7  a.m.  on  16th  January  1919  the  Askelad 
left  Havre  for  the  North  and,  following  instructions  from  the 
French  naval  authorities,  steered  a  course  close  to  the  shore  at 
low  speed.  There  was  a  strong  wind,  with  a  heavy  sea.  Full 
speed  ahead  was  ordered  at  midday,  and  during  the  afternoon 
Fecamp,  P.  Valery,  St.  Valery,  Pt.  d'Ailley,  P.  Treports  Pirere, 
and  Cayeux  were  passed.  At  9.15  p.m.,  in  a  strong  wind  with 
rain  and  a  heavy  sea,  the  ship  struck  a  sandbank  in  the  estuary 
of  the  River  Somme,  about  midway  between  Cayeux  and  Pte.  de 
St.  Quentin  ;  the  place  where  the  ship  struck  is  marked  "  A  " 
in  Fig.  40.  The  helm  was  put  hard  over  in  an  attempt  to  get 
the  ship  out  to  sea  ;  but  the  ship  was  driven  inshore,  coming 
to  rest  eventually  in  the  position  marked  "  B  "  in  Fig.  40,  about 
four  miles  from  "  A."  While  being  driven  ashore  the  ship 
bumped  violently  at  every  heave  of  the  sea,  and  this  continued 
after  she  was  brought  up  on  the  beach.  The  shocks  were  so 
severe  that  footing  could  not  be  kept  on  the  bridge.  Heavy  seas 
swept  the  ship,  and  the  starboard  lifeboat  and  the  dinghy  were 
carried  away.  After  a  time  the  shocks  became  less  violent  and 
by  about  11  p.m.  they  had  died  away.  Shortly  after  it  was 
found  that  the  ship  was  practically  high  and  dry  at  the  bow, 
and  a  member  of  the  crew  who  had  been  sent  out  to  investigate 
reported  that  it  was  possible  to  get  to  land  in  about  half  an  hour, 
and  that  it  was  necessary  to  wade  waist-deep  in  only  a  few  places 
on  the  way.  The  crew,  therefore,  took  the  opportunity  of  getting 
ashore  with  their  belongings,  also  some  food  and  water,  as  they 
were  afraid  that  the  ship  would  break  up  at  the  next  high  tide. 
In  a  report  to  the  owners,  dated  18th  January,  the  Captain 
stated  that  the  ship  was  still  bumping  violently  at  high  tide, 

86 


DAMAGES   AND   REPAIRS 


87 


though  the  weather  had  moderated  a  bit  ;    in  his  report  was  the 
remark  "  Strange  to  say,  the  ship  is  quite  tight."     During  the 


'•a 


II 
31 


i 


. 

O     oj 

^  I 

l-s 

o  t 

0 


day  of  the  17th  the  Captain  had  made  arrangements  for  a  tug 
to  come  from  St.  Valery  when  the  weather  moderated  ;  and  on 
the  forenoon  of  the  18th  an  attempt  was  duly  made  to  get  the 
ship  off,  tug  and  ship's  engines  working  together.  But  the 


88        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

attempt  was  unsuccessful.  The  tides  were  falling  and  the 
Captain  was  of  the  opinion  that  there  was  no  use  in  making  any 
further  attempt  at  refloating  before  the  beginning  of  February, 
.  .  .  "if  the  ship  holds  together."  "  Should  another  gale  spring 
up  there  is  every  probability  that  the  ship  will  break  to  pieces, 
although  she  seems  to  be  strong  as  a  rock."  (The  passages 
quoted  are  from  the  Captain's  report  dated  18th  January.) 

The  attempt  at  refloating  made  on  the  18th  January  was  a 
failure  in  part  through  the  main  engines  stopping  as  the  result  of 
the  cooling  water-pipes  becoming  choked  with  sand.  In  order  to 
get  over  this  trouble  and  ensure  that  the  engines  would  be  available 
when  needed  the  ship's  engineers  arranged  a  temporary  circulating 
system,  taking  supplies  from  the  sanitary  tank  on  the  bridge  to 
the  engines,  and  using  the  fore-peak  tank  as  a  storage  tank  from 
which  the  sanitary  tank  was  filled  ;  by  this  means  it  was  possible 
to  keep  the  engines  going  for  a  spell  at  each  high  tide. 

While  waiting  for  the  spring  tides  at  the  beginning  of  February 
the  ship  was  shifted  as  far  as  possible  every  high  tide.  As 
preparation  for  the  ensuing  high  tide  advantage  was  taken  of 
low  tide  to  dig  a  trench  in  the  sand  astern  of  the  ship,  and  also 
to  shift  the  kedge  and  stern  anchors  a  further  stage  out  to  sea. 
Then  at  each  high  tide  the  ship  was  taken  a  short  distance 
seawards,  the  efforts  of  the  main  engines  being  backed  by  the 
deck  machinery  pulling  on  wires  attached  to  the  anchors  out 
astern. 

Towards  the  end  of  January  the  Captain  was  enabled  to 
make  an  aeroplane  survey  of  the  channels  in  the  sands, 
by  courtesy  of  the  commanding  officer  of  the  aerodrome  at 
St.  Valery  ;  and  then  on  the  night  of  1st  February  the  ship  was 
floated  off  after  working  the  main  engines  and  pulling  on  the 
anchors  for  about  an  hour.  The  ship  was  then  taken  out  to 
deep  water  by  way  of  the  channels  surveyed  by  the  Captain, 
and  anchored  to  await  the  morning. 

On  6th  February  the  Askelad  left  St.  Valery  for  London, 
arriving  there  four  days  later.  Owing  to  a  strike  there  was  a 
difficulty  in  obtaining  dry  dock  accommodation,  but  a  survey 
with  the  ship  afloat  was  carried  out  by  representatives  of  the 
Norwegian  Veritas,  of  the  underwriters,  and  of  the  engine-builders. 
The  underwriters'  surveyor  reported  the  presence  of  various 
cracks  in  the  concrete.  There  were  cracks  in  the  centre  keelson 


DAMAGES  AND  REPAIRS 


89 


in  nearly  every  frame  space  in  the  holds  ;  in  most  of  the  bottom 
frames  in  the  holds  near  the  centre-line  ;  and  also  in  a  few  of 
the  bottom  frames  near  the  bilges.  But  these  cracks  seemed  to 
be  only  in  the  surface.  As  regards  the  deck,  there  were  cracks 
in  the  raised  portion  between  the  hatches,  and  in  the  portion 
between  No.  2  hatch  and  the  fore  end  of  the  deckhouse  ;  these 
cracks  all  radiated  from  the  hatch  coamings  at  the  centre-line 
of  the  ship,  and  were  probably  due  to  the  hold  pillars  underneath 


FIG.  41. — M.S.  Askelad  aground. 

being  forced  up  by  the  keelson  when  the  ship  was  bumping  over 
the  sandbanks.  Such  an  explanation  is  consistent  with  the 
presence  of  cracks  in  the  keelson  and  floors.  There  was  no 
indication  of  damage  to  the  two  forward  bulkheads,  but  there 
were  slight  cracks  in  the  bulkhead  between  the  engine-room  and 
No.  2  hold.  There  was  a  very  small  quantity  of  water  in  the 
bottom  of  the  ship  ;  but  the  pumps  had  not  been  in  use  since  the 
ship  left  St.  Valery.  This  water  was,  however,  completely  bailed 
out  and  the  bottom  carefully  examined  ;  only  a  few  cracks  were 
found,  and  these  were  in  the  bottom  frames,  low  down.  But 


90        SEAGOING   AND   OTHER   CONCRETE   SHIPS 

from  the  presence  of  the  water  it  was  inferred  that  there  was  a 
crack  through  the  bottom,  though  it  was  obviously  of  little 
importance.  In  the  report  from  which  this  information  was 
extracted  the  underwriters'  surveyor  expressed  the  opinion  that 
the  ship  was  sufficiently  seaworthy  to  go  to  Grimsby,  but  that 
she  should  be  dry- docked  there  for  examination  of  the  bottom 
and  of  the  propeller  shafts. 

The  Askelad  accordingly  left  the  Thames  on  7th  March,  and 
arrived  at  Grimsby  on  the  10th,  where  she  was  dry- docked  two 
days  later.  It  was  found  that  some  cement  finish  had  been 
rubbed  off  and  that  there  was  a  slight  leak  in  No.  2  hold.  A 
few  patches  of  cement  plaster  were  applied  by  the  crew,  but  no 
other  work  was  done  on  the  concrete  hull.  There  was  a  certain 
amount  of  work  done  to  the  machinery,  the  principal  item  being 
the  renewal  of  the  starboard  propeller  on  account  of  the  loss  of 
a  blade  during  the  grounding  or  the  refloating  ;  but  no  work  was 
called  for  as  the  result  of  any  defect  in  the  concrete  hull. 

After  the  survey  at  Grimsby  the  Askelad  was  immediately 
put  into  service  and  was  not  again  dry-docked  until  September, 
when  she  was  surveyed  at  Moss  as  required  by  the  Norwegian 
Department  of  Shipping  in  terms  of  the  yearly  certificate  of 
seaworthiness.  Following  on  this  survey  minor  repairs  were 
carried  out  on  the  deck  fittings,  and  the  cement  finish  on  the  deck 
was  repaired  in  a  few  places.  The  total  bill  for  the  work  done 
at  this  time  amounted  to  kr.  1879-31  (about  £100)  ;  of  this 
amount  the  cost  of  the  cement  used  was  about  two  pounds,  by 
far  the  major  portion  being  due  to  alteration  to  deck  fittings. 
It  can  safely  be  said  that  the  total  cost  of  repairing  the  concrete 
hull  after  the  grounding  on  the  French  coast  did  not  exceed  twenty- five 
pounds. 

Captain,  officers,  and  crew  deserve  great  credit  for  the  work 
done  in  salving  the  ship.  In  recognition  of  this  work  the  under- 
writers presented  gold  watches  and  chains  to  captain  and  chief 
engineer. 

The  grounding  of  the  Garry  Owen,  referred  to  in  Chapter  I, 
did  much  to  establish  the  reputation  of  the  iron  ship  ;  the 
grounding  of  the  Askelad  has  equally  established  the  reputation 
of  the  concrete  ship. 

M.S.  "Nicanor." — This  ship  was  built  by  the  author's  firm, 
and  is  of  practically  the  same  dimensions  and  type  as  the  Namsen- 


DAMAGES   AND   REPAIRS  91 

fjord.  During  the  night  of  llth  April  1919  she  ran  on  a  sub- 
merged rock  near  South  Torgersogap,  when  on  a  passage  to 
Christiania  ;  subsequently  the  strong  current  in  the  channel 
carried  her  over  on  to  another  rock  which  held  her  abaft  amid- 
ships. After  vainly  trying  to  get  the  ship  off  by  her  own  power 
a  call  was  sent  out  for  a  salvage  boat,  and  one  arrived  during  the 
following  day.  The  salvage  boat  put  a  hawser  on  to  the  bows 
of  the  Nicanor,  which  were  nearly  under  water,  intending  to 
pull  alongside  by  means  of  her  winch  ;  but  the  pull  on  the  hawser, 
instead  of  bringing  the  salvage  boat  alongside,  slewed  round  the 
bows  of  the  Nicanor,  causing  her  to  slide  slowly  off  the  rock 
and  dive  to  the  bottom  of  the  channel,  where  she  rested  almost 
on  end  in  six  fathoms  of  water.  A  month  later  the  Nicanor 
was  salved  and  taken  to  a  steel  ship  builder  for  repairs. 

A  survey  of  the  damage  showed  that  there  were  ten  holes 
in  the  concrete  hull,  some  cement  finish  rubbed  off,  both  bilge 
keels  damaged,  and  the  wood  fender  on  the  stern  damaged. 
There  was  damage  to  machinery  and  accommodation  as  the 
result  of  immersion,  and  damage  also  to  deck  fittings  and  gear. 
The  costs  of  the  repairs,  as  assessed  by  Magistrate  for  insurance 
claim  purposes,  were  : 

£ 

Repairs  of  bottom  and  stem     ....     250 
,,  deckhouse,    crew's   quarters,    painting, 

etc 175 

,,  rails,  boat  davits,  boat  deck          .          .        75 

,,  engines     .          .          .          .          .          .     250 

,,  rigging,  hatches,  etc.          .^         .          .50 

Equipment  lost  or  destroyed     ....     200 

Dock  dues  150 


Total        .          .1,150 

The  ship  in  her  damaged  condition  was  valued  at  £2,800. 
Repairs  were  very  expensive  in  1919,  but  even  so  the  concrete 
hull  could  easily  have  been  repaired  for  £100  to  £150,  instead  of 
£250  as  given  above.  To  the  £100  or  £150  there  must  be  added,  of 
course,  the  dry  dock  dues  ;  but  these  would  not  amount  to 
£150,  as  given  above,  on  account  of  repairs  to  concrete,  for  in 
the  particular  case  the  time  in  dry  dock  was  determined  by  the 
other  repairs,  the  concrete  work  only  taking  a  week. 


92        SEAGOING  AND   OTHER  CONCRETE   SHIPS 

M.S.  "  Stier." — During  a  dense  fog  on  the  evening  of   17th 
December  1918,  when  bound  for  Christiania,  the  Stier  touched 
bottom  in  the  Christianiafjord,  but  she  slid  over  the  obstruction 
and  continued  on  her  way  ;    the  holds  were  sounded  and  found 
to  be  dry.     Shortly  afterwards  the  ship  struck  hard    against  a 
small  reef,  but  again  she  slid  off  ;    this  time,  though,  there  was 
leakage,  for  the  fore  peak  was  found  to  be  flooded.     Both  holds 
were  again  sounded  and  found  to  be  dry,  the  collision  bulkhead 
holding  good  ;    and  the  ship  was  able  to  make  port  under  her 
own  power. 

The  Stier  was  not  repaired  until  several  weeks  had  elapsed, 
and  she  made  the  passage  round  to  Moss  for  repairs  in    her 
damaged  condition.     The  work  was  carried  out  by  a  steel  ship 
building  firm,  and  the  costs  as  assessed  by  Magistrate  for  insurance 
claim  purposes  were  : 

£ 
Repairs  to  bow         ......     325 

Repairs  to  keel  aft  .....          1 

Removing  interior  ceiling  for  inspection     .          .       60 
Overhauling  winches,  etc.  ....       65 

Dock  dues  209 


Total        .          .    £660 

The  damage  to  the  concrete  hull  could  in  this  case  also  have 
been  made  good  for  a  much  smaller  figure  than  given  above  ; 
in  fact,  the  author's  firm  would  gladly  have  done  the  work  for 
£175,  but  for  personal  reasons  the  owner  wanted  the  steel  builder 
to  do  the  work.  And  as  the  steel  ship  builder  had  no  experience 
of  concrete,  and  got  no  assistance  from  the  classification  society, 
since  the  Stier  is  not  classed,  the  repairs  were  not  carried  out  so 
fast  or  so  cheaply  as  might  have  been. 

S.S.  "Polias." — This  ship,  while  southward  bound  to  Norfolk 
in  light  trim,  was  run  on  to  the  CiJley  Ledge,  off  the  coast  of 
Maine,  on  6th  February  1920.  At  the  time  of  the  grounding 
the  ship  was  running  at  full  speed,  making  probably  9J  to  10 
knots.  Eleven  of  the  crew  put  off  in  one  of  the  boats  against 
the  captain's  orders  ;  they  have  not  been  heard  of  since,  nor 
has  any  trace  been  found  of  their  boat.  The  remainder  of  the 
crew,  about  thirty  men,  stayed  by  the  ship  overnight  and  were 
taken  off  by  coastguards. 


FIG.  42. — M.S.  Stier  in  dry  dock  after  grounding. 


93 


94        SEAGOING  AND   OTHER  CONCRETE   SHIPS 

A  few  weeks  after  the  accident  an  inspection  was  made  by 
a  representative  from  the  U.S.  Shipping  Board,  a  few  days  of 
calm  weather  having  allowed  a  diver  to  make  a  careful  examina- 
tion of  the  underwater  damage.  The  ship  was  found  to  be 
lying  on  a  shelving  rock,  with  the  stern  in  about  1 1  feet  of  water, 
and  the  bow  nearly  submerged,  at  low  tide.  In  grounding  the 
ship  had  evidently  passed  between  two  jagged  rocks,  for  the 
sides  were  ripped  open  practically  from  end  to  end,  the  depths 
of  the  openings  varying  from  about  two  feet  to  about  seven  feet. 


HHHHHHE 


FIG.  43. — S.S.  Polias  aground  on  Cilley  Ledge. 

But  the  damage  was  found  to  be  confined  almost  entirely  to 
the  shell,  although  in  a  few  places  small  pieces  had  been  torn 
out  of  the  frames.  A  careful  examination  of  the  above  water 
portion  of  the  ship  failed  to  discover  structural  damage  ;  the 
ship  had  evidently  not  deflected,  as  there  were  no  cracks  dis- 
cernible in  the  deck.  Further  information  on  the  report  of  the 
Shipping  Board  representative,  Mr.  Lewis  R.  Ferguson,  can  be 
obtained  in  Engineering  News-Record  for  4th  March  1920. 

In  the  latter  part  of  April  1920,  Mr.  Ferguson  received  a 
letter  from  the  officer  in  charge  of  the  coastguard  near  the  Cilley 
Ledge  ;  in  the  letter  was  the  following  interesting  statement  : 


DAMAGES  AND   REPAIRS  95 

"  Yes,  the  old  steamer  still  lies  in  the  same  position,  and 
tho'  severe  storms  have  washed  over  and  around  her  since  you 
were  here  she  remains  the  same  ;  no  apparent  change  has  been 
noticed,  and  with  the  exception  of  the  paint  washing  off  I  do 
not  believe  the  hull  has  been  damaged  in  the  least. 

"  I  am  still  of  the  opinion  that  the  concrete  boat  is,  if  kept 
off  the  rocks,  the  strongest  built  ship  afloat,  as  no  steel  or  wood 
ship  would  have  stood  the  severe  storms  that  have  beaten 
against  the  Polias  during  the  past  two  months  with  such  little 
damage  being  done." 

The  above  statement  should  provide  plenty  of  food  for  thought 
for  those  who  will  contemplate  the  probable  fate  of  a  steel  ship 
of  even  the  best  construction  after  running  on  to  these  rocks 
at  a  speed  of  ten  knots. 

Owing  to  the  depression  in  shipping  the  Polias  has  not  been 
salved.  She  will  probably  remain  for  many  years  in  her  exposed 
position,  bearing  testimony  to  the  strength  and  durability  of 
the  seagoing  concrete  ship. 

Striking  confirmation  of  the  remarks  in  the  previous  para- 
graph comes  to  hand  at  the  moment  of  going  to  press  in  tho 
following  paragraph  (reprinted  from  The  Times  Trade  Supplement 
(Engineering  Section,  p.  173)  of  22nd  July  1922),  which  it  has 
been  ascertained  refers  to  the  Polias  : 


A   WRECKED    CONCRETE    SHIP 

In  February  1920  a  concrete  steamship,  250  feet  long,  struck  a  sub- 
merged reef  of  rock  off  Port  Clyde,  U.S.A.  Inspection  of  the  vessel  in 
the  following  July  is  said  to  have  revealed  no  damage  except  a  hole  in 
the  bottom,  the  concrete  hull,  decks,  and  bulwarks  being  in  perfect 
condition  in  spite  of  the  heavy  seas  to  which  they  had  been  subjected. 
A  second  inspection  in  August  1921  disclosed  little  change  in  the  state 
of  the  vessel.  Some  of  the  timber  upper  works  had  been  washed  away, 
but  the  hull  appeared  as  solid  as  the  rock  on  which  it  rested.  According 
to  recent  reports  the  hull  is  still  intact  after  exposure  to  the  sea  for  over 
twenty-eight  months.  The  chief  of  the  salvage  crew  is  reported  to  have 
stated  that  a  steel  or  timber  vessel  would  not  have  survived  for  more 
than  three  months  in  the  same  situation.  The  test  is  one  showing  very 
clearly  the  high  resistance  of  reinforced  concrete  to  exceptionally  severe 
shocks  and  stresses. 


CHAPTER    VIII 

COMPARISONS    OF    CONCRETE    SHIPS    WITH    STEEL 

SHIPS 

First  Cost — Units  of  Material  and  Labour  per  Ton — Examples  of  Costs — 
Speed — Strength — Running  Expenses — The  Future  of  the  Concrete  Ship. 

First  Cost. — It  is  very  difficult  to  present  reliable  and  useful 
information  on  first  cost.  Current  market  prices  do  not  give 
any  guidance,  since,  as  is  well  known,  during  the  present  depres- 
sion in  shipping  ships  change  hands  at  prices  far  below  the  first 
costs.  The  majority  of  shipbuilders  do  not  care  to  publish  their 
cost  data  ;  or,  if  they  do  publish  any  of  it,  they  do  so  in  such 
a  form  that  it  does  not  give  a  true  idea  of  the  cost  of  production. 
Further,  the  war-time  inflation  of  wage  rates  and  costs  of  materials 
introduces  a  disturbing  element.  Accordingly,  the  figures  used 
in  the  comparison  below  can  be  taken  as  only  approximately 
correct.  But  they  are  based  on  actual  costs  of  completed 
ships  ;  the  concrete  ships  were  built  by  the  author's  firm,  the 
steel  ships  by  a  firm  on  the  west  coast  of  Norway.  Only  hulls 
are  taken  into  account  in  the  comparison,  since  engines  and 
equipment  are  practically  the  same  whether  the  hull  be  of  concrete 
or  steel. 

Concrete,  Ships 

Units  ol  Material  and  Labour  per  Ton. — The  materials  used 
are  :  Concrete  of  mixture  1  :  1-85  :  0-65  ;  steel  reinforcement  of 
mild,  medium  grade,  round  rods,  and  second  quality  pine  or 
spruce  boards  for  centring  : 

One  ton  (2,240  Ib.)  of  concrete  in  the  finished  hull  afloat  requires  : 

f  1-9  barrels  of  Portland  cement  (at  3-8  cub.  ft.). 
Concrete-^  14    cub.  ft.  of  sand. 
{  5    cub.  ft.  of  gravel. 
10  cub.  ft.  wood  for  centring. 

96 


CONCRETE   AND   STEEL   SHIPS   COMPARED        97 
24  hours  of  carpenter  work  on  centring. 


,  14  concreting. 

Labour  5       . 

10         ?>  plastering  nnish. 

,,          erecting  scaffolding  and  launching. 
100  per  cent,  of  cost  of  labour  should  be  added  for 
supervision  and  all  other  charges. 

One  ton  (2,240  Ib.)  of  steel  reinforcement  in  the  finished  hull 
afloat  requires  : 

2,240  Ib.  of  steel  delivered  in  the  yard. 

116  hours  of  bending,  cutting,  and  placing. 

100  per  cent,  of  actual  cost  of  labour  for  charges. 

Notes. — Wood  materials  for  the  centring  are  assumed  to  be 
used  three  times. 

Average  wages  for  masons  and  helpers  should  be  figured  for 
plastering  the  cement  finish.  One  cubic  yard  of  concrete  weighs 
1-7  tons. 

The  cost  of  a  concrete  hull  is  found  by  adding  the  weights  of 
concrete  and  steel  multiplied  by  their  respective  unit  prices.  It 
is  best  to  calculate  separately  the  weight  and  cost  of  equipment. 

The  estimate  can  be  summarized  as  follows  : 

Weight.         Cost. 

Concrete      ..... 
Reinforcement      .... 
Engines  and  equipment 
Deadweight  .... 

Displacement  loaded  in  tons  (at  2,240  Ib.)  : 

Steel  Ships 

The  material  used  is  steel  of  ordinary  shipbuilding  quality. 
One  ton  (2,240  Ib.)  steel  in  the  finished  hull  afloat  requires  : 

2,240  Ib.  of  steel  delivered  in  the  yard. 
104  hours  of  shaping,  erection,  and  riveting. 
100  per  cent,  of  actual  cost  of  labour  for  charges. 

Notes. — The  number  of  working  hours  per  ton  is  an  average 
of  actual  figures  from  seven  ships,  varying  in  sizes  from  1,600 
tons  to  8,000  tons  deadweight  built  between  1900  and  1919. 

The  100  per  cent,  addition  to  the  actual  cost  of  labour,  for 

7 


98        SEAGOING  AND   OTHER  CONCRETE   SHIPS 

supervision  (including  foremen),  overhead  charges,  tools,  etc.,  is 
also  an  average  figure,  which  may  vary  considerably.  Sometimes 
this  item  is  covered  by  adding  a  much  lower  percentage,  namely 
between  30  and  50  per  cent.,  to  the  cost  of  labour  plus  materials  ; 
and  this  in  the  end  gives  practically  the  same  figure. 

The  deadweight  capacity  is  known,  and  it  is  useful  to  express 
the  weight  of  hull  in  terms  of  the  deadweight.  For  concrete 
ships  the  concrete  and  reinforcement  should  be  figured  separately. 
In  the  preceding  chapters  it  has  been  shown  that  the  majority 
of  concrete  ships  have  been  constructed  far  too  heavily.  The 
Askelad  and  Faith  have  practically  the  same  ratio  of  weight  of 
hull  to  deadweight ;  but  since  the  exact  quantities  of  steel  and 
concrete  are  known  only  for  the  Askelad,  data  from  her  con- 
struction are  used  in  the  present  calculations. 

Concrete  Ships 

For  Askelad  :  1,076  tons  deadweight  and  628-0  tons  con- 
crete give  0-583  ton  (0-343  cub.  yd.)  concrete  per  ton  deadweight ; 
1,076  tons  deadweight  and  105-0  tons  reinforcement  give  0-0976 
ton  reinforcement  per  ton  deadweight. 

Steel  Ships 

The  average  gross  weight  of  steel  required  in  constructing  the 
hulls  of  seven  ships,  varying  in  size  from  1,600  to  8,000  tons 
deadweight,  was  found  to  be  36-5  per  cent,  of  the  deadweight. 
On  account  of  waste  in  cutting  plates,  punching  rivet-holes,  etc., 
this  amount  is  reduced  by  about  one-tenth  in  the  finished  hulls  ; 
but  the  gross  quantity  of  steel  should  naturally  be  used  as  a 
oasis  in  determining  the  cost  of  production.  Therefore  : 

0-365  ton  of  steel  is  required  per  ton  deadweight. 

Examples  of  Costs. — From  the  above  data  the  costs  of  con- 
structing hulls  of  concrete  and  steel  can  be  readily  estimated 
for  any  prices  of  labour  and  materials.  In  Chapters  II,  III,  and 
IV  are  given  the  actual  costs  of  some  concrete  ships,  but  these 
are  of  no  permanent  interest ;  neither  are  war-time  prices  of 
steel  ships.  Comparisons  of  practical  value  can  only  be  made 
when  and  where  it  is  desired  to  build  either  concrete  or  steel 
ships,  and  the  costs  must  be  based  on  the  local  prices  of  labour 


COMPARATIVE   EXAMPLES   OF   COSTS  99 

and  materials.  It  is  of  course  impossible  to  say  what  these 
may  be  five  or  ten  years  hence,  when  shipbuilding  perhaps  again 
becomes  normal  after  the  present  depression,  but  the  following 
figures  are  assumed  in  order  to  give  an  example  : 

It  is  desired  to  build  a  cargo  carrier  of  ordinary  type,  either  of 
concrete  or  steel.     Deadweight  capacity  to  be  2,000  tons. 
Unit  prices  of  materials  and  labour  : 

£    s.    d. 

Portland  Cement,  per  barrel  .  .  .  0  10  0 
Sand  and  Gravel,  per  cub.  ft.  .  .  .  004 
Second  quality  Pine  and  Spruce,  per  cub.  ft.  020 
Steel  Reinforcing  Rods  per  ton  (2,240  Ib.)  .  15  0  0 
Steel  Plates,  Angles,  etc.,  per  ton  (2,240  Ib.)  1600 

Average  wages  for  skilled  tradesmen  and  their  helpers  : 

£    s.    d. 

Carpenters  per  hour  .  .  .  .  .016 
Concrete  workers  per  hour  .  .  .013 

Brick- masons  (Plasterers)  per  hour  .  .020 
General  labour  per  hour  .  .  .  .010 
Steel  shipbuilders  per  hour  .  .  .019 

Concrete  Hull 

£    s.    d. 

Portland  Cement,  1-9  barrels  @  10/-  .  .  0  19  0 
Sand  and  Gravel,  19  cub.  ft.  @  41  .  .  064 
Second  quality  lumber,  10  cub.  ft.  @  2/-  .  100 
Carpenter  work,  24  hours  @  1/6  .  .  1  16  0 

Concreting,  14  hours  @  1/3  .  .  .  0  17  6 
Plastering,  10  hours  @  2/-  .  .  .100 
Scaffolding  and  launching,  18  hours  @  I/-  .  0  18  0 
100  per  cent,  of  cost  of  labour  charges  ,  4116 


One  ton  of  Concrete      .          .          .£1184 

£    s.    d. 

Steel  reinforcement,  1  ton  @£15  .  .  1500 
Placing,  bending,  etc.,  116' hours  @  I/-  .  5  16  0 
100  per  cent,  of  cost  of  labour  for  charges  .  5  16  0 

One  ton  of  Steel  Reinforcement     ,   £26  12     0 


100       SEAGOING  AND   OTHER  CONCRETE  SHIPS 

£    s.    cl 

0-583  ton  of  Concrete  @  £11  8s.  4d.     .          .        6   13     1 
0-0976  ton  of  Steel  Reinforcement  @  £26  12s.     2  12     0 

Cost  per  ton  deadweight  .  .£951 
2,000  tons  deadweight  @  £9  5s.  Id.,  £18,508  6s.  Sd. 

Steel  Hull 

£     s.    d. 

Steel  plates,  angles,  etc.,  1  ton  @  £16  .          .      1600 
Shaping,  riveting,  erection,   etc.,    104  hours 

@  1/9    . 920 

100  per  cent,  of  cost  of  labour  for  charges  .       920 

One  ton  of  Shipbuilding  Steel  , .  £34  4  0 

0-365  ton  Steel  @  £34  4s £12  10  0 

Cost  per  ton  deadweight  .  .  £12  10  0 
2,000  tons  deadweight  @  £12  10s.,  £25,000. 

From  the  above  it  is  seen  that,  with  the  assumed  prices  of 
materials  and  labour,  the  steel  hull  costs  :  £25,000-£18,508  = 
£6,492  more  than  the  concrete  hull. 

In  other  words  :  The  hull  of  a  steel  ship  is  35  per  cent,  more 
expensive  in  first  cost  than  that  of  a  concrete  ship  of  the  same  type 
and  deadweight  capacity. 

Speed. — Several  elements  combine  to  form  the  total  resistance 
of  a  ship  to  motion  through  water  ;  but  by  far  the  most  important 
element  in  the  case  of  ordinary  cargo  carriers  is  the  skin  resistance, 
which  amounts  to  nearly  80  per  cent,  of  the  total  resistance  in 
the  case  of  a  steel  ship.  Skin  resistance  is  due  to  the  friction  of 
the  water  against  the  sides  and  bottom.  Obviously  the  smoother 
the  immersed  surface  the  less  the  resistance.  On  steel  ships  the 
projecting  plate  edges  and  rivet-heads  contribute  appreciably 
to  the  skin  resistance  ;  Mr.  G.  S.  Baker  has  shown  in  a  paper  to 
the  North- East  Coast  Institution  of  Engineers  and  Shipbuilders 
in  1915  that  as  compared  with  a  smooth  hull  the  additional 
resistance  due  to  plate  edges  and  rivet- heads  amounts  to  about 
10  per  cent.  Accordingly,  due  to  her  smooth  surface,  a  concrete 
ship  may  be  expected  to  show  appreciably  less  resistance  than 
a  steel  ship  of  the  same  dimensions  and  form.  And  it  is  with 


CONDITIONS  AFFECTING   SPEED  101 

this,  as  well  as  watertightness,  in  mind  that  the  author  recom- 
mends the  application  of  a  cement  mortar  finish  to  the  outer 
surfaces  of  the  hulls  of  concrete  ships  ;  with  careful  trowelling 
the  finished  surfaces  are  very  smooth  and  dense. 

How  far  vibration,  rolling,  and  pitching  affect  the  speed  of  a 
ship  can  probably  not  be  accurately  ascertained,  except  through 
actual  trials  of  full-size  sister  ships  built  of  different  materials. 
But  it  is  a  fact,  proved  beyond  doubt,  that  concrete  ships  have 
easier  movements  and  much  smaller  vibrations  than  similar 
steel  ships.  In  the  author's  opinion  these  advantages,  which 
are  due  to  the  greater  stiffness  and  heavier  sides  of  the  hull, 
account  to  a  considerable  extent  for  the  good  speeds  generally 
obtained  by  concrete  ships. 

Not  long  ago  the  author  had  an  excellent  opportunity  of 
observing  the  movements  in  the  hull  of  a  steel  ship.  It  was  in 
the  North  Atlantic  in  November  during  a  raging  gale.  The  ship 
was  a  large  passenger  steamer  about  six  hundred  feet  long,  and 
practically  empty  as  regards  cargo — 600  tons  of  matches  was  all 
she  carried — but  the  bottom  ballast  tanks  were  filled.  The 
"  panting  "  of  this  ship  was  most  remarkable,  especially  when 
she  was  hit  a  hard  blow  in  the  fore- part  of  her  bottom,  while 
riding  on  the  crest  of  another  wave.  And  it  seems  logical  that 
excessive  resistance  must  be  caused  by  such  an  undulating 
surface  passing  through  water  ;  for  instance,  a  pliable  spear 
vibrating  through  the  air  will  not  travel  as  far  as  one  that  is  more 
rigid.  It  should  also  be  remembered  that  the  vibration  is  two- 
fold in  steel  ships  driven  by  engines  ;  as  well  as  the  temporary 
deflections  of  the  hull  from  external  forces  of  the  waves,  there 
is  a  perpetual  vibration  due  to  the  engines. 

That  considerable  deflections  do  take  place  in  steel  ships  is 
amply  proved  by  shorn-off  rivets,  and  in  many  other  ways.  It 
is  equally  certain  that  they  do  not  affect  the  concrete  ship  to  any 
appreciable  extent,  otherwise  cracks  would  at  once  appear  in 
the  surface  of  bottom  and  sides,  even  from  deflections  of  fractions 
of  an  inch.  No  such  cracks  have  been  seen  on  any  of  the  concrete 
ships  built  by  the  writer,  which  have  now  been  in  use  for  nearly 
four  years. 

Concrete  ships  are,  however,  in  the  matter  of  speed  subject 
to  one  disadvantage,  namely,  increased  displacement  for  given 
deadweight.  The  increased  displacement  involves  increased 


102       SEAGOING  AND  OTHER  CONCRETE  SHIPS 

wetted  surface,  resulting  in  increased  skin  resistance.  But  this 
disadvantage  will  be  diminished  as  the  weights  of  concrete  hulls 
are  reduced. 

Strength.  —  In  preceding  chapters  it  has  been  shown  that 
concrete  ships  have  been  built  having  sufficient  strength  for 
normal  service,  and  even,  as  in  the  case  of  the  Askelad,  sufficient 
strength  for  abnormal  service. 

Running  Expenses. — The  principal  elements  which  combine 
to  make  up  the  total  running  expenses  are  :  Interest  on  capital 
invested  ;  Depreciation  ;  Insurance  ;  Bunkers  and  Stores  ; 
Crew's  Wages  and  Provisions  ;  Handling  of  Cargo;  Brokers' 
Fees  ;  Harbour  and  Dock  Dues  ;  Upkeep  and  Repairs.  It  is 
the  sum  of  these  charges  on  revenue  and  items  of  expenditure 
which  is  of  prime  importance  to  the  shipowner. 

Several  items  of  running  expenses  are  the  same  for  concrete 
ships  as  for  steel  ships  of  the  same  deadweight,  namely,  Bunkers, 
Stores,  Crew's  Wages,  Provisions,  Handling  of  Cargo,  and 
Brokers'  Fees.  Harbour  Dues  are  slightly  larger  for  concrete 
ships,  since  they  are  based  on  register  tonnage,  which  is  larger 
for  concrete  ships  than  for  steel  ships  of  the  same  deadweight 
on  account  of  increased  dimensions.  The  charge  made  on 
revenue  to  cover  Interest  on  Capital  invested  is  less  for  a  concrete 
ship  than  for  a  steel  ship  of  the  same  deadweight ;  this  item,  of 
course,  depends  entirely  on  first  cost,  or  purchase  price,  and  so 
the  reduced  cost  of  construction  of  the  concrete  ship  involves 
an  appreciable  saving  in  running  expenses. 

The  cost  of  Insurance  ought  to  be  rather  less  for  concrete 
ships,  but,  in  fact,  underwriters  have,  up  till  now,  demanded 
higher  rates  than  for  steel  ships.  The  result  is  that  some  Nor- 
wegian owners  of  concrete  ships  have  discontinued  insurance, 
except  for  complete  loss,  as  they  have  found  it  unnecessary  to  pay 
exorbitant  premiums  to  cover  costs  of  repairs  which  often  are 
carried  out  by  the  crew  in  a  few  hours. 

The  greatest  savings  in  the  running  expenses  of  concrete 
ships  are  accomplished  on  the  scores  of  Depreciation,  Upkeep,  and 
Repairs.  After  four  years  of  service  there  are  no  signs  of  attack 
from  sea-water,  rust  spots  on  the  unpainted  concrete  surfaces, 
nor  other  signs  of  depreciation  on  the  ships  built  by  the  author's 
firm.  A  barge  with  pile  driver,  now  belonging  to  the  Moss 
Harbour  Authorities,  was  docked  for  inspection  on  20th  June 


RUNNING  EXPENSES   COMPARED  103 

1921,  after  having  been  continuously  in  sea- water  for  four  years 
and  four  days.  The  surface,  when  cleaned  of  seaweeds,  was 
just  as  smooth  and  solid  as  it  was  four  years  ago.  In  no  place 
was  the  finish  rubbed  off  or  loose.  The  docking,  cleaning,  and 
coating  of  the  barge — which  up  to  then  had  received  no  painting 
—with  coal  tar  was  done  at  the  trifling  cost  of  about  £9.  This 
little  ship  furnished  proof  of  an  interesting  fact,  namely,  that 
outside  cement  finish  can  be  applied  a  considerable  time  after 
the  concrete  has  hardened,  and  yet  will  adhere  perfectly.  The 
hull  was  concreted  on  23rd  April  1917  and  the  following  few 
days.  The  sides  were  plastered  with  cement  finish  between  4th 
and  9th  May,  and  the  under  side  of  bottom  between  15th  and 
19th  May  1917. 

The  matter  of  repairs  has  been  treated  at  some  length  in 
Chapter  VII. 

Actual  figures  for  comparing  the  running  expenses  of  concrete 
and  steel  ships  under  exactly  the  same  conditions  have  not  so 
far  been  available.  One  reason  for  this  is  the  annual  survey 
demanded  by  the  classification  societies  or  by  the  Director  of 
Shipping.  Another  reason  is  the  already  mentioned  attitude  of 
the  underwriters,  who  unnecessarily  increase  the  insurance 
premiums.  The  principal  concrete  shipowner  in  Norway,  Mr. 
Thygo  Sorensen,  of  Christiania,  expressed  his  opinion  to  the 
author  substantially  as  follows  : 

"  There  is  no  doubt  that  concrete  ships  are  cheaper  to  run, 
out  up  to  the  present  considerable  extra  expense  has  been 
incurred  by  the  annual  survey  (for  steel  ships  only  every  four 
years),  and  by  the  fact  that  even  the  inner  ceiling  must  be 
removed  for  inspection.  Outside  inspection  of  the  hull  ought 
to  be  sufficient,  as  long  as  it  seems  to  be  perfectly  sound." 

This  is  a  reasonable  attitude,  and  it  will  probably  be  only  a 
matter  of  time  before  concrete  ships  are  surveyed  no  more  fre- 
quently than  steel  ships.  Many  cases  of  minor  damage  have 
occurred,  where  the  concrete  surface  has  suffered  abrasion  from 
collisions  with  docks,  etc.,  but  as  regards  seagoing  ships  such 
damage  could  nearly  always  have  been  avoided  with  more  care. 
In  a  letter  to  the  designers,  Messrs.  Leopold  Walford,  Ltd., 
London,  express  their  opinion  on  the  upkeep  expenses  of  the 
S.S.  Armistice  (see  Chapter  XIII),  estimating  these  to  average 
about  one-fifth  of  those  for  a  steel  ship  working  under  the  same 


104       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

conditions.  They  base  their  views  on  figures  noted  for  three 
typical  steel  ships,  which  respectively  compare  to  the  Armistice 
as  2  J  to  1,  3  to  1,  and  10  to  1.  Their  experience  covers  1 J  years 
of  service. 

The  Future  of  the  Concrete  Ship. — There  are  no  technical 
difficulties  to  prevent  the  building  of  concrete  ships  of  much 
greater  size  than  have  already  been  built.  The  author  believes, 
however,  that  with  the  present  materials  of  construction  the 
future  of  the  concrete  ship  lies  in  sizes  from  about  2,000  tons  to 
6,000  tons  deadweight.  For  short  voyages  between  harbours  of 
limited  depth  the  smaller  sizes  are  required,  and  for  oversea 
cargo  service  the  larger  sizes  should  probably  be  economical. 
The  construction  of  concrete  ships  of  larger  sizes  than  6,000  tons 
requires  relatively  more  steel  reinforcement  in  the  hull  and  more 
equipment  in  the  builder's  yard,  as  the  centring  is  heavier  to 
handle  ;  it  is  doubtful  whether  the  cost  per  ton  deadweight 
would  be  lower. 

When  a  really  satisfactory  light-weight  concrete  is  invented, 
with  better  elastic  properties  than  at  present,  it  will  involve  a 
great  improvement  and  radically  change  the  interior  details  of 
the  hull.  All  frames  will  probably  be  eliminated  ;  in  other 
words,  the  steel  reinforcement  will  be  embedded  in  a  thick  slab, 
where  it  will  act  as  frames  spaced  very  close  together,  and  so 
will  be  very  effective.  The  weight  of  reinforcement  will  be 
reduced  for  three  reasons  : 

On  account  of  the  thick  concrete  sides  absorbing  more  of  the 
shearing  strains,  without  the  aid  of  reinforcement. 

Because  the  steel  near  the  inner  and  outer  faces  can  be  better 
utilized  in  a  thick  slab,  having  greater  "  effective  depth." 

Because  with  a  concrete  able  to  stretch  slightly  more  than 
the  present  material,  high  carbon  steel  of  much  greater  strength 
can  be  employed  as  reinforcement  to  full  advantage.  Such 
steel  cannot  be  used  in  the  construction  of  steel  ships,  where 
the  material  is  exposed  to  twisting  and  bending  as  well  as  tension 
and  compression  ;  but  as  reinforcement  it  can  be  used  safely. 

The  exterior  form  of  the  ship  should  be  maintained  exactly 
as  desired  by  the  naval  architect,  but  the  elimination  of  interior 
frames  would  improve  facilities  for  loading  cargo.  The  cubic 
capacity  for  "  bale "  goods  would  be  increased  considerably 
because  the  massive  slab  would  not  be  nearly  as  deep  as  the 


FUTURE   OF   THE   CONCRETE   SHIP  105 

present  frames,  and  the  saving  on  inside  centring  and  work  in 
placing  the  reinforcement  is  obvious.  Such  construction  of  sides 
would  permit  greater  deflections,  so  reducing  greatly  the  risk  of 
injury  from  local  blows,  and  the  thickness  would  prevent  minor 
damage  from  penetrating. 

The  author  firmly  believes  that  this  improvement  in  concrete 
will  come,  and  that  it  will  play  a  very  important  part  in  the  ship- 
building of  the  future.  He  does  not  dream  of  a  concrete  with  an 
elasticity  of  steel  or  wood,  nor  does  he  expect  the  material  to 
possess  great  tensile  strength — the  steel  reinforcement  supplies 
that ;  but  he  does  believe  that  a  concrete  will  be  developed 
which  will  stretch  rather  more  than  the  present  material.  The 
new  concrete  will  stretch  sufficiently  to  prevent  cracks  forming 
around  a  reinforcement  of  high  carbon  steel  worked  to  perhaps 
thirty  per  cent,  higher  tensile  stress  than  is  used  now.  The 
author  anticipates  also  that  this  concrete  will  be  between  one- 
half  and  two-thirds  of  the  weight  of  the  present  material.  In 
conclusion  the  author  may  sum  up  his  views  as  follows  : 

"  With  the  present  materials,  seagoing  concrete  ships  have 
been  built  cheaper  than  steel  ships.  They  are  seaworthy  and 
strong,  with  low  upkeep  expenses  and  no  higher  fuel  consumption 
than  steel  ships  of  the  same  deadweight.  On  account  of  their 
larger  cubic  capacity  and  better  insulating  qualities  against 
temperature  changes,  they  are  especially  suited  for  cargoes  like 
lumber,  coke,  ice,  fruit,  etc." 

Up  to  now  seagoing  concrete  ships — or  rather  the  builders 
of  such  ships — have  hardly  had  a  fair  chance  to  develop  the 
new  construction,  on  account  of  war  conditions  and  the  following 
depression  with  over-production  of  steel  and  wood  tonnage. 
It  is  not  true  that  the  seagoing  concrete  ship  was  a  "  war- pro- 
duct "  or  poor  substitute  doomed  to  sink  into  oblivion.  It 
would  have  arrived  regardless  of  the  war,  and  shows  even  in 
its  present  crude  state  of  development  some  advantages  over 
steel  ships,  and  a  decided  superiority  over  seagoing,  engine- 
driven,  ships  of  wood.  Some  years  from  now,  when  the  excess 
of  war-tonnage  has  been  absorbed  and  when  demand  for  tonnage 
begins  to  overtake  the  supply,  the  next  chapter  of  concrete  ship- 
building will  commence.  It  will  call  for  special  reinforcement 
for  concrete  ships,  manufactured  to  save  field  work,  a  lighter 
concrete,  greater  refinements  of  construction,  especially  of  the 


106       SEAGOING  AND   OTHER  CONCRETE  SHIPS 

centring  and  placing  of  the  concrete.  The  classification  societies 
will  have  collected  experience  from  the  concrete  ships  in  use, 
and  will  no  doubt  be  less  exacting  in  their  demands  ;  and  the 
result  will  be  a  type  of  ship  built  with  one-third  the  amount  of 
steel  used  in  a  steel  ship,  and  that  material  thoroughly  and 
permanently  protected  against  corrosion. 


CHAPTER   IX 
SHIPBUILDING  CONCRETE 

Introductory — Portland  Cement — Water — Aggregate — Impurities  in  Aggre- 
gate— Sand — Light-weight  Aggregate — Proportions  of  Mixture — Mixing — 
Placing  and  Curing — Steam  Curing — Freezing — Vibration,  Pressure,  etc. — 
Compressive  Strength — Shear  Strength — Bond  Strength — Elasticity — Water- 
tightness — Contraction  and  Expansion — Trass  Concrete — Action  of  Sea-water 
— Action  of  Oils,  etc. — Repairs — Fire-resisting  Power. 

Introductory. — Concrete  is  probably  the  most  commonly  used 
material  in  modern  constructional  work.  Not  only  are  founda- 
tions and  underground  work  almost  exclusively  built  of  this 
material,  but  superstructures  such  as  buildings,  bridges,  dock 
walls,  etc.,  are  built  of  it  to  an  extent  that  could  not  have  been 
conceived  fifty  years  ago.  This  vast  development  was  made 
possible  by  two  inventions — the  manufacture  of  artificial  Portland 
cement,  and  the  reinforcing  of  concrete  by  steel. 

The  concrete  of  former  days  did  not  possess  the  strength  or 
reliability  of  the  present  reinforced  material,  and  could  not  be 
used  to  build  an  ordinary  flat  roof  or  floor.  It  was  employed 
only  as  a  mortar  or  for  vault  and  arch  construction  like  stone  or 
brick  work.  The  difference  between  the  poorest  grade  of  iron 
known  to  our  ancestors  and  the  shipbuilding  steel  of  to-day  is 
no  greater  than  that  between  the  concrete  of  fifty  years  ago  and 
that  used  for  the  building  of  concrete  ships.  But  there  is  still 
ample  room  for  improvement  in  concrete  whether  for  land  or 
ship  work. 

Concrete  for  land  work  and  concrete  for  ship  work  differ 
materially.  Concrete  for  land  work  should  be  : 

of  strength  and  mixture  as  specified  or  as  required  by 
local  building  regulations. 

composed  of  durable,  clean  materials, 
as  cheap  as  possible,  while  of  the  specified  quality. 
107 


108       SEAGOING  AND   OTHER  CONCRETE   SHIPS 
Concrete  for  ship  work  should  be  : 

of  maximum  strength  and  elasticity, 
of  maximum  water  tightness. 

of    minimum    weight,    subject    to    the    strength    being 
sufficient. 

In  this  case  the  cost  is  of  minor  importance. 

The  fact  that  the  cost  is  of  minor  importance  in  concrete 
for  ship  work  may  seem  to  be  surprising.  But  it  is  explained  by 
the  other  fact  that  the  total  cost  of  all  the  concrete  materials  in 
the  hull  of  a  seagoing  concrete  ship  amounts  only  to  about  five 
per  cent,  of  the  total  cost  of  the  ship  complete  ;  of  this  five 
per  cent,  the  Portland  cement  makes  up  about  three  per  cent. 
and  the  aggregate  about  two  per  cent.  For  lighters,  in  which 
there  is  no  machinery  and  little  deck  equipment  and  fittings, 
the  cost  of  the  concrete  materials  amounts  to  about  10  per  cent, 
of  the  total. 

Concrete  consists  of  the  following  materials  : 

Portland  cement. 

Water. 

Fine  aggregate  (sand). 

Coarse  aggregate  (gravel  or  broken  stone). 

Of  these  elements  the  cement  and  water  are  active,  and  the 
others  inactive.  It  is  obvious  that  the  cement  is  of  great  influence 
in  determining  the  quality  of  concrete  ;  but  it  is  only  recently 
that  investigations  have  shown  that  the  amount  of  water  is  also 
a  matter  of  vital  importance. 

Portland  Cement. — It  is  known  from  structures  still  in  exist- 
ence that  various  kinds  of  cement  were  used  even  in  ancient 
times.  The  cements  used  were,  however,  different  from  the 
Portland  cement  used  to-day  ;  they  were  entirely  of  natural 
origin,  whereas  the  present-day  article  is  a  factory  product. 
Natural  cements  are  still  available,  but  they  are  rarely  used 
since  they  are  of  erratic  quality  and  are  inferior  in  strength  to 
the  manufactured  article. 

Early  in  the  nineteenth  century  the  Frenchman  Vicat  tried 
to  produce  an  hydraulic  cement  by  burning  a  mixture  of  limestone 
and  clay  at  a  high  temperature,  but  without  satisfactory  results. 
At  about  the  same  time  the  Englishman  Joseph  Aspdin  worked 


SHIPBUILDING  CONCRETE  109 

on  the  same  lines  and  finally  succeeded.  Aspdin  took  out 
patents  on  his  method,  and  called  the  product  Portland  Cement 
because  in  colour  and  hardness  it  resembled  the  building  stone 
obtained  from  Portland.  Owing  to  lack  of  chemical  knowledge 
the  early  material  was  uncertain  in  quality  and  so  was  not  much 
used.  The  accidental  discovery  that  waste  products  from  the 
burning  when  ground  to  a  fine  powder  made  a  better  cement 
was  the  foundation  of  the  present  methods  of  manufacture. 
And  practical  experience,  together  with  extensive  chemical 
investigation,  has  made  Portland  Cement  a  reliable  material  of 
exact  chemical  proportions  whose  properties  need  never  be 
doubted  if  it  is  obtained  from  a  reputable  manufacturer. 

Portland  Cement  is  a  finely  pulverized  mixture  of  burnt  clay 
and  limestone,  having  approximately  the  following  analysis  : 

Silica.  Alumina.     Iron  Oxide.     Calcium  Oxide.    Magnesia. 

Si02  A1203         Fe203  CaO  MgO 

19-25%         5-9%          2-4%  60-64%        1-2-5% 

The  raw  materials  are  obtained  from  many  sources,  but  they 
are  always  proportioned  in  such  a  manner  that  the  chemical 
analysis  of  the  finished  product  agrees  closely  with  the  figures 
above. 

The  development  in  the  use  of  Portland  Cement  can  be 
roughly  appreciated  from  figures  of  production.  In  the  United 
States  the  annual  production  was  990,000  barrels  in  1895,  and 
about  94  million  barrels  in  1917,  practically  a  hundredfold 
increase  in  22  years.  In  Germany  29  factories  produced  in 
1877  2,200,000  barrels  ;  in  1907  the  production  was  26,750,000 
barrels  from  87  factories  ;  and  at  the  outbreak  of  the  war  the 
annual  output  was  approximately  50  million  barrels. 

Setting  and  Hardening. — According  to  latest  investigations 
during  and  after  manufacture,  Portland  Cement  contains  three 
principal  compounds  which  harden  by  hydration  : 

Tri-calcium  silicate  (3CaO  .  Si02). 
Di-calcium  silicate  (2CaO  .  Si02). 
Tri-calcium  aluminate  (3CaO  .  A1203). 

Of  these  tri- calcium  silicate  seems  to  have  the  greatest 
cementing  quality.  It  is  the  last  constituent  completed  during 
manufacture  and  is  formed  by  combination  of  calcium  oxide 


110       SEAGOING  AND   OTHER   CONCRETE  SHIPS 

(CaO)  with  2CaO  .  Si02.  Some  free  CaO  is  also  present  in  amounts 
depending  on  the  burning  process.  The  iron  oxide,  magnesia, 
alkalies,  etc.,  have  little  effect  on  the  three  principal  cementing 
compounds,  but  are  added  to  bring  about  a  combination  of  CaO 
with  alumina  (A1203)  and  silica  (Si02)  during  manufacture. 
Hardening  takes  place  in  the  following  order  : 

Tri-calcium  aluminate  (3CaO  .  A1203)  ;  Tri-calcium  silicate 
(3CaO  .  Si02)  ;  Di-calcium  silicate  (2CaO  .  Si02). 

When  water  is  added  to  Portland  Cement  these  compounds 
are  first  of  amorphous  and  later  both  crystalline  and  amorphous 
character,  acting  much  like  ordinary  glue.  The  hardening 
continues  under  water,  as  the  minerals  are  nearly  insoluble. 
The  initial  set  of  Portland  Cement  is  no  doubt  due  to  hydration 
of  tri-calcium  aluminate. 

Specification. — All  ordinary  requirements  and  tests  have 
been  standardized  in  detail  and  are  practically  identical  in 
countries  where  Portland  Cement  is  manufactured.  In  general 
the  consumer  will  find  it  most  practical  to  send  samples  for 
testing  to  laboratories  which  specialize  in  this  work.  A  descrip- 
tion of  such  tests  can  readily  be  obtained  from  any  testing 
laboratory  or  from  any  handbook  on  ordinary  concrete  con- 
struction. Briefly  the  following  requirements  must  be  fulfilled  : 

(1)  Definition. — Portland  Cement  is  the  product  obtained  by 
finely  pulverizing   clinker   produced   by   calcining   to   incipient 
fusion  an  intimate  and  properly  proportioned  mixture  of  argil- 
laceous and  calcareous  materials,  with  no  additions  subsequent 
to  calcination  excepting  water  and  calcined  or  uncalcined  gypsum. 

I.  Chemical  Properties 

(2)  Chemical  Limits. — The  following   limits   should   not   be 
exceeded  : 

Per  cent. 

Loss  on  ignition         .          .          .          .          .  4-00 

Insoluble  residue        .....  0«85 

Sulphuric  anhydride  (S03)  .          .          .  2-00 

Magnesia  (MgO) 5-00 

II.  Physical  Properties 

(3)  Specific  Gravity. — The   specific  gravity  of  cement   shall 
not  be  less  than  3-10  (3-07  for  white  Portland  Cement).     Should 


SHIPBUILDING  CONCRETE  111 

the  test  of  cement  as  received  fall  below  this  requirement  a  second 
test  may  be  made  upon  an  ignited  sample.  The  specific  gravity 
test  will  not  be  made  unless  ordered. 

(4)  Fineness. — The  residue  on  a  standard  No.    200  l   sieve 
shall  not  exceed  22%  by  weight. 

(5)  Soundness. — A  pat  of  neat  cement  shall  remain  firm  and 
hard,  and  show  no  signs  of  distortion,  cracking,  checking,  or 
disintegration  in  the  steam  test  for  soundness. 

(6)  Time  of  Setting. — The  cement  shall  not    develop   initial 
set  in  less  than  45  minutes  when  the  Vicat  needle  is  used  or 
60  minutes  when  the  Gillmore  needle  is  used.     Final  set  shall 
be  attained  within  10  hours. 

(7)  Tensile  Strength. — The  average  tensile  strength  in  pounds 
per  square  inch  of  not  less  than  three  standard  mortar  briquettes 
composed  of  1  part  cement  and  3  parts  standard  sand,  by  weight, 
shall  be  equal  to  or  higher  than  the  following  : 

Age  at  Test,  Storage  of  Tensile  Strength, 

days.  Briquettes.  Ib.  per  sq.  in. 

7  1  day  in  moist  air,  200 

6  days  in  water 

28  1  day  in  moist  air,  300 

27  days  in  water 

(8)  The  average  tensile  strength  of  standard  mortar  at  28 
days  shall  be  higher  than  the  strength  at  7  days. 

The  above  example  is  extracted  from  Standard  Specifications 
and  Tests  for  Portland  Cement  worked  out  by  a  special  Committee 
representing  the  U.S.  Government,  American  Society  of  Civil 
Engineers,  and  American  Society  for  Testing  Materials  in  1916. 

Storage. — The  best  Portland  Cement  may  be  destroyed  before 
use  by  being  stored  in  a  wrong  manner.  The  storage  house 
must  be  absolutely  weatherproof  with  floor  at  least  2  feet  above 
ground  level  and  free  air  circulation  under  the  floor.  Instead 
of  windows  there  should  be  covered  openings  for  ventilation  and 
the  cement  must  be  placed  at  least  8  inches  away  from  external 
walls  and  the  floor.  It  should  be  stored  so  that  inspection  and 
samples  can  be  readily  taken  from  each  shipment,  which  is  kept 
separate  until  approved. 

Cement  in  bags  piled  on  top  of  each  other  frequently  tends 

1  i.e.  200  wires  per  inch. 


112       SEAGOING  AND   OTHER  CONCRETE   SHIPS 

to  harden  from  the  pressure  ("  warehouse  set  ").  This  does  no 
harm  and  is  broken  up  by  tossing  the  bags  about,  as  the  hardening 
is  not  due  to  any  chemical  action  in  the  cement. 

A  moderate  amount  of  seasoning  improves  Portland  Cement, 
which  sometimes  contains  a  little  free  lime,  which  causes  expansion 
during  hardening.  By  seasoning  this  is  first  slaked  and  then 
changed  to  calcium  carbonate,  which  does  not  swell  when 
hydrated. 

Water. — It  is  generally  advisable  to  use  fresh  water  when 
making  concrete.  But  sea-water  can  be  used  in  rich  mixtures, 
such  as  shipbuilding  concrete  ;  the  results  of  extensive  tests 
do  not  indicate  any  detrimental  effects  from  the  use  of  sea- water 
with  such  mixtures. 

The  water  should  be  of  ordinary  clean,  drinking  quality ; 
free  from  impurities  such  as  oils,  acids,  alkalies,  or  vegetable 
matter.  Acids  or  alkalies  are  easily  detected  by  litmus  paper, 
oils  are  detected  by  iridescent  surface  films,  and  vegetable  matter 
and  other  impurities  either  float  in,  or  give  a  bad  taste  to,  the 
water.  If  in  any  doubt,  chemical  analysis  and  tests  should  be 
made  to  decide  the  effect  of  the  water  on  the  strength  and 
hardening  of  the  cement. 

Water  reacts  chemically  with  Portland  Cement  and  forms  a 
binding  composition  of  amorphous  and  crystalline  character, 
which  unites  the  grains  of  fine  and  coarse  aggregate  in  the  con- 
crete. It  also  carries  the  cement  particles  over  all  surfaces  of 
the  aggregate  and  promotes  close  adhesion  by  filling  with  the 
cementing  substance  all  minute  irregularities  between  the 
aggregate  filler.  Further,  a  certain  amount  of  water  is  required 
to  lubricate  the  concrete  mass  in  order  to  reduce  friction  between 
the  particles  and  allow  the  concrete  to  be  properly  placed  in  the 
forms. 

The  binding  strength  of  cement  depends  upon  the  interlacing 
of  crystals,  and  crystallization,  as  is  well  known,  will  only  take 
place  from  a  saturated  or  supersaturated  solution.  If  insufficient 
water  is  supplied  the  chemical  reaction  will,  naturally,  stop 
before  it  is  completed.  Too  much  water  is  also  bad,  because  it 
dilutes  the  cementing  compound  and  reduces  the  strength  of 
the  binding  substance,  even  if  this  afterwards  is  partly  recovered 
when  the  water  evaporates.  Further,  small  air  bubbles  are  often 
enclosed  by  superfluous  water  and  adhere  to  the  surfaces  of  the 


SHIPBUILDING   CONCRETE  113 

aggregate,  sometimes  even  to  the  extent  of  displacing  the  finest 
aggregate  ;  this  defect  frequently  occurs  also  as  the  result  of 
excessive  mixing.  The  various  elements  in  concrete,  cement, 
water,  fine  aggregate,  and  coarse  aggregate,  all  occupy  definite 
amounts  of  space.  If  the  concrete  is  placed  in  watertight  forms 
all  the  materials  remain  in  the  mass  ;  whereas  if  the  forms  are 
not  watertight  some  of  the  water  will  escape,  either  before  or 
after  the  concrete  has  hardened.  But  when  the  forms  are  removed 
any  water  remaining  uncombined  can  escape,  either  by  evapora- 
tion, gravity,  or  capillary  action  ;  and  the  escape  of  uncombined 
water  leaves  spaces  in  the  concrete.  Hence  an  excess  of  water 
reduces  the  strength  of  concrete  ;  it  also  reduces  the  durability, 
for  porous  concrete  is  subject  to  penetration  by  water  or  other 
liquids  of  chemical  action  which  may  freeze  with  a  bursting 
effect,  so  causing  deterioration. 

A  result  of  excess  water  is  frequently  evident  in  cases  where 
concreting  has  been  stopped  for  a  day.  A  chalky  substance— 
laitance — gathers  on  the  surface  of  the  material  last  poured  ; 
this  is  composed  of  light  particles  of  inactive  cement  which  have 
floated  to  the  top  and  remain  there  as  a  creamy  substance, 
possessing  no  strength,  and  so  detrimental  to  the  attainment  of 
a  good  joint. 

The  strongest  and  most  waterproof  concrete  is  secured  by 
thorough  mixing  with  the  addition  of  the  minimum  amount  of 
water  for  complete  hydration  of  the  cement.  The  amount  of 
water  should  be  determined  by  means  of  actual  tests  such  as  are 
described  below.  The  water  should  be  added  gradually,  and 
the  cement  and  aggregate  should  be  mixed  dry  before  any  water 
is  added.  The  results  of  some  tests  showing  the  effects  of  varying 
amounts  of  water  are  given  in  Table  C  on  p.  126. 

Aggregate. — The  inactive  elements  of  concrete,  sand,  gravel, 
crushed  stone,  etc.,  all  classed  as  aggregate,  make  up  about 
80  per  cent,  of  the  total  volume.  And  the  quality  of  this  ' '  filling  ' ' 
material  is  just  as  important  as  that  of  the  active,  or  binding, 
ingredients. 

There  is  no  definite  distinction  between  sand  and  small 
gravel.  It  is  customary,  however,  to  consider  all  particles  of 
gravel,  crushed  stone,  or  other  material  less  than  J  inch  diameter 
to  be  fine  aggregate,  and  to  classify  as  sand  all  mineral  particles 
between  two  millimetres  and  0-5  millimetre  diameter.  All 
8 


114       SEAGOING  AND   OTHER  CONCRETE   SHIPS 

particles  larger  than  J  inch  diameter  are  termed  coarse  aggregate. 
In  concrete  for  land  work  the  coarse  aggregate  is  generally  from 
f  inch  to  1J  inch  diameter  ;  but  in  concrete  for  shipbuilding 
purposes  the  coarse  aggregate  should  not  exceed  \  inch  diameter. 

The  essential  qualities  of  an  aggregate  for  shipbuilding  con- 
crete are  :  maximum  density,  hardness,  durability,  light  weight, 
and  insolubility  in  water.  These  qualities  are  possessed  in  varying 
degree  by  materials  belonging  to  the  following  main  groups  ; 
and  aggregates  in  common  use  generally  belong  to  one  or  other 
of  these : 

Igneous  Rocks,  such  as,  for  example,  Granite,  formed  by  the 
consolidation  of  molten  matter.  Granite  is  composed  almost 
entirely  of  minerals,  quartz,  orthoclase,  and  mica  or  hornblende, 
without  any  cementing  substance.  It  is  exceedingly  hard  and 
dense  ;  and  it  has  the  strength  and  durability  of  a  first-class 
aggregate,  but  is  rather  lacking  in  toughness.  Trap  Bock,  or 
Diabase,  is  another  volcanic  rock  of  high  compressive  strength, 
and  it  adheres  well  to  cement.  It  is  an  excellent  aggregate 
except  when  it  contains  much  iron  in  low  oxides,  for  these  expand 
by  absorption  of  oxygen  and  may  rupture  the  concrete. 

Sedimentary  Rocks,  such  as,  for  example,  Sandstone.  Sand- 
stone is  in  structure  a  natural  concrete,  depending  for  its  character 
upon  the  different  aggregates  present,  which  may  be  quartz, 
felspar,  hornblende,  chlorite,  magnetite,  etc.,  cemented  together 
by  oxides  of  iron  and  carbonates  of  lime  or  clay  ;  the  strength 
and  hardness  depend  on  the  quality  of  the  cementing  substance. 
Sandstones  are  not,  in  general,  suitable  aggregates  for  ship- 
building concrete  since  they  lack  strength  and  durability.  Lime- 
stone, carbonate  of  lime  deposited  under  water  and  subsequently 
hardened,  is  another  example  of  a  sedimentary  rock.  Some  types 
are  chemical  products,  others  are  formed  from  shells  of  small 
animals  or  hardened  tissues  of  plants.  Limestone  rarely  con- 
sists of  pure  carbonate  of  lime  and  is  found  in  many  colours, 
white,  yellow,  blue,  green,  etc.,  frequently  containing  some 
magnesia.  It  is  generally  considered  to  be  a  suitable  aggregate 
for  land  construction  ;  but  when  it  is  crushed  to  a  small  size, 
as  for  shipbuilding  concrete,  it  ruptures  in  a  flaky  manner,  and 
so  it  should  be  thoroughly  tested  with  varying  mixtures. 

Metamorphic  Rocks  (Conglomerates). — These  geological  forma- 
tions may  contain  rocks  of  varying  origins,  and  their  qualities 


SHIPBUILDING  CONCRETE  115 

must  be  thoroughly  investigated  by  chemical  analysis  and  practical 
tests.  Gravel  is  natural  rock  broken  away  from  parent  ledges 
and  worn  round  by  rolling  in  rivers  ;  it  possesses,  therefore,  the 
same  qualities  as  the  parent  rock,  and  if  of  good  mineral  quality 
is  a  very  satisfactory  aggregate  for  shipbuilding  concrete.  The 
surface  is  generally  rough  and  well  suited  for  the  adhesion  of 
cement. 

Artificial  Aggregates,  such  as  Crushed  Bricks,  Cinders,  Blast- 
furnace Slag,  and  similar  materials  are  used  in  cases  where 
strength  and  watertightness  are  not  of  importance. 

Impurities  in  Aggregate.  —  Silt,  which  consists  of  particles 
between  0-5  millimetre  and  0-005  millimetre  in  diameter,  and 
Clay,  which  consists  of  particles  less  than  0-005  millimetre  in 
diameter,  are  both  as  a  rule  harmful,  although  a  small  amount 
(about  five  per  cent.)  of  finely  pulverized,  perfectly  clean,  clay 
improves  the  watertightness  of  the  less  rich  concretes  ;  but  this 
is  a  risky  method  of  trying  to  obtain  watertightness,  for  the  clay 
has  a  tendency  to  form  lumps  which  obviously  cause  weak  spots. 
Clay  should  not  be  used  in  any  form  in  shipbuilding  concrete. 

Mica  is  very  harmful  in  high-grade  concrete.  It  has  hardly 
any  strength  ;  and  the  surface  is  not  made  moist  by  water,  so 
that  the  cementing  compound  does  not  adhere  and  the  mica  is 
merely  loosely  embedded  in  the  concrete  mass. 

Iron  Pyrites  (Fe2S),  a  bright  yellow  substance,  is  a  common 
impurity  in  stone.  In  contact  with  water  it  forms  sulphuric 
acid,  which  attacks  cement  with  disastrous  results.  In  coarse 
aggregate,  however,  it  is  not  so  harmful  as  in  fine  aggregate, 
where  it  is  more  active  in  forming  acids,  and  where  its  presence 
should  be  carefully  prevented. 

'Stone  Dust  (crushed  stone  screenings)  has  practically  the  same 
effect  as  Silt  or  Clay.  It  is  never  of  value  in  high-grade  concrete 
such  as  is  used  in  shipbuilding,  and  should  be  removed  from  the 
aggregate  by  careful  washing. 

Organic  impurities  are  all  harmful.  The  most  common 
organic  impurity  is  Loam,  which  not  only  prevents  cement  from 
adhering  to  mineral  grains  of  sand  but  seems  to  have  also  a 
chemical  action  which  is  at  present  under  investigation.  Tannic 
Acid,  Colloidal  Sewage,  Manure,  Sugar,  Tobacco  Juice  (Spit), 
etc.,  are  examples  of  organic  impurities  having  very  injurious 
effects  on  concrete.  Other  impurities,  too  minute  to  be  seen, 


116       SEAGOING  AND   OTHER  CONCRETE   SHIPS 

must  be  detected  by  chemical  analysis,  or  by  practical  tests 
where  a  lack  of  strength  is  difficult  otherwise  to  explain. 

Most  organic  impurities  can  be  removed  by  careful  washing. 
Hence  the  first  condition  for  a  satisfactory  aggregate  is  that  it 
shall  be  perfectly  clean. 

Sand. —  All  fine  aggregates  come  from  rocks  which  have 
disintegrated.  Sand  is  the  natural  deposit  of  such  material, 
carried  for  thousands  of  years  by  rivers  towards  the  sea.  Changes 
which  have  taken  place  during  the  vast  periods  of  time  and 
travel  are  partly  physical  and  partly  chemical.  The  physical 
effects  have  not  changed  the  character  of  the  particles  from  that 
of  the  parent  rock,  which  is  merely  broken  up  and  reduced  in 
size.  For  instance,  a  quartz  sand  contains  silicates  of  exactly 
the  same  type  as  the  parent  rock;  it  is  probably  the  best  sand 
for  all  concrete  work. 

Chemical  changes  of  the  fine  aggregate  which  have  taken 
place  during  thousands  of  years  are  quite  different  from  the 
physical  changes.  The  particles  decompose,  losing  their  original 
character,  and  enter  into  new  compositions  ;  examples  of  such 
change  are  clay  and  silt.  As  a  rule  chemical  changes  are  harmful. 

The  composition  and  character  of  the  original  rocks  are  of 
great  importance.  For  instance,  a  fine  aggregate  obtained  from 
sandstone  consisting  of  quartz  grains  cemented  together  with 
calcium  carbonate  or  clay  is  not  suitable  for  shipbuilding  con- 
crete. It  is  often  white  and  very  pleasing  to  the  eye,  but  the 
cementing  clay  absorbs  water  during  the  mixing  of  the  concrete 
and  forms  a  soft  putty,  which  separates  the  sand  particles  and 
prevents  contact  with  the  Portland  Cement,  so  reducing  the 
strength  of  the  concrete.  Calcium  carbonate  may  be  detected 
by  muriatic  acid,  which  will  effervesce  if  calcium  carbonate  is 
present. 

Sand  originating  from  limestone  formed  by  the  fossilizing  of 
minute  prehistoric  shells  is  not  suitable  as  a  fine  aggregate, 
since  it  is  easily  decomposed  and  contains  tiny  voids. 

Sea  sand  is  generally  satisfactory,  but  it  should  be  taken 
from  the  bottom,  not  from  the  beach  where  the  grains  are  polished 
and  smooth  from  being  rubbed  together  by  the  waves  instead  of 
having  the  rough  irregular  surface  which  enables  the  cement 
particles  to  adhere  intimately.  Further,  beach  sand  contains 
more  organic  matter  than  sand  from  the  bottom  or  from  above 


SHIPBUILDING  CONCRETE  117 

the  beach.  Saline  deposits  do  not  seem  to  be  harmful  in  rich 
concretes. 

The  sand  grains  should  be  of  varying  sizes.  Standard  testing 
sand  used  in  laboratories  passes  through  a  No.  20  sieve  and 
remains  on  a  No.  30  sieve  ;  the  grains  are  therefore  of  uniform 
size,  and  so  the  sand  has  a  large  amount  of  voids.  Mortars  made 
with  such  sand  are  not  strong  ;  but  most  regulations  for  concrete 
construction  accept  a  strength  equal  to  that  from  tests  with 
standard  sand.  For  shipbuilding  concrete,  however,  such  a 
strength  is  not  sufficient,  and  the  very  best  quality  of  sand  is 
required  for  mortar  and  concrete.  As  pointed  out  above,  the 
cost  is  of  less  importance  than  in  land  construction,  and  the 
material  may  accordingly  be  washed  and  screened  in  a  more 
thorough  manner. 

The  customary  manner  of  specifying  fine  aggregate,  or  sand, 
for  land  construction  is  merely  to  state  that  the  material  should 
be  "  sharp,  clean,  and  coarse."  Individual  opinions  may  differ 
considerably  as  regards  these  qualities,  and  the  specification  is 
not  sufficiently  exact  for  the  high-class  aggregate  required  for 
shipbuilding  concrete.  For  shipbuilding  concrete  the  fine 
aggregate  must  have  : 

Cleanness,  determined  by  careful  washing,  by  chemical  tests, 
or  by  both  methods  together.  Sand  containing  more  than  one 
per  cent,  of  mica  should  be  prohibited.  , 

Coarseness,  determined  by  granulometric  screening. 

Strength,  determined  by  actual  compression  tests  with  mortars 
and  concretes  at  7  days  and  28  days  with  different  mixtures. 

Light-weight  Aggregate. — Extensive  experiments  were  carried 
out  by  the  Concrete  Ship  Section  of  the  U.S.  Shipping  Board  in 
order  to  develop  an  artificial  aggregate  of  light  weight.  Experi- 
ments towards  the  same  end  ha^e  been  carried  out  also  by  the 
author. 

The  author  burned  clay  in  a  limekiln  under  various  conditions 
of  moisture  and  temperature  and  succeeded  in  obtaining  an 
aggregate  which  floats  in  water  owing  to  the  air-cells  blown  in 
the  material.  The  strength  was  not,  however,  comparable  to 
that  of  first-class  gravel,  and  much  of  the  advantage  as  regards 
lightness  was  lost  when  the  material  was  crushed  down  to  the 
sizes  required  in  shipbuilding  concrete  ;  many  of  the  air-cells 
were  broken  up  and  so  the  unit  weight  increased.  Particulars 


118       SEAGOING  AND   OTHER  CONCRETE   SHIPS 

of  the  U.S.  Shipping  Board  material  can  be  obtained  in  Engineering 
News-Record,  vol.  Ixxxii,  No.  17,  p.  802. 

Concrete  made  with  any  of  the  light-weight  aggregates  which 
have  sufficient  strength  to  be  considered  for  shipbuilding  pur- 
poses weighs  about  100-110  Ib.  per  cubic  foot,  that  is,  about 
75  per  cent,  of  the  weight  of  gravel  concrete.  But  when  it  is 
borne  in  mind  that  the  reduced  strength  of  the  light-weight 
concrete  involves  the  use  of  more  concrete  in  the  ship  in  order 
to  attain  a  desired  standard  of  strength,  it  is  obvious  that  the 
saving  in  weight  of  hull  is  not  so  great  relatively  as  the  saving 
in  weight  per  cubic  foot. 

Light-weight  aggregate  is  harsh  and  unpleasant  to  work, 
and  readily  forms  pockets  in  the  concrete  on  account  of  the 
porous,  sharp  surfaces  grinding  against  each  other,  thereby 
causing  excessive  friction  between  the  pieces  of  aggregate  and 
reinforcement.  This  fact  accounts  for  the  easy  shattering  of 
the  shell  from  an  external  blow  recorded  with  reference  to  the 
S.S.  Cape  Fear  in  the  last  report  (21st  January  1921)  of  the 
"  Special  Committee  on  Concrete  Ships  and  Barges "  to  the 
American  Concrete  Institute.  In  none  of  the  collisions,  ground- 
ings, etc.,  of  concrete  ships  built  by  the  author's  firm,  in  which 
gravel  concrete  was  used,  has  damage  in  the  form  of  cracks  or 
shattering  of  surrounding  concrete  extended  appreciably  beyond 
the  local  wound  ;  the  crushing  has  always  been  clearly  defined 
and  limited. 

The  author  does  not  agree  with  the  frequent  assertions  that 
the  light-weight  aggregate  is  waterproof  because  each  air-cell  is 
closed  off  from  its  neighbours  ;  simple  experiments — for  example, 
floating  a  few  pieces  of  the  aggregate  in  water — show  that  after 
a  few  weeks,  at  most,  the  pieces  lose  buoyancy  and  finally  sink. 
It  is  believed  that  Lloyd's  Register  have  not  so  far  been  satisfied 
with  the  waterproof  qualities  of  the  light-weight  aggregate. 
Of  course,  mixing  with  Portland  Cement,  which  fills  up  the  pores, 
greatly  adds  to  the  watertightness.  When,  further,  special 
coatings  and  paints  are  applied  to  the  concrete  surface  a  ship 
built  with  light-weight  aggregate  can  probably  be  made  perfectly 
watertight. 

Proportions  of  Mixture.  — Scientists  and  engineers  are  at 
present  trying  to  determine  general  rules  for  securing  the  best 
possible  grade  of  concrete.  But  from  the  nature  of  the  problem 


SHIPBUILDING  CONCRETE  119 

it  is  not  probable  that  definite  rules  will  cover  all  cases,  since 
finished  concrete  depends  for  its  quality  not  only  on  the  correct 
proportions  of  the  ingredients,  but  on  the  mixing,  placing  in  the 
forms,  and  conditions  during  the  setting  and  hardening. 

The  following  considerations  should  be  borne  in  mind  when 
deciding  the  proportions  for  shipbuilding  concrete  : 

1.  The  compressive  strength  after  28  days  of  age  should  not 
be  less  than  4,000  Ib.  per  sq.  inch. 

2.  The  watertightness  should  be  perfect  for  pressures  due  to 
at  least  the  full  depth  of  the  ship  in  which  the  concrete  is  to  be 
used. 

3.  The  mixture  should  be  plastic  and  easily  worked  around 
the  steel  reinforcement  in  the  forms  without  too  much  water 
being  used. 

If  the  first  condition  is  fulfilled  the  shearing  strength,  abrasive 
quality,  and  adhesion  to  the  steel  will  generally  also  be  satisfactory. 

If  the  second  condition  is  fulfilled  the  density  of  the  concrete 
will  generally  be  satisfactory,  thereby  assuring  durability  pro- 
vided the  aggregate  is  of  the  highest  class. 

If  the  third  condition  is  carefully  maintained,  the  result  will 
be  an  all-round  good  quality  of  concrete.  The  bad  effects  of  too 
much  water  have  already  been  explained.  On  the  other  hand; 
the  mixture  must  not  be  so  dry  that  there  is  insufficient  water 
for  the  chemical  reaction  or  that  the  concrete  clogs  between 
the  reinforcing  rods  and  leaves  hollow  spaces.  The  amount  of 
water  should  not  always  be  constant,  but  should  vary  according 
to  the  temperature,  speed  of  concreting,  and  position  in  which 
the  concrete  is  to  be  placed.  In  bottom  and  deck  the  concrete 
is  readily  worked  around  the  reinforcement  even  if  the  mixture 
is  fairly  dry.  In  the  ship's  sides  this  is  not  possible,  nor  in 
bulkheads,  narrow  beams  or  stanchions,  and  so  in  these  places 
the  concrete  must  be  relatively  moist. 

The  author  has  found  from  practical  experience  gained  during 
four  years  by  the  construction  of  about  30  concrete  ships  that 
the  proportions  of  the  mixture  should  be  about 

1  part  Portland  Cement, 
2-J-  parts  Aggregate. 

The  mixture  found  to  be  most  satisfactory  with  the  brand 


120       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

of  Portland  Cement  and  the  local  aggregates  used  in  the  ships 
built  Ijy  the  author's  firm  was 

1  part  Portland  Cement, 
1-85  parts  Sand, 
0-65  part  Gravel. 

It  may  be  mentioned  that  in  the  Namsenfjord  the  mixture 
used  in  the  deck  and  bottom  was 

1  part  Portland  Cement, 
1-4  parts  Sand, 
2-6  parts  Gravel. 

The  mixture  used  in  the  sides  was 

1  part  Portland  Cement, 
1-5  parts  Sand, 
1-5  parts  Gravel. 

The  difference  between  the  proportions  used  in  the  Namsen- 
fjord and  those  used  latterly  is  the  result  of  experience.  Gravel 
is  difficult  to  work  around  steel  reinforcement  in  confined  spaces, 
and  it  cannot  be  mixed  in  mortar  which  is  plastered  on,  for  the 
gravel  jumps  out  when  the  mortar  is  thrown  on  to  the  metal 
mesh.  Apart  from  these  considerations,  a  large  amount  of 
gravel  in  the  mixture  not  only  tends  to  cheaper  concrete  but 
also  to  stronger  concrete.  Compare,  for  example,  the  following 
results  from  tests  made  by  the  author  : 

Mixture.  Age.  Compressive  Strength. 

1:2           .  .3  months  4,270  Ib.  per  sq.  inch 

l:2i        .  .  „  3,840        „ 

l:lj:2i  .  „  4,520        „ 

l:lf:2|  .  „  4,880        „ 

Since  cement  is  the  most  expensive  ingredient  of  concrete  it 
is  obvious  that  the  last  mixture,  containing  1  part  cement  to 
4  parts  aggregate,  is  cheaper,  besides  being  stronger,  than  the 
first  mixture,  containing  1  part  cement  to  2  parts  aggregate. 
But  for  shipbuilding  concrete  compression  tests  made  in  a  labora- 
tory do  not  always  indicate  the  most  satisfactory  proportions, 
because  watertightness  and  easy-working  quality  are  of  greater 
importance  in  relation  to  compressive  strength  than  in  the  case 
of  concrete  for  land  construction. 


SHIPBUILDING  CONCRETE 


121 


In  the  ships  built  for  the  U.S.  Shipping  Board  the  mixture 
used  was  generally 

1  part  Portland  Cement, 
0-67  part  Sand, 
1-33  parts  Gravel. 

As  a  general  rule  the  mixture  should  not  be  made  richer  than 
1  part  cement  :  2  parts  aggregate,  because  expansion,  contraction, 
and  Modulus  of  Elasticity  increase  with  the  proportion  of  cement. 
On  the  other  hand,  the  mixture  should  not  be  leaner  than  1  part 
cement  :  3  parts  aggregate,  because  watertightness  then  becomes 
uncertain  ;  the  ship  may  not  actually  leak,  but  water  will  pene- 
trate into  the  concrete  and  cause  corrosion  of  the  reinforcement. 
The  following  table  gives  average  values  of  the  compressive 
strengths  of  various  mixtures,  as  determined  from  tests  carried 
out  by  the  author  : 

TABLE  A.— AVERAGE  COMPRESSION  VALUES  OF  VARIOUS  MIXTURES 


Proportions 

of  Mixture  Cement  :  Sand  : 
Gravel  . 

Percentage 
of  Water 
by  Volume. 

Compression,  Ib.  per  sq.  inch, 
average  after 

7  days. 

28  days. 

fl  : 

2-50  :  0-00 

15 

2,020 

3,540 

1  :  2HI  : 

2-00  :  0-50 

15 

3,180 

3,060 

\1: 

1-85  :  0-65 

w 

3,320 

4,130 

1:3       1  : 

2-25  :  0-75 

14i 

2.  005 

3,225 

f1: 

1-50  :  2-50 

11 

2,990 

3,885 

1:4    {  1  : 

1-90  :  2-10 

12 

2,450 

3,345 

1 

2-25  :  1-75 

13 

2,220 

2,730 

All  tests  were  made  on  8"  X  8"  X  8"  cubes  at  the  Christiania 
Materials  Testing  Laboratories  according  to  instructions  from 
the  author.  The  concrete  was  not  rammed,  but  the  sides  of  the 
forms  were  tapped  lightly  and  the  free  surface  smoothed  off  with 
a  straight  board. 

The  amount  of  water  is  stated  as  a  percentage  of  the  total 
volume  of  cement,  sand,  and  gravel.  The  materials  were  always 
proportioned  by  volume  (not  by  weight). 

The  sand  was  retained  on  a  No.  30  and  passed  through  J  inch 
screen.  The  gravel  was  retained  on  J  inch  and  passed  through 
J  inch  screen  (the  meshes  in  the  latter  were  nearly  f  inch). 

Assuming  that  the  cement  and  quality  of  aggregate  are  first- 


122        SEAGOING  AND   OTHER  CONCRETE   SHIPS 

class  and  have  been  examined  or  tested  as  previously  described, 
the  following  simple  field  tests  to  determine  the  amount  of  voids 
in  the  aggregates  and  the  density  of  the  concrete  are  very  useful 
as  indicating  the  mixtures  likely  to  give  the  best  results  in  actual 
compression  tests  ;  they  are  carried  out  by  means  of  an  accurate 
pair  of  scales  and  a  large  graduated  measuring  glass. 

The  percentage  of  voids  in  the  aggregate  can  be  determined  by 
two  methods  : 

1.  By  finding  the  amount  of  water  required  to  fill  all  the 
voids  in  a  certain  volume  of  the  aggregate. 

2.  By  determining  the  specific  gravity  of  solid  pieces  of  the 
aggregate,  then  weighing  a  given  volume  of  the  aggregate,  and 
finally  calculating  the  percentage  of  voids. 

By  the  first  method  voids  in,  for  example,  sand  are  found 
by  filling  the  measuring  glass  with,  say,  100  measures  of  dry 
sand.  Pour  this  out  and  fill  the  glass  up  to,  say,  60  measures 
with  water.  Into  this  sprinkle  slowly  the  same  100  measures 
of  dry  sand.  These  will  now  be  found  to  fill  the  glass  only  to, 
say,  94  measures,  having  shrunk  six  per  cent.  ;  while  the  water 
will  reach  to,  say,  121  measures,  of  which  121  —  94  =21  measures 
will  be  above  the  sand,  and  60  —  27  =  33  measures  will  be 
filling  the  voids  in  94  measures  of  wet  sand.  Then  the  voids  in 

33 

the  wet  sand  amount  to  —  =  0-351  =  35-1  per  cent,  of  the  wet 

mass.  If  the  sand  is  poured  into  the  water  hastily  air  is  carried 
in  with  it,  the  voids  will  not  be  filled,  and  the  result  will  be 
misleading. 

If  the  second  method  be  adopted  the  specific  gravity  of  a 
solid  piece  of  aggregate  must  first  be  determined,  either  by 
dropping  the  aggregate  into  a  given  volume  of  water  (noting  the 
increase  in  volume  of  the  liquid),  or  by  suspending  a  piece  of 
aggregate  by  thread  from  the  scales  and  noting  the  weight  in 
air  and  weight  when  hanging  in  water.  In  such  tests  it  is 
desirable  to  use  metric  measures  of  volume  and  weight,  as  sim- 
plifying the  arithmetic  since  1-0  cub.  cm.  of  water  weighs  1-0 
gram.  For  example,  670  cub.  cm.  of  quartz  weigh  1,775-5 

1775*5 
gram.     Therefore  =  2-65  is  the  specific  gravity  of  quartz. 

If  now,  say,  450  cub.  cm.  of  sand  weigh  793  gram  and  the  same 
volume  of  solid  quartz  weighs  450  X  2-65  =  1,192  gram,  the 


SHIPBUILDING  CONCRETE 


123 


sand  is 


793 


=  0-665  solid,  or  contains  :    1-000  —  0-665  =  0-335 


1192 
=  33-5  per  cent,  of  voids. 

The  specific  gravity  of  sand  is  practically  constant  at  a  value 
of  2-65. 

The  specific  gravity  of  gravel  is  also  practically  uniform ;  an 
average  value  is  2-66. 

For  different  kinds  of  stone  the  specific  gravity  varies  from 
2-4  for  Sandstone  to  2-6  for  Trap  Rock.  The  percentage  of  voids 
in  dry  sand  ranges  from  28  in  coarse,  well- graded  material  to 
45  in  uniform  screened  sand  ;  in  coarse  aggregate  it  varies  from 
25  to  55  per  cent.  Natural  sand  contains  2  to  4  per  cent,  of 
moisture  by  weight.  It  increases  in  volume  to  a  maximum  at 
about  7  per  cent,  of  moisture,  because  the  water  surrounds  the 
particles  and  separates  individual  grains. 

The  following  values  are  based  on  a  specific  gravity  of  2-65. 


TABLE  B.—  PERCENTAGES  OF  VOIDS  IN  SAND  AND  GRAVEL  CORRE- 
SPONDING   TO    DIFFERENT    WEIGHTS    PER    CUBIC    FOOT 


Percentages 

Weight  per  cubic  foot  of  Sand  or  Gravel  in  lb. 

by  Weight  . 

90 

95 

100 

105 

110 

115 

120 

125 

0 

45-7 

42-7 

39-6 

36-6 

33-6 

30-6 

27-5 

24-5 

2 

4C-7 

43-8 

40-8 

37-9 

34-8 

31-9 

28-9 

26-0 

4 

47-8 

45-0 

42-0 

38-1 

36-2 

33-3 

30-4 

27-5 

6 

48-9 

46-0 

43-2 

40-4 

37-5 

34-7 

31-7 

29-0 

8 

50-0 

47-2 

44-5 

41-6 

38-9 

36-1 

33-3 

30-6 

The  amount  of  voids  depends  on  the  compactness  of  the 
aggregate,  and  it  is  customary  to  determine  voids  in  dry  sand 
well  shaken,  and  for  coarse  aggregate  in  loose  measure,  because  in 
concrete  the  particles  of  coarse  aggregate  are  separated  by  sand 
and  cement.  By  shaking  coarse  aggregate  the  amount  of  voids 
may  be  reduced  by  as  much  as  10  per  cent.  If  spheres  of  any 
uniform  size  are  carefully  piled  together  in  the  most  compact 
manner,  the  mass  contains  26  per  cent,  of  voids.  If  thrown 
together  and  allowed  to  arrange  themselves  the  voids  will 
increase  to  44  per  cent.  When  all  particles  are  of  uniform  size 
and  shape  the  voids  will  be  practically  the  same  as  in  other 
materials  having  larger  or  smaller  particles  of  similar  shape  and 
iunorm  size.  Aggregate  with  round  grains  contains  less  voids 


124       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

than  aggregate  with  angular  particles,  and  the  largest  percentage 
occurs  when  all  grains  are  of  the  same  size.  The  minimum 
amount  of  voids  is  obtained  in  a  material  so  graded  that  each 
size  of  particle  fills  the  voids  between  the  other  particles. 

The  density  of  concrete  can  be  investigated  by  means  of  a 
simple  field  test  preliminary  to  laboratory  tests  of  strength, 
which  must  be  carried  out  later. 

Definite  quantities  of  cement,  fine  and  coarse  aggregate  are 
weighed  in  proportions  corresponding  approximately  to  the 
mixture  it  is  proposed  to  use.  The  materials  are  mixed  together 
with  a  certain  amount  of  water,  also  weighed,  and  after  obtaining 
a  concrete  of  proper  consistency,  it  is  poured  into  a  large  measur- 
ing glass,  which  is  gently  tapped  on  the  sides  a  certain  number 
of  times  and  the  volume  of  concrete  is  noted  after  a  certain 
time,  for  instance  three  minutes.  This  concrete  is  then  thrown 
away  and  a  new  batch  made  with  exactly  the  same  total  weight 
of  materials,  but  slightly  altered  proportions  of  fine  and  coarse 
aggregate  and  water.  After  mixing  and  filling  the  concrete  into 
the  measuring  glass  in  exactly  the  same  manner  as  before  the 
volume  is  noted,  and  if  smaller  than  that  of  the  first  batch  it 
proves  that  the  mixture  has  greater  density. 

By  such  preliminary  investigations  an  indication  is  obtained 
of  the  proportions  likely  to  be  most  satisfactory. 

Mixing. — Shipbuilding  concrete  should  always  be  machine- 
mixed  in  a  batch  mixer,  of  which  there  are  many  well-known 
types  on  the  market.  The  capacity  is  generally  J,  },  or  1  cub. 
yard,  and  the  mixer  should  be  driven  at  the  speed  recommended 
by  the  manufacturer.  The  concrete  should  remain  in  the  mixer 
at  least  1J  to  2  minutes  ;  an  average  time  of  3  minutes  for  each 
batch  was  adopted  for  the  ships  built  by  the  author's  firm. 

Before  the  materials  are  put  into  the  mixer  they  are  carefully 
measured  (by  volume)  and  proportioned  to  suit  a  practical 
measure  of  cement,  for  example  2  bags  or  1  barrel  in  each  batch. 
The  fine  and  coarse  aggregates  are  stored  in  separate  bins  and 
measured  in  hoppers,  steel-lined  or  of  steel,  and  made  carefully 
true  to  form  so  that  the  quantity  of  material  can  be  closely 
gauged.  In  this  way  it  is  unnecessary  to  measure  the  cement 
except  by  checking  once  in  a  while  the  weight  of  cement  bags 
(or  barrels).  Water  is  supplied  from  a  barrel  or  tank  provided 
with  a  gauge  glass  and  a  large  outlet  cock  to  permit  a  rapid 


SHIPBUILDING  CONCRETE  125 

supply  to  the  mixer.  In  cold  weather  the  water  must  be  heated 
by  steam  coils  in  the  barrel,  even  to  the  boiling-point  if  necessary 
and  sufficient  steam  is  available.  In  cold  weather  it  is  also  well 
to  heat  the  aggregates  by  steam  coils  in  the  storage  bins  or  by 
any  other  method. 

The  details  of  a  mixing  plant  depend  on  the  facilities  of  the 
shipbuilder  and  should  be  planned  accordingly.  At  least  two 
mixers  should  be  installed,  in  case  of  a  break-down.  An  inspector, 
preferably  an  engineer  realizing  his  full  responsibility,  should 
always  be  present  at  the  mixing  plant  when  concreting.  He 
sees  that  the  materials  are  clean,  of  quality  as  specified,  and 
proportioned  correctly  t;  and  he  must  assure  himself  that  the 
mixer  is  clean  before  work  commences,  that  the  water-cock  and 
other  valves  supplying  materials  are  tight-fitting  so  that  no 
leak  occurs  by  which  extra  material  is  added  or  lost  in  the 
mixer.  The  amount  of  cement  is  controlled  by  counting  empty 
bags  and  checking  up  the  number  in  relation  to  the  number  of 
batches.  One  man  controls  the  supply  of  materials  and  one 
runs  the  mixer.  The  latter  is  responsible  for  the  time  consumed 
and  proper  mixing  of  each  batch.  If  a  stop  occurs  in  the  con- 
creting operation  a  batch  should  not  be  mixed  longer  than 
30  minutes,  and  in  such  a  case  the  mixer  should  be  run  very 
slowly. 

Tests  have  shown  that  even  mixing  for  three  to  four  hours 
has  not  materially  reduced  the  tensile  strength  of  mortar,  but 
the  results  are  so  erratic  that  no  certain  conclusions  can  be  made, 
and  other  tests  show  opposite  results.  Slightly  more  water 
should  be  added  during  exceptionally  long  mixing. 

Concrete  should  always  be  placed  in  its  final  position  within 
one  hour  from  the  completion  of  mixing.  In  exceptional  cases 
mixtures  up  to  two  hours  old  can  be  remixed  and  used,  but 
this  should  never  happen  unless  quite  unavoidable  and  both 
water  and  extra  cement  should  be  added  to  the  concrete,  which 
must  be  thoroughly  stirred  up  and  remixed  until  it  has  normal 
consistency. 

U.S.  Dept.  of  Agricult.  Bull.  No.  235  refers  to  tests  by  the 
Office  of  Public  Roads  which  show  that  mortars  of  mixture  1  :  2 
have  at  the  age  of  four  months  approximately  the  same  tensile 
strength  whether  remixed  after  If  hours  (initial  set  of  cement) 
and  after  7J  hours  (final  set  of  cement),  or  when  left  to  harden 


126       SEAGOING  AND   OTHER  CONCRETE   SHIPS 


immediately  after  being  mixed.  Water  was  added  to  restore 
normal  consistency.  But  the  same  tests  show  that  mortar  of 
mixture  1  :  3  lost  about  17  per  cent,  in  tensile  strength  under 
the  same  conditions. 

Placing  and  Curing. — Concrete  may  be  transported  to  the 
forms  by  carts  or  buckets,  but  not  by  spouts. 

Spouts  are  satisfactory  in  ordinary  land  construction,  but  ship- 
building concrete  must  be  handled  more  carefully  than  land 
concrete.  In  traversing  long  spouts  the  concrete  tends  to 
separate  and  absorbs  air-bubbles.  When  passed  along  spouts 
concrete  must  be  made  moister  than  when  transported  in  buckets 
or  carts. 

The  inspector  must  carefully  inspect  the  forms  and  all  steel, 
which  should  be  placed  in  position  before  concreting.  The  forms 
must  be  tight  and  are  sprayed  with  a  water  hose,  but  care  should 
be  taken  that  superfluous  water  escapes  through  special  drain 
holes  made  for  this  purpose  before  any  concrete  is  deposited. 
The  most  important  duty  of  the  engineer  in  charge  of  placing 
concrete  is  to  decide  and  maintain  the  correct  consistency  of  the 
concrete  and  regulate  the  amount  of  water  accordingly. 

sThe  facts  stated  on  the  preceding  pages  should  be  carefully 
borne  in  mind,  since  apart  from  these  only  practical  experience 
with  the  actual  materials  can  show  how  much  water  is  needed. 
In  hot  weather  the  mixture  should  be  softer,  because  the  water 
naturally  evaporates  faster.  Table  C  gives  average  values 
from  about  100  tests  on  samples  taken  from  the  concreting  of 
two  seagoing  ships  during  summer  and  autumn  and  shows  the 
effect  of  varying  amounts  of  water. 

TABLE    C.— COMPRESSIVE    STRENGTH    AFTER    28    DAYS 


Mixture  by  Volume. 

Ship  No. 

Date  of  Concreting. 

Percentage  of 
Water  by  Volume. 

Compressive  Strength 
in  Ib.  per  sq.  inch. 

1  :  1-85  :  0-65 

28 

Nov.  1918 

14 

4,607 

M 

n 

Oct.   1918 

15 

4,522 

)» 

»       »» 

19 

4,593 

» 

33 

July   1919 

20 

4,323 

» 

» 

»       » 

25 

4,110 

The  test  cubes  (8"  X  8"  X  8")  were  made  in  the  shipyard 
from  samples  selected  by  the  Classification  Society's  inspector 
during  the  actual  concreting. 


SHIPBUILDING  CONCRETE  127 

Concrete  should  preferably  be  placed  continuously  until  the 
hull  is  completed.  Practical  difficulties  may  prevent  this, 
however,  and  it  has  been  found  that  a  shut-down  from,  say, 
11  p.m.  to  5  a.m.  does  no  harm,  when  care  is  taken  that  the 
surfaces  of  the  joints  are  kept  scrupulously  clean  and  brushed 
with  a  solution  of  neat  cement  and  water  before  new  concrete  is 
placed.  No  joints  can  then  be  seen  after  the  forms  are  removed. 

Concrete  should  be  tamped  in  the  forms  with  short  rods  in 
layers  of  about  4  to  6  inches  until  it  has  a  uniform  consistency 
like  soft  jelly.  Water  will  work  itself  to  the  top,  but  the  mixture 
should  not  be  so  wet  that  superfluous  water  will  collect  on  top 
of  the  concrete  before  the  next  batch  is  placed.  A  few  bags 
of  cement  should  always  be  kept  near  the  forms  so  that  the 
mixture  can  be  made  dryer  in  case  a  single  batch  is  made  too 
wet  by  accident. 

The  curing  of  shipbuilding  concrete  is  generally  easier  than 
that  of  ordinary  concrete  in  roofs,  floors,  etc.,  since  ships  are 
usually  built  under  cover  and  the  double  forms  on  the  sides 
retain  the  moisture  in  the  concrete.  The  most  exposed  part 
is  the  deck,  on  which  the  finishing  coat  should  not  be  worked 
until  all  machinery,  fittings,  rigging,  etc.,  are  placed ;  this 
may  be  several  months  after  the  ship  is  launched.  During  the 
first  8  or  10  days  after  concreting  the  deck  should  be  kept 
moist  with  wet  sacks  and  all  exposed  parts  of  the  concrete  sprayed 
by  means  of  a  hose  regularly  in  the  mornings  and  evenings.  After 
this  period  the  outside  forms  can  be  removed  and  the  exterior 
finish  plastered  on,  the  rough  concrete  surface  having  first  been 
thoroughly  soaked  by  means  of  a  hose  exerting  good  water- 
pressure. 

The  exterior  cement  finish  should  be  mixed  in  the  proportion 

1  part  Portland  Cement, 
2|  parts  Sand. 

The  sand  may  be  considerably  finer  than  that  used  in  the  con- 
crete, and  may  pass  through  a  No.  20  and  be  retained  on  a  No.  40 
sieve.  The  cement  finish  should  be  about  J  inch  thick,  plastered 
on  by  hand  in  the  usual  manner,  as  a  continuous  operation.  It 
should  be  kept  moist  for  about  10  days  and  be  protected  against 
strong  sunshine  for  another  10  days. 

Much  research  work  has  been  done  to  find  the  best  method 


128       SEAGOING  AND   OTHER  CONCRETE   SHIPS 


of  placing  and  curing  concrete,  but  many  experiments  are  based 
on  artificial  conditions  (in  the  laboratory)  which  never  occur  in 
practical  life,  and  the  results  are  of  little  interest  to  the  engineer 
or  shipbuilder. 

Steam  Curing.  —  In  exceptional  cases,  such  as  repairs  of 
ships  after  grounding  or  collisions,  concrete  may  be  cured  by 
special  methods,  so  as  to  harden  in  a  few  days  to  an  extent 
which  otherwise  would  require  the  same  number  of  weeks  or 
even  months.  The  curing  can  be  done  by  steam,  and  interesting 
tests  on  the  subject  have  been  made  by  the  U.S.  Bureau  of 
Standards  (Tech.  Paper  No.  58)  as  referred  to  in  Table  D. 

TABLE  D.— EFFECT   OF  CURING   1  :  4  MORTAR  UNDER   STEAM 
PRESSURE    (8"  X   16"  cylinders) 


Gauge  Pressure 
Ib.  per  sq.  inch. 

Temperature 
(Fahr.). 

Duration  of 
Exposure  to 
Steam  (hours). 

Compressive  Strength  in  Ib.  per  sq.  inch. 

2  days. 

7  days. 

14  days. 

28  days. 

Not  steamed 

613 

1,296 

1,528 

1,727 

0 

212 

48 

1,267 

— 

— 

— 

2 

218 

24 

1,808 

1,792 

1,805 

— 

10 

239 

24 

1,786 

1,555 

1,701 

1,902 

20 

258 

24 

2,139 

2,284 

2,740 

— 

40 

286 

24 

3,292 

3,381 

3,984 

— 

80 

323 

24 

3,964 

3,966 

4,433 

— 

80 

323 

24 

4,487 

4,187 

4,840 

~~ 

These  tests  were  made  on  Portland  Cement  mortar,  but 
similar  results  were  found  with  regard  to  concrete.  The  mortar 
and  concrete  should  have  an  initial  set  before  being  exposed  to 
treatment  with  steam. 

Freezing. — The  opposite  effect  to  steam  curing  is  found  when 
concrete  freezes,  or  is  cured  at  low  temperatures.  Hardening 
requires  from  4  to  8  times  as  long  as  is  required  normally. 
Experimental  studies  of  the  effect  of  frost  on  mortar  and  concrete 
are  somewhat  conflicting  in  their  conclusions.  It  is  generally 
assumed  that  if  concrete  is  prevented  from  freezing  during  the 
first  48  hours  after  being  placed  the  chemical  action  will  continue 
even  if  the  temperature  drops  considerably  below  freezing-point. 
Tests  indicate  that  a  mixture  of  1  Cement,  2  Sand,  4  Aggregato 
(|  inch  size)  when  cured  at  30°  F.  will  have  at  28  days  of  age 
about  60  per  cent,  of  the  compressive  strength  which  it  would 
have  had  if  placed  and  cured  at  normal  temperature  (70°  F.). 

Two  facts  tend  to  lessen  the  injurious  effect   of  freezing 


SHIPBUILDING  CONCRETE  129 

that  concrete  is  a  poor  conductor  of  heat,  and  that  the  chemical 
action  of  setting  and  hardening  cement  evolves  heat  and  raises 
the  temperature.  Both  points,  however,  apply  to  concrete  in 
large  bulk  more  than  to  concrete  in  shipbuilding,  where  the 
quantities  are  always  small. 

Vibration,  Pressure,  etc. — Vibration  of  the  forms  and  com- 
pression of  the  mass  have  been  tried  as  means  of  producing 
concrete  of  increased  strength.  Mechanical  methods  of  shaking 
and  jigging  the  concrete  have  also  been  tried,  and  interesting 
results  from  elaborate  researches  on  these  subjects  are  given 
by  Prof.  Duff  A.  Abrams  in  Bull.  No.  3,  published  by  the  Struc- 
tural Materials  Research  Laboratory,  Lewis  Institute,  Chicago,  who 
arrives  at  the  following  general  conclusions,  assuming  that  a 
"  Standard  "  method  of  hand-puddling  concrete  for  laboratory 
tests  should  be  25  strokes  with  a  f  inch  steel  bar  for  each  4  inch 
layer  of  concrete  in  a  6"  X  12"  cylinder  : 

Varying  the  number  of  strokes  from  12  to  50  in  the  "  Stan- 
dard "  method  of  hand-puddling  had  little  influence  on  the 
compressive  strength. 

The  various  methods  of  mechanical  shaking  generally  gave 
lower  strengths  than  hand-puddling,  and  a  tamping  rod  of  large 
diameter  was  less  effective  than  a  smaller  one. 

Striking  the  metal  forms  with  a  steel  bar  after  puddling  by 
the  "  Standard  "  method  had  no  effect  on  the  strength  of  the 
concrete. 

Vibration  by  means  of  an  electric  hammer  did  not  affect  the 
strength  of  concrete  hand-puddled  by  the  "  Standard  "  method 
if  carried  on  for  about  30  seconds,  but  the  strength  of  the  concrete 
was  reduced  by  about  10  per  cent,  when  vibrated  for  about 
60  seconds. 

Jigging  generally  reduced  the  compressive  strength,  no  matter 
the  height  of  drop,  or  rate  or  duration  of  treatment ;  the  greater 
the  drop  the  greater  the  reduction  in  strength. 

Pressure  applied  during  moulding  increased  the  compressive 
strength  of  concrete  to  the  extent  of  20—35  per  cent,  for  pressure 
from  200-500  Ib.  per  sq.  inch.  The  increase  in  strength  was 
due  to  water  being  expelled  ;  the  duration  of  pressure  therefore 
made  very  little  difference. 

It  is  concluded  that  all  these  artificial  methods  of  treating 
the  concrete  do  no  good  and  may  be  harmful  if  too  severe  or 
9 


130       SEAGOING  AND   OTHER    CONCRETE   SHIPS 

too  long-continued  ;  finally  it  is  stated,  that  by  applying  such 
methods  concrete  may  be  placed  dryer  than  usual,  that  excess 
water  brought  to  the  surface  must  be  removed,  and  that  coarser 
aggregate  than  usual  may  be  used. 

Compressive  Strength. — In  the  introduction  to  this  chapter 
it  was  stated  that  shipbuilding  concrete  should  possess  maximum 
strength,  elasticity,  and  watertightness.  Since  these  qualities  do 
not  always  go  together  it  becomes  necessary  to  investigate  each 
separately  by  actual  test,  and  it  may  be  found  that  a  partial 
sacrifice  of  one  quality  is  necessary  to  obtain  the  others. 

Investigators  in  different  countries  have  tried  to  devise 
empirical  formulas  giving  definite  mathematical  relations  between 
the  properties  of  finished  concrete  and  the  proportions  of  the 
mixture.  The  author  is  inclined  to  believe  that  the  application 
of  such  formulas,  with  their  preliminary  preparations  of  aggregate, 
will  be  restricted  mostly  to  laboratory  investigations  because  no 
general  rule  can  cover  the  conditions  for  every  shipyard  ;  further, 
concrete  is  made  on  the  spot,  not  manufactured  in  a  laboratory 
by  scientists,  and  shipped  to  the  builder  like  steel. 

Amongst  the  large  number  of  rules  presented  by  different 
authorities  to  determine  the  strength  of  concrete  the  author 
has  only  been  able  to  recognize  two  which  apply  in  all  cases, 
namely  : 

1.  The  strength  of  concrete  increases  with  inherent  strength  of 
cement  and  aggregates,  provided  the  minimum  amount  of  water  to 
make  the  mixture  workable  is  used. 

2.  Strength  increases  with  age  for  an  indefinite  period. 

It  may  be  assumed  that  the  strength  of  concrete  generally 
increases  with  the  richness  of  mixture  (amount  of  cement),  but 
this  is  not  always  the  case.  Note,  for  instance,  in  Tables  A  and  E 
that  a  mixture  1  part  cement  :  4  parts  aggregate  (1  :  1-5  :  2-5) 
has  greater  strength  than  1  part  cement  :  2J  parts  aggregate 
(1:2:  0-5)  or  1  part  cement :  3  parts  aggregate  (1  :  2-25  :  0-75). 

Further,  density  generally  denotes  strength,  but  this  assump- 
tion also  has  frequent  exceptions,  and  cannot  be  considered  a 
rule.  Maximum  density  generally  means  maximum  water- 
tightness,  but  the  greatest  strength  is  often  obtained  by  using 
coarser  aggregates  in  the  mixture.  Aggregates  of  different 
sizes  and  gradings  may  be  combined  in  different  proportions  to 
produce  concretes  of  practically  the  same  strength. 


SHIPBUILDING  CONCRETE 


131 


Everything  depends  on  the  materials  actually  used  and  the 
placing  and  curing  of  .the  concrete.  Rules  and  results  of  tests 
with  other  mixtures  are,  therefore,  only  of  comparative  value, 
and  each  shipbuilder  ought  to  carry  out  his  own  investigations 
with  all  materials  at  his  disposal.  Such  tests  should  investigate 
compressive  strength,  shear  strength,  adhesion  to  steel  (bond), 
elasticity,  and  watertightness. 

In  Table  A  are  shown  7  day  and  28  day  tests  of  one  mortar 
and  six  different  mixtures  of  concrete.  Some  further  tests  of 
compression  after  7  days,  28  days,  and  3  months  are  given  in 
Table  E  for  two  mortars  and  one  concrete,  mixed  and  placed 
under  two  different  conditions,  but  from  the  same  materials. 

TABLE  E.— COMPRESSIVE  STRENGTH 


Proportions  by 
Cement,  Sand, 

Volume  : 
Gravel. 

Percentage  of 
Water  by      . 
Volume. 

Compression,  Ib.  per  sq.  inch,  average  after 

7  days. 

.28  days. 

3  months. 

1  :  2 

15 

2,530 

3,780 

4,270 

1  :  2-5 

15 

2,020 

3,540 

3,840 

1:1-5: 

2-5 

11 

2,335 

3,520 

4,520 

Very  dry  mixture,  mechani- 

cally rammed  : 

1:2 

8i 

5,700 

6,800 

7,990 

1:2-5 

H 

4,880 

5,890 

6,900 

1:1-5: 

2-5 

7-2 

4,680 

6,310 

7,830 

All  the  figures  represent  an  average  of  three  tests.  The  first 
concretes  were  of  usual  consistency,  and  were  placed  in  the 
forms  without  any  puddling.  A  thin  knife  was  inserted  along 
the  inner  sides  of  the  forms,  which  were  slightly  tapped  outside, 
and  the  free  surface  was  smoothed  off  with  a  straightedge.  The 
last  concretes  were  made  very  dry  and  mechanically  rammed 
in  the  forms.  All  the  materials  were  of  the  same  quality.  The 
test  cubes  of  mortar  were  4"  X  ¥  X  4"  and  of  concrete  8"  X  8" 
X  8".  The  average  specific  gravities  of  the  first  mixtures 
were  2-27  for  the  mortars  and  2-40  for  the  concrete  ;  for  the 
second  mixtures  they  were  respectively  2-35  and  2-43.  The 
compressive  strength  after  7  days  is  seen  to  be  more  than  100  per 
cent,  greater  for  the  mechanically  rammed,  dry  concrete  ;  but 
the  mixture  was  much  too  dry  to  use  in  shipbuilding. 

Shear  Strength. — In  Table  F  the  shearing  strengths  are  given 
for  the  concretes  considered  in  Table  A  ;  each  figure  represents 
the  average  of  three  tests. 


SEAGOING  AND   OTHER  CONCRETE  SHIPS 


Compared  to  results  obtained  by  other  experimenters  the 
shearing  values  are  very  low.  It  is  probable,  therefore,  that, 
in  spite  of  precautions  taken,  considerable  tension  has  contri- 
buted to  the  failure  of  each  specimen.  Pure  shear  stress  is 
difficult  to  obtain  in  a  laboratory  and  rarely  occurs  in  practice. 
The  tests  were  carried  out  on  briquettes  2f"  X  2f"  X  8J",  firmly 
fixed  in  iron  frames  from  both  ends  towards  the  middle  third, 
which  was  loaded. 

A  formula  sometimes  used  to  find  the  shearing  strength  of 
concrete  is  : 

S  =  \  .  V  @-  T,     where  8  =  shear  strength,    C  =  compres- 
sive  strength,  T  =  tensile  strength. 

TABLE    F.—  SHEARING    STRENGTH 


Proportions  by  Volume  : 
Cement,  Sand,  Gravel. 

Percentage  of 
Water  by 
Volume. 

Shear,  Ib.  per 
sq.  inch, 
after  28  days. 

,     01  f  1  :  2-00  :  0-50 
1  :  **\i  :  1-85:  0-65 

15 
144 

645 
600 

1:3     1  :  2-25  :  0-75 

14| 

560 

(  1  :  1-50  :  2-50 

11 

620 

1:4  {  1  :  1-90:  2-10 

12 

705 

1  1  :  2-25  :  1-75 

13 

605 

The  total  shearing  surface  was  100  sq.  cm.,  and  the  load 
varied  from  3|  to  4J  tons.  The  results  are  uniform,  and  since 
shear  in  concrete  ships  is  resisted  principally  by  reinforcement 
the  shearing  strength  of  concrete  is  relatively  less  important 
than  the  compressive  strength. 

Bond  Strength. — Table  G  gives  values  of  the  "bond"  or 
adhesion  between  steel  and  the  surrounding  concrete  after 
28  days,  for  the  mixtures  of  concrete  considered  in  Tables  A,  E, 
and  F. 

TABLE   G.— ADHESION   BETWEEN   STEEL   AND    CONCRETE 


Proportions  by  Volume  : 
Cement,  Sand,  Gravel. 

Percentage  of 
Water  by 
Volume. 

Stress  at  initial  slip 
of  steel,  Ib.  per  sq. 
inch,  after  28  days. 

,  .  91/  1:2-00:  0-50 
1  '  Z*U  :  1-85:  0-65 

15 

640 

775 

1:3      1  :  2-25  :  0-75 

14£ 

775 

{1  :  1-50  :  2-50 

11 

790 

1  :  1-90:  2-10 

12 

650 

1  :  2-25  :  1-75 

13 

535 

SHIPBUILDING  CONCRETE 


133 


The  tests  were  made  by  pulling  rods  out  of  concrete  blocks, 
in  which  they  were  inserted  about  5  to  7  inches.  The  exact 
diameters  of  the  rods  varied  from  15-1  to  15-5  mm.,  and  the 
surface  of  contact  between  steel  and  concrete  varied  from  66-4 
to  86-2  sq.  cm.  The  steel  rods  were  taken  from  stock  and  tested 
in  their  usual  condition,  with  a  slight  surface  film  of  rust.  The 
bond  between  concrete  and  steel  is  nearly  always  increased 
considerably  by  mechanical  means,  namely,  by  the  fitting  of 
hooks  on  the  ends  of  rods,  or  by  the  use  of  special  bars  either 
twisted  or  provided  with  lugs. 

Elasticity.  — Tables  H  and  I  give  the  moduli  of  elasticity, 
in  compression  and  tension,  for  the  concretes  already  considered, 
together  with  measurements  of  the  permanent  and  total  defor- 
mations in  each  test.  The  compressive  tests  were  carried  out 
with  briquettes  2f"  X  2|"  X  8J",  sectional  area  50  sq.  cm.,  age  28 
days.  Each  figure  is  the  average  of  three  tests. 

TABLE    H.— ELASTICITY    OF    CONCRETE    IN    COMPRESSION 


Proportions  of  Volume  : 
Cement,  Sand,  Gravel. 

Percentage  of 
Water  by 
Volume. 

Reduction  in  Length  per  cent. 

Modulus  of 
Elasticity, 
Ib.  per  sq.  inch. 

Permanent. 

Total. 

,     9,(1  :  2-00:  0-50 

15 

0-066 

0-190 

5,405,000 

1  ^*U  :  1-85:  0-65 

14£ 

0-062 

0-171 

4,975,000 

1:3      1  :  2-25  :  0-75 

14| 

0-057 

0-158 

6,400,000 

(1  :  1-50:  2-50 

11 

0-075 

0-167 

6,255,000 

1:4  1  1  :  1-90:  2-10 

12 

0-042 

0-103 

6,045,000 

1  1  :  2-25:  1-75 

13 

0-041 

0-092 

4,695,000 

The  tensile  tests  were  carried  out  with  briquettes  21"  X 
2}"  X  about  5f",  sectional  area  50  sq.  cm.,  age  28  days.  Since 
the  elongations  were  very  irregular  the  results  in  Table  I  are 
given  for  individual  tests. 

Properly  speaking  an  inelastic  material  like  concrete  has  no 
coefficient,  or  modulus,  of  elasticity,  which  is  the  ratio  between 
unit  stress  and  unit  stretch  or  deformation  within  the  elastic 
limit.  The  modulus  of  elasticity  for  concrete  is,  therefore,  defined 
as  the  ratio  of  an  increment  of  stress  to  a  corresponding  increment 
of  deformation. 

It  increases  with  age  and  richness  of  mixture  and  varies 
considerably  with  different  aggregates  and  cements.  For  cinder 
concrete  it  is  about  half  of  the  value  obtained  for  ordinary  stone 
or  gravel  concrete. 


134        SEAGOING  AND   OTHER   CONCRETE   SHIPS 


TABLE    I.— ELASTICITY    OF    CONCRETE    IN    TENSION 


Proportions  by  Volume  : 
Cement,  Sand,  Gravel. 

Percentage  of 
Water  by 
Volume. 

Test 
No. 

Elongation  per  cent. 

Modulus  of 
Elasticity, 
Ib.  per  sq.  inch. 

Permanent. 

Total. 

f 

a, 

0-0012 

0-0055 

4,700,000 

ri  :  2-00:  0-50 

15 

b 

0-0010 

0-0042 

3,550,000 

1 

c 





— 

1 

j 

a 

0-0019 

0-0058 

4,065,000 

ll  :  1-85:  0-65 

b 

0-0039 

0-0075 

4,700,000 

1 

c 

0-0019 

0-0055 

3,780,000 

( 

a 

0-0011 

0-0049 

4,380,000 

1:3      1  :  2-25  :  0-75 

14| 

b 

0-0016 

0-0042 

4,380,000 

I 

c 

0-0008 

0-0035 

4,065,000 

a 

0-0033 

0-0069 

— 

1  :  1-50  :  2-50 

11 

b 

0-0033 

0-0075 

3,780,000 

1 

c 

0-0018 

0-0051 

5,175,000 

( 

a 

0-0044 

0-0080 

5,690,000 

1:4      1  :  1-90:  2-10 

12 

b 

0-0005 

0-0025 

4,065,000 

{ 

c 

0-0033 

0-0061 

4,380,000 

1  :  2-25:  1-75 

13        { 

a 
b 

0-0006 
0-0024 

0-0017 
0-0070 

5,175,000 
4,380,000 

Watertightness. — Since  the  practical  experience  gained  from 
building  concrete  lighters  proved  these  to  be  perfectly  tight 
laboratory  tests  of  watertightness  were  only  carried  out  for  one 
of  the  six  concrete  mixtures  previously  tested  for  strength,  etc., 
namely,  the  mixture 

1  cement :  1J  fine  aggregates  :  2J  coarse  aggregate 

Four  plates  4  inches  thick  of  slightly  conical  shape,  average 
diameter  8J  inches,  were  tested. 

(1)  Head  of  water  20'  0"  ;    examination  made  after  5  days  : 
Test  No.   1,  under  glass  cover  :    no  trace  of  moisture  on  surface. 

2,   no   covering :     a   fine    crack   occurred    around   the 
perimeter  ;   the  surface  appeared  entirely  dry. 

(2)  Head  of  water  40'  0"  ;    examination  made  after  3  days  : 
Test  No.   1  :   entirely  dry. 

2  :    slight  drops  beginning  to  form  around  perimeter. 

3  :    entirely  dry. 
„          4  :    entirely  dry. 

(3)  Leakage  of  water  under  40'  0"  head  : 

Between  3-7  days.     Between  7-14  days. 

Test  No.    1         .  2  g.  126  g. 

2  .          .       72  g.  Ill  g. 

3  .          .        0  32  g. 
400 


SHIPBUILDING  CONCRETE  135 

The  average  leakage  shown  by  all  four  tests  during  the  last 
week  was  67  g.  =0-19  cub.  cm.  per  sq.  cm.  surface  per  week, 
or  in  round  figures,  a  2  mm.  layer  of  water  per  week. 

Note. — The  above  water- pressure  was  equal  to  about  three 
times  that  on  bottom  of  the  standard  size  ships  to  be  constructed. 
The  thickness  of  the  concrete  plates  tested  was  only  4  inches, 
while  the  thickness  of  bottom  in  ships  of  this  size  is  generally 
4J  to  5  inches,  of  which  the  outside  J  inch  is  waterproof  cement 
mortar  finish. 

For  these  tests  1  per  cent,  of  alum  was  dissolved  in  the  water 
used  in  making  the  concrete,  but  later  experience  has  shown  that 
rich  concretes  (say  1  :  1-85  :  0-65),  proportioned  to  obtain  the 
greatest  density,  and  of  proper  consistency,  are  watertight  under 
moderate  pressures  without  any  artificial  means  of  waterproofing. 

Some  of  the  much  advertised  compounds  may  help  to  make 
lean  concretes  waterproof,  but  they  nearly  all  reduce  the 
strength.  To  secure  complete  watertightness  in  ships  a  rich 
mixture  of  concrete  with  an  outside  J  inch  finishing  coat  of 
mortar  is  generally  quite  sufficient.  In  order  to  make  still  more 
sure,  and  to  prevent  marine  growths,  concrete  ships  may  be 
painted  below  the  water-line  with  hot  coal-tar. 

Contraction  and  Expansion. — Concretes  expand  with  rise  in 
temperature  and  contract  when  the  temperature  is  lowered. 
The  coefficient  of  expansion  per  degree  F.  is  0-000006  for  a 
mortar  of  mixture  1  :  2,  and  0-00000677  for  a  concrete  of  mixture 
about  1  :  1  \ :  3,  according  to  experiments  made  at  Cornell 
University  by  Prof.  A.  P.  Mills.  The  range  of  temperatures 
was  from  70°  to  212°  F.  on  specimens  from  one  to  eight 
months  old. 

Tests  show  that  the  coefficient  of  expansion  increases 
slightly  with  richness  of  mixture.  A  fact  of  great  importance  is 
that  average  concrete  has  almost  exactly  the  same  coefficient  of 
expansion  as  average  steel  (from  0-00000617  to  0-00000676). 

Concretes  expand  also  under  moisture  and  contract  when 
dried  or  exposed  in  air  after  having  been  immersed  in  water  ; 
and  this  is  true  not  only  of  the  early  hardening  period,  but  even 
after  20  years  in  service.  Prof.  A.  H.  White  at  the  University 
of  Michigan  (Proc.  Am.  Soc.  Test.  Mat.,  vols.  xi.  and  xiv)  found 
that  two  briquettes  I"  X  1"  X  4",  of  1  :  3  mortar,  expanded 
0-05  per  cent,  in  length  in  a  3-4  months'  period  when  placed  in 


136       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

water  ;  they  contracted  in  air  at  about  the  same  speed.  Other 
tests  with  the  same  proportions,  but  other  brands  of  cement, 
showed  greater  changes  in  volume.  A  mortar  stored  in  air 
contracted  about  1-10  per  cent,  during  the  first  three  months, 
and  a  briquette  of  a  rich  mortar  finishing  coat  from  a  side  walk 
20  years  old  expanded  about  0-16  per  cent,  through  being  stored 
for  two  years  in  water  ;  while  a  specimen  from  the  gravel  concrete 
base  of  the  same  side  walk  expanded  about  0-12  per  cent,  in  the 
same  period. 

The  conclusions  obtained  from  various  tests  are  that  concrete 
drying  out  in  air  generally  contracts  from  0-02  to  0-05  per  cent., 
and  expands  at  least  half  this  amount  when  immersed  in  water. 
This  means  (assuming  E  =  2,000,000)  that  tensile  stresses  from 
400  to  1,000  Ib.  per  sq.  inch  may  occur  in  a  concrete  structure 
restrained  from  freely  contracting  ;  the  concrete  will  then  crack 
and  frequently  does  so.  Difficulties  from  strains  induced  by 
expansion  are  more  rare  and  never  cause  failure  in  compression, 
but  at  the  worst  a  buckling  action  in  large  surfaces. 

Shrinkage  stresses  in  concrete,  with  resulting  hair-cracks  in 
the  surface,  are  at  present  seemingly  unavoidable,  but  they  can 
be  reduced  in  size  to  be  quite  harmless  and  of  no  importance. 
The  best  means  of  accomplishing  this  are  : 

1.  Light  steel  reinforcement  (temperature  bars)  placed  near 
the  surface  to  absorb  internal  stresses  from  expansion  and  con- 
traction and  distribute  these  so  that  no  large  cracks  can  occur. 

2.  The  exterior  mortar  finish  should  not  be  too  rich  nor  too 
thick.     It  must  adhere  closely  to  the  underlying  concrete,  which, 
being  protected  against  moisture  and  temperature  variations, 
changes  less  in  volume. 

3.  The  outside  finish  should  not  be  trowelled  too  much,  since 
this  brings  the  cement  out  and  causes  more  hair-cracks  in  the 
surface. 

Trass  Concrete. — The  subject  of  using  Trass  l  or  other  puzzo- 
lanas  as  a  partial  substitute  for  Portland  Cement  in  rich  con- 
cretes has  not  been  sufficiently  investigated  to  justify  definite 
conclusions.  Most  of  the  trass  obtained  in  Europe  comes  from 
Germany,  and  it  is  natural  that  investigations  regarding  the 
material  have  been  made  there.  If  the  advantages  claimed  by 

1  Trass  is  finely  ground   Tufa  (Trass-stone),  containing  chiefly  silica  and 
some  alumina.     Used  alone  it  has  very  little  cementing  power. 


SHIPBUILDING  CONCRETE 


137 


manufacturers  of  trass  can  be  substantiated  the  material  is  of 
considerable  importance  to  the  concrete  shipbuilding  of  the 
future.  But  it  should  be  borne  in  mind  that  the  Portland 
Cement  of  to-day  is  of  higher  quality  than  that  of  about  20  years 
ago,  when  some  of  the  investigations  were  made.  The  tests 
recorded  in  Table  J  were  made  by  Herr  Helbing  at  Essen  in  1906. 
Since  the  amount  of  water  and  method  of  mixing  and  placing 
are  not  stated,  the  results  are  of  uncertain  value,  and  unfortun- 
ately they  deal  only  with  trass  mortars. 

TABLE    J.— COMPRESSIVE    STRENGTH    OF    TRASS    MORTARS 


Proportions  by  Volume  : 

Compression,  Ib.  per  sq.  inch,  average  at 

Cement,  Trass,  Sand. 

14  days. 

28  days. 

100  days. 

1  :  0-5  :  3-5 

3,340 

4,200 

5,900 

1:0-7:3 

2,850 

3,900 

5,040 

1:0-8:4 

3,040 

3,730 

4,950 

1:1:5 

2,350 

3,020 

3,900 

1:1:6 

2,040 

2,740 

3,770 

Note. — Since  the  tests  were  supervised  by  a  Government 
Engineer  in  connexion  with  the  construction  of  municipal  water- 
works the  results  should  be  comparable  with  those  required  for 
concrete  used  in  actual  land  construction. 

The  tests  recorded  in  Table  K  were  carried  out  at  the 
Laboratory  of  the  Technical  High  School  at  Berlin  in  1910  with 
trass  from  Andernach. 

TABLE    K.— COMPRESSIVE    STRENGTH    OF    TRASS    MORTARS 


Proportions  by  Volume : 


Compression,  Ib.  per  sq.  inch,  average  at 


Cement,  Trass,  Sand. 

14  days. 

28  days. 

3  months. 

1  :  1 
1  :  1 

3 
4 

6,060 
4,520 

7,530 

5,780 

7,050 

Note. — The  figures  stated  are  averages  of  10  tests,  the 
majority  of  which  are  remarkably  consistent.  The  average 
ratios  of  tensile  strength  to  compressive  strength  were  : 

;r     at  14  days 


13-1 
1 


28 


3  months 


138       SEAGOING  AND    OTHER   CONCRETE   SHIPS 

The  proportions  of  trass  recommended  are  :  30  per  cent, 
trass  -f  70  per  cent.  Portland  Cement,  and  40  per  cent, 
trass  -+-  60  per  cent.  Portland  Cement. 

Apart  from  the  lower  cost,  which  may  be  doubtful  in  countries 
where  trass  is  not  found  and  Portland  Cement  is  manufactured, 
the  principal  advantages  claimed  as  the  result  of  adding  trass 
to  concrete  are  : 

(1)  Greater  elasticity. 

(2)  Greater  resisting  power  against  action  of  sea- water. 

(3)  Lighter  weight. 

Definite  information  is  not  available  on  the  first  point.  The 
modulus  of  elasticity  has  not  been  ascertained,  and  the  numerous 
tests  of  tensile  strength  generally  referred  to  in  the  German 
statements  give  no  proof  of  the  amount  of  stretch,  or  elasticity,  of 
the  mass.  The  results  give  only  the  resistance  against  stretch, 
which  is  of  small  interest  in  reinforced  concrete  construction, 
where  all  tensile  stresses  are  assumed  to  be  absorbed  by  the  steel. 

As  regards  the  claim  in  respect  of  increased  resistance  to  the 
action  of  sea-water,  there  is  probably  some  benefit  from  an 
admixture  with  trass  for  lean  concretes,  especially  with  the  Port- 
land Cement  of  20  years  ago,  that  contained  more  free  lime 
which  became  chemically  bound  with  the  trass.  In  shipbuilding 
concrete  the  use  of  trass  should  not  be  necessary. 

The  weight  of  ground  trass  is  claimed  by  manufacturers  to 
be  40  per  cent,  less  than  that  of  Portland  Cement.  If  an  admix- 
ture of  30-40  per  cent,  of  trass  is  added  to  the  Portland  Cement 
in  shipbuilding  concrete,  there  is  a  reduction  of  about  5  per  cent, 
in  the  weight  of  concrete. 

Action  of  Sea-water.— So  long  ago  as  1882  Dr.  W.  Michaellis, 
of  Berlin,  waged  a  war  against  the  German  Cement  Makers' 
Association  in  favour  of  adding  trass  to  Portland  Cement,  in 
order,  especially,  to  increase  the  resistance  of  concrete  to  the 
action  of  sea- water.  He  submitted  a  paper  on  the  subject  to 
the  Institution  of  Civil  Engineers  (No.  2592,  vol.  cvii,  session 
1891-2,  part  No.  1)  and  made  a  comprehensive  study  of  the 
subject  which  has  been  of  benefit  to  the  manufacture  of  Portland 
Cement.  He  claimed  that  the  excess  of  lime  in  Portland  Cement 
which  reacts  with  soluble  sulphates  in  sea- water  to  form  gypsum 


SHIPBUILDING  CONCRETE  139 

should  be  prevented  by  providing  trass  as  a  suitable  agent  to 
bind  the  free  lime  and  form  hydraulic  mortar. 

For  many  years  the  general  question  of  the  action  of  sea- 
water  has  been  much  discussed  in  regard  to  concrete  docks, 
breakwaters,  and  harbour  works  in  general.  The  quality  of 
concrete  used  in  these  structures  is  much  inferior  to  shipbuilding 
concrete  ;  the  mixture  is  never  richer  than  1  part  Portland 
Cement :  6  parts  Aggregate  (1:2:4),  the  grading  of  fine  and 
coarse  aggregate  has  hardly  ever  been  done  according  to  scientific 
principles,  nor  was  the  importance  of  using  a  minimum  of  water 
in  mixing  the  concrete  understood.  Further,  a  considerable 
amount  of  concrete  construction  for  harbour  works,  etc ,  is 
poured  in  situ,  where  below  the  water-line,  and  this  prevents  the 
application  of  a  protective  covering  of  rich  mortar. 

Sea-water  has  a  disintegrating  action  on  poor  concrete,  but 
even  before  disintegration  takes  place  corrosion  of  the  reinforce- 
ment, shown  by  rust  spots  on  the  surface  of  the  concrete,  may 
be  observed.  The  rust  spots  are  frequently  followed  by  the 
cracking,  and  displacement,  of  the  surface  concrete  due  to  the 
expansion  of  the  reinforcement  resulting  from  corrosion.  If  the 
concrete  is  of  poor  quality  a  thickness  of  1 J  inches,  or  even  more, 
may  be  insufficient  to  protect  the  reinforcement  against  the 
action  of  sea-water.  But  shipbuilding  concrete  can  protect 
the  reinforcement  with  a  thickness  of  one- half  to  three-quarters 
of  an  inch. 

In  the  shipbuilding  concrete  made  by  the  author's  firm  the 
aggregates  were  scientifically  graded,  the  mixture  was  rich, 
properly  proportioned,  of  the  right  consistency,  and  carefully 
placed.  The  concrete  was  therefore  watertight,  but  for  further 
assurance  it  was  protected  with  an  outside  mortar  finish,  carefully 
placed,  and  inspected  by  sounding  the  entire  surface  with  heavy 
hammers  before  the  ships  were  launched.  Coal  tar  or  anti- 
fouling  composition  painted  on  the  hulls  went  still  further  ta 
make  the  hulls  immune  to  the  action  of  sea-water.  And  none 
of  the  ships  showed  any  sign  of  the  action  of  sea-water  on  the 
concrete. 

Action  of  Oils,  etc. — The  conclusions  reached  with  regard  to 
the  action  of  sea- water  on  concrete  apply  also  to  the  action  of 
oils,  alkalies,  acids,  etc.  :  first-class  concrete,  such  as  shipbuilding 
concrete,  is  not  attacked  appreciably  by  oils,  etc.,  under  ordinary 


140       SEAGOING  AND   OTHER  CONCRETE   SHIPS 

conditions,  but  a  poor  grade  of  concrete  is  attacked.  But  strong 
acids  which  injure  other  materials,  such  as  sulphuric  and  muriatic 
acids,  will  also  affect  concrete,  and  in  tanks  to  hold  these  acids 
elastic  and  proof  linings  are  necessary.  Substances  which 
contain  acids  in  diluted  form,  manure  for  example,  may  injuri- 
ously affect  green  concrete,  but  not  concrete  that  has  hardened 
and  been  properly  cured.  It  has  been  proved  by  many  years 
of  experience  that  concrete  sewers  are  not  seriously  injured  by 
the  action  of  sewage,  which  commonly  contains  diluted  acids 
and  other  active  chemicals. 

Petroleum  and  the  heavier  mineral  oils  used  for  fuel  do  not 
injure  concrete,  but  oils  containing  fatty  acids  produce  injurious 
effects  by  forming  compounds  of  lime.  For  small  tanks  with 
no  great  head  of  oil,  and  for  reservoirs  below  ground  level  where 
slight  initial  leakage  is  of  minor  importance,  special  oilproofing 
is  not  necessary,  provided  the  concrete  is  of  first-class  quality 
and  is  properly  reinforced  so  that  cracks  do  not  occur.  Deposits 
in  the  pores  from  heavy  oils  will  after  a  few  days  make  the 
concrete  oilproof  for  low  pressures  if  it  is  not  initially  perfectly 
tight.  But  even  with  rich  mixtures  such  as  1  part  cement  to 
2 1  or  3  parts  aggregate  a  thin  surface  coat  of  1  part  cement 
to  1J  or  2  parts  sand  should  be  plastered  on  the  inside  to  fill 
crevices  or  irregularities  from  the  forms. 

Interesting  tests  were  carried  out  by  the  U.S.  Bureau  of 
Standards  on  a  large  number  of  small  concrete  tanks  15  inches 
diameter  by  16  inches  high  inside,  with  no  oilproofing  or  finish. 
A  few  tanks  were  covered  and  tested  under  a  pressure  head  of 
25  feet.  Eleven  kinds  of  mineral  oils,  varying  from  commercial 
petrol  to  very  viscous  residual  oil  (paraffin),  five  vegetable  oils 
of  different  types,  and  two  animal  oils  were  used,  during  a  period 
of  13  months.  During  this  time  the  penetration  of  the  oils  not 
under  pressure  head  into  the  concrete  averaged  about  0-6  inch. 
Cylinders  stored  in  the  oils  showed  no  appreciable  diminution 
in  compressive  strength,  and  only  coco-nut  oil  and  lard  oil  seemed 
to  attack  the  concrete  surface  appreciably.  The  tests  with 
25  feet  head  on  the  tanks  showed  that  even  under  this  condition 
heavy-  and  medium-grade  fuel  oils  can  be  stored  in  concrete 
tanks  without  excessive  loss.  The  concrete  in  the  test  tanks 
was  made  with  1  part  cement,  f  part  sand,  1J  parts  small 
gravel.  The  storage  of  kerosenes  and  gasolines  under  a  con- 


SHIPBUILDING  CONCRETE  141 

siderable  head  is  not  economical  unless  the  concrete  is  oilproofed 
beforehand. 

For  low  pressures  of  only  a  few  feet  various  types  of  coatings 
can  be  applied  with  a  brush  to  the  concrete  surface,  such  as  : 

Shellac  Varnish, 
Sodium  Silicate  (water-glass), 
Magnesium  Fluosilicate  (MgSiFl6), 
Spar  Varnish. 

The  best  results  are  obtained  when  the  first  coat  is  thinned 
out,  the  second  made  somewhat  thicker,  and  the  third  coat  of 
heavy  consistency.  A  stiff  brush  should  be  used  and  the  concrete 
surface  must  be  perfectly  clean,  dry,  and  free  from  cracks  other 
than  unavoidable  hair-cracks.  The  author  has  used  shellac 
varnish  and  sodium  silicate  ;  while  in  America  spar  varnish  and 
magnesium  fluosilicate  have  been  tried  with  considerable  success. 
The  latter  is  the  main  constituent  of  numerous  liquid  "  hardeners  " 
for  concrete  floors,  etc.,  which  are  sold  under  different  trade 
names.  Magnesium  fluosilicate  fills  the  pores  and  neutralizes 
free  lime  in  the  concrete  which  would  otherwise  attack  the 
film  of  oilproof  coating. 

A  method  of  oilproofing  which  was  used  in  the  construction 
of  the  oil-tankers  for  the  Standard  Oil  Company  described  in 
Chapter  VI  was  developed  by  the  author's  brother,  Mr.  Hermann 
Fougner.  The  method  was  found  satisfactory  for  petrol  under 
a  20  feet  head,  and  it  will  no  doubt  be  satisfactory  for  heavier 
oils  under  much  larger  heads.  It  consists  in  using  a  mixture  of 
finely  pulverized  iron,  Portland  Cement,  and  sand  in  the  pro- 
portions : 

100  Ib.  bag  of  pulverized  iron. 
1  bag  of  Portland  Cement, 
f  cub.  feet  of  sand. 

To  the  water  used  for  mixing  one  per  cent,  of  ammonium 
chloride  should  be  added  if  the  worker  can  endure  the  fumes 
generated,  for  this  addition  accelerates  the  oxidation  which  is 
the  source  of  the  oil- tightness.  The  concrete  surface  to  be 
treated  must  be  thoroughly  clean,  moderately  roughened  with 
a  stiff  wire  brush,  and  made  thoroughly  moist.  The  mixture  is 


142       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

then  hand-plastered  in  the  usual  manner.  A  finishing  coat  is 
applied  with  a  brush  a  few  hours  after  the  plastered  coat  has 
set.  For  this  purpose  iron-powder  with  five  per  cent,  of 
ammonium  chloride  is  mixed  with  water,  the  mixture  being 
made  as  stiff  as  can  conveniently  be  handled,  and  being  stirred 
frequently  so  that  the  iron  does  not  settle  to  the  bottom.  The 
quality  of  the  pulverized  iron  is  of  great  importance.  The 
material  should  be  made  from  pure  ingredients  and  not  from 
scraps  containing  dirt,  oil,  etc.  ;  the  fineness  should  be  such 
that  the  material  will  pass  a  No.  100  sieve. 

With  regard  to  this  method  of  oilproofing,  the  Head  of  the 
Marine  Department  of  the  Standard  Oil  Co.  reported  on  8th  June 
1920  as  follows  : 

"  The  oilproofing  in  the  tanks  of  our  concrete  barges  has 
been  satisfactory,  except  that  on  the  overhead  surfaces  it 
flakes  off,  and  a  better  adhesive  substance  would  be  an  im- 
provement." 

The  flaking- off  overhead  was  probably  due  in  part  to  the 
steaming  out  of  the  tanks  with  live  steam,  a  procedure  which  is 
necessary  before  workmen  may  enter  oil  tanks.  The  defect  can 
be  remedied  by  using  one  of  the  other  methods  for  the  oilproofing 
of  the  overhead  surfaces,  assuming  that  it  is  necessary  to  treat 
these  surfaces. 

Repairs. — The  simplicity  of  repairs  is  one  of  the  great  advan- 
tages of  concrete  ships.  Minor  repairs  can  frequently  be  carried 
out  at  sea  by  the  crew  ;  and  every  concrete  ship  should,  there- 
fore, carry  a  small  supply  of  materials  for  the  purpose,  such  as  : 

2  bags  of  Portland  Cement. 

4          ,,      coarse,  clean  sand, 

4  Ib.  of  alum. 

\  gall,  water-glass  (sodium  silicate). 

12  \  inch  diam.  round  steel  rods  6  feet  long. 

*••*      A  ,,  55  55  55  55 

The  cement  must  be  stored  in  a  dry  place  or  kept  in  an  air- 
tight tin. 

Penetration  of  Moisture  can  be  remedied  by  brushing  the  face 
exposed  to  water-pressure  with  a  hot  5  per  cent,  solution  of 
soft  soap.  When  this  has  dried  a  warm  5  per  cent,  solution  of 


SHIPBUILDING  CONCRETE  143 

alum  is  applied  in  the  same  way.     The  treatment  should  be 
repeated  two  or  three  times. 

Leakage  through  a  small  crack  or  hole  can  be  stopped  by  filling 
the  crack  or  hole  with  neat  cement  mixed  with  water-glass. 
The  mixture  should  be  stiff,  and  must  be  held  in  position  during 
the  setting  by  centring  ;  the  mixture  hardens  very  rapidly. 
The  hole  must  be  thoroughly  cleaned  before  being  filled. 

Larger  damage — for  example,  from  grounding  or  collision — 
may  be  repaired  while  the  ship  is  floating  if  above  the  water-line, 
otherwise  the  work  must  be  done  in  dry  dock  or  on  a  suitable 
beach.     All  fragments  of  the  crushed  concrete  must  be  removed 
and  cut  away,  so  that  the  entire  circumference  is  free  from  cracks 
or  loose  pieces.     The  edge  of  the  hole  must  be  made  rough  and 
irregular  to  allow  of  a  good  joint  being  made  with  the  new  con- 
crete and  may  widen  slightly  outwards.     If  the  reinforcement 
is  bent,  it  should  be  straightened  back  into  position  or  extra 
steel  put  in.     Broken  rods  can  be  spliced  by  placing  new  ones 
alongside,  arranging  an  overlap  of  15  diameters  on  each  side  of 
the  break,  with  hooks  of  five  diameters  on  the  ends  of  the  rods. 
The  entire  circumference  of  the  hole  must  be  thoroughly  cleaned 
with  a  stiff  wire  brush.     Centring  must  be  placed  against  one 
side  ;   this  may  be  held  in  position  by  wires  attached  to  the  rein- 
forcement.    The  concrete  should  be  mixed  with  1  part  Portland 
Cement  and  1J  parts  coarse,  well-graded  Sand  (up  to  J  in.  size). 
Alum  to  the  amount  of  two  per  cent,  should  be  mixed  in  the 
water  before  adding  this  to  the  Cement  and  Sand  previously 
mixed  dry.     The  concrete  may  be  placed  by  careful  ramming 
and  placing  boards  in  front  as  the  hole  fills  up,  or  by  throwing 
the  concrete  on  in  layers  of  plaster.     The  filling  method  is  best 
for  all  thicknesses  above  2J  inches.     The  perimeter  of  the  hole 
must  be  thoroughly  wetted  by  alum  water  mixed  with  neat 
cement  immediately  before  the  concrete  is  placed.     The  forms 
can   be  removed  after  two  or  three  days,   but  if   considerable 
water-pressure  is  exerted  against  the  repaired  portion  the  inside 
forms  should  remain  in  position  for  eight  days,  or  even  longer 
in   cold   weather,    and    should    be   well   braced.      During  frost 
the  concrete  materials   should   be  heated  and  prevented  from 
freezing  for  at  least  48  hours.     The  new  concrete  must  be  kept 
moist  for  at  least  4  or  5  days.     If  necessary,  the  outside  face 
can  be  coated  with  coal  tar  or  an  antif  ouling  composition  two 


144       SEAGOING  AND   OTHER  CONCRETE  SHIPS 

days   after   pouring,    but   it   is   preferable   to   wait   a   few  days 
longer  until  the  surface  is  dry. 

Fire-resisting    Power.  — In    connexion    with   a   proposed   oil- 
storage  tank  which  was  designed  by  the  author  for  Singapore, 


FIG.  44. — Concrete  Tank  containing  burning  oil.     Singapore,  1912. 

an  experiment  on  the  fire-resisting  power  of  concrete  was  made 
for  the  satisfaction  of  the  municipal  authorities. 

A  tank  6  feet  by  6  feet  by  6  feet  was  constructed,  the  sides 
and  bottom  being  of  2  J  inch  concrete  plastered  on  metal  sheeting. 
Into  this  were  poured  500  gallons  of  petroleum  which  was 
ignited  by  a  ball  of  waste  soaked  in  benzine.  The  flames  burst 
about  30  feet  into  the  air  with  an  explosion,  and  a  roaring  fire 


SHIPBUILDING  CONCRETE  145 

kept  blazing  for  four  hours.  The  tank  became  extremely  hot, 
but  stood  up  perfectly  to  the  pressure  of  water  from  a  fire  hose 
playing  full  force  against  the  sides.  The  internal  coats  of  cement 
mortar  flaked  off  at  the  top  during  the  conflagration,  and  cracks 
were  caused  when  the  hot  walls  were  suddenly  cooled  off  by 
water  from  the  hose.  But  no  burning  oil  escaped  from  the  tank, 
and  the  damage  was  repaired  at  the  trifling  cost  of  ten  dollars. 


10 


CHAPTER    X 
STEEL    REINFORCEMENT 

Types— Quality — High-Carbon  Steel . 

Types. — In  ordinary  land  construction  the  sectional  area  of  the 
steel  reinforcement  amounts  to  about  0-5  to  1-0  per  cent,  of  the 
sectional  area  of  the  concrete  section,  although  in  special  cases 
the  higher  figure  may  be  exceeded.  In  seagoing  concrete  ships 
the  percentage  of  the  sectional  area  occupied  by  reinforcement 
amounts  to  4-5 — 5-5  per  cent.,  or  even  more.  In  other  words, 
about  seven  times  as  much  steel  is  embedded  in  the  hull  of  a 
concrete  ship  as  there  would  be  if  the  same  amount  of  concrete 
were  used  in  construction  on  land.  Such  a  proportion  of  steel 
is  too  high  and  should  be  reduced  considerably,  both  for 
economical  and  practical  reasons. 

Bars  of  round,  square,  triangular,  octagonal,  or  almost  any 
other  section  are  used ;  they  may  be  twisted  or  provided  with 
lugs  or  indentations  to  ensure  better  bond  with  the  concrete. 
Some  bars  have  stirrups  attached,  either  shorn  directly  out  of 
flanges  in  the  section  or  by  some  other  patent  arrangement.  All 
manufacturers  claim  special  advantages  for  their  proprietary 
types,  but  as  a  rule  there  is  very  little  difference  between  their 
merits.  Reinforcement  is  also  made  in  sheets,  either  from  solid 
steel  plates  which  are  perforated  and  expanded,  or  by  weaving 
light  rods  and  wires  into  a  fabric. 

The  present  types  of  reinforcement  are  not  well  adapted  for 
shipbuilding.  All  expanded  metals,  wire  mesh,  or  other  sheet 
reinforcements  are  too  light  in  section  and  cannot  be  used  with 
economy  ;  and  the  employment  of  several  layers  is  not  advisable, 
since  the  flow  of  the  concrete  round,  and  through,  the  reinforce- 
ment would  be  seriously  obstructed.  Bars  with  rigidly  attached 
stirrups  also  obstruct  the  flow  of  the  concrete.  Round  rods 
are  used  for  sizes  below  J  inch  diameter,  and  square,  octagonal, 
or  bars  of  other  sections  are  used  for  the  larger  sizes  up  to 
1J  inch  diameter,  or  side  dimension. 

Costs  being  equal,  the  author  prefers  a  type  of  octagonal 
bar  with  cross  ribs,  because  the  quality  has  always  been  satis- 

146 


STEEL  REINFORCEMENT 


147 


factory  ;  this  type  of  bar  bends  easily  cold,  without  warping  or 
springing  out  of  place  as  square  bars  are  apt  to  do — for  example, 
in  the  bilges  before  concreting.  Square  bars  have  larger  sectional 
area  than  round  rods  of  the  same  dimension,  so  that  more  steel 
can  be  placed  in  narrow  frames  by  using  such  bars  than  by 
using  round  bars,  and  they  have  the  advantage  that  they  are 
more  rigid  and  easier  to  keep  in  position  than  round  bars,  so 
permitting  workmen  to  climb  about  the  reinforcement  without 
disturbing  it  ;  but  they  have  the  disadvantage  that  concrete 
does  not  flow  easily  round  them.  There  is  no  object  in  using 
deformed  bars  of  less  than  J  inch  size,  because  the  lugs  or  inden- 
tations become  so  small  as  to  have  no  practical  value. 

Quality. — The  steel  generally  used  for  the  reinforcement  of 
concrete  ships  is  the  mild,  medium,  open  hearth  material  used  for 
the  construction  of  steel  ships.  Such  material  must  have  the 
properties  required  to  pass,  for  example,  the  tests  laid  down  by 
Lloyd's  Register  and  Norwegian  Veritas  as  follows  : 

Tensile  breaking  strength  28  to  32  tons  per  sq.  inch. 

Elongation  of  at  least  20  per  cent,  on  a  test  piece  8  inches  long. 

Bending  the  test  piece  cold  through  180  degrees  without 
fracture,  the  internal  radius  being  1J  times  the  thickness  of 
the  test  piece. 

By  way  of  comparison,  extracts  from  the  "  Standard  Specifi- 
cations for  Billet-Steel  Concrete  Reinforcement  Bars  "  of  the 
American  Society  for  Testing  Materials  are  given  below  : 


Structural  Grade. 

Intermediate  Grade. 

Hard  Grade. 

Tensile  strength,  Ib.    per    sq. 
inch           .... 
Yield  point,  Ib.  per  sq.  inch, 
at  least     .... 
Elongation,    in  8   inches,    per 
cent.,  at  least   . 
Bending   cold   around   a   pin 
without  cracking  on  the  out- 
side of  the  bent  portion: 
Under  £  inch  diam. 

f  inch  or  over 

55,000  to  70,000 
33,000 
1,400,000 

70,000  to  85,000 
40,000 
1,300,000 

80,000 
50,000 
1,200,000 

Ten.  str. 

180  deg. 

d  =  t 
180  deg. 
d  =  t 

Ten.  str. 

180  deg. 
d  =  2t 
90  deg. 

d  =  2t 

Ten.  str. 

180  deg. 
d  =  3t 
90  deg 
d  =  3* 

d  =  diameter  of  pin  about  which  the  specimen  is  bent. 

t  =  thickness,  or  diameter,  of  specimen. 

For  bars  over  £  inch  in  thickness  or  diameter  a  deduction  of  1  from  the 
percentages  of  elongation  shall  be  made  for  each  increase  of  ^  inch  in  thickness 
or  diameter  above  f  inch. 


148       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

All  steel  must  be  free  from  paint,  oil,  heavy  rust,  or  mill  scale. 
A  slight  film  of  rust  is  not  objectionable. 

High-Carbon  Steel. — In  comparing  the  requirements  of  Lloyd's 
Register  with  the  specification  of  "  Hard  "  Billet- Steel  Rein- 
forcement Bars,  it  will  be  observed  that  the  "  Hard  "  steel  has 
considerably  greater  tensile  strength  but  less  elasticity  against 
cold  bending  than  the  shipbuilding  material.  The  difference  in 
test  requirements  arises  from  the  difference  in  the  conditions 
under  which  the  materials  do  their  work.  The  reinforcement 
in  concrete  construction,  whether  on  land  or  afloat,  is  protected 
against  shocks  and  blows  ;  and  the  forces  acting  on  it  cause 
tension,  but  neither  torsion  nor  bending.  Practically  every 
kind  of  stress  is  set  up  in  the  material  of  a  ship,  and,  in  addition, 
the  material  must  be  able  to  withstand  the  severe  treatment  it 
receives  during  its  preparation  in  the  shipyard.  Consideration 
of  these  differences  in  conditions  would  seem  to  indicate  that  it 
is  possible  to  use  a  higher  grade  of  steel  for  reinforcement  than 
for  the  construction  of  steel  ships.  But  the  higher  grades  of 
steel  have  practically  the  same  modulus  of  elasticity  as  mild 
steel ;  and  equality  in  modulus  of  elasticity  involves  equality 
in  "  stretch,"  or  deformation,  at  a  given  stress.  The  fact  that 
high-grade  and  mild  steel  will  stretch  to  the  same  extent  at  the 
same  stress  is  equivalent  to  the  fact  that  the  increased  working 
stress  permissible  with  high-grade  steel  involves  increased 
"  stretch  "  as  compared  with  mild  steel.  And  the  increased 
"  stretch  "  consequent  upon  the  adoption  of  an  increased  working 
stress  involves  an  increased  possibility  of  cracks  in  the  concrete. 
Thus  it  is  neither  breaking  strength,  nor  yield  point,  nor  elastic 
limit,  that  determines  the  value  of  a  steel  as  reinforcement ;  it 
is  the  modulus  of  elasticity,  or,  using  the  reciprocal  expression, 
it  is  the  Coefficient  of  Elongation,  that  is  the  determining  quality. 

A  high-grade  steel  with  a  high  modulus  of  elasticity  would 
be  specially  desirable  for  the  reinforcement  of  concrete  ships, 
since  the  permissible  increase  in  working  stress  would  involve 
a  reduction  in  the  weight  of  reinforcement.  Such  a  material 
cannot,  however,  be  made  at  present.  Alternatively,  a  concrete 
with  a  lower  modulus  of  elasticity,  that  is,  a  larger  coefficient 
of  elongation,  will  allow  the  great  strength  of  high- carbon  steel 
to  be  utilized  to  full  advantage.  But  this  material  is  not  obtain- 
able either. 


STEEL  REINFORCEMENT  149 

Some  engineers  object  to  the  high-carbon  steel  on  account  of 
possible  irregularity  in  quality  ;  but  strict  inspection  and  careful 
manufacture  can  eliminate  that  cause  of  complaint,  particularly 
in  the  case  of  steel  for  reinforcing  bars,  since  this  is  rolled  in 
small  sections  which  are  readily  cooled.  It  may  be  mentioned 
that  a  high- carbon  steel  containing  0-56  to  0-60  per  cent,  carbon 
is  used  in  the  United  States  for  the  manufacture  of  locomotive 
tires. 


CHAPTER    XI 
CONDITIONS  GOVERNING  STRUCTURAL  DESIGN 

Theory  of  Design — Side  Frames — Bottom  Frames — Centre  Keelson — 
Longitudinal  Strength — Strength  of  Shell  Slab — Watertight  Bulkheads — 
Norwegian  Government  Requirements — Deflection  Test  on  Lighter. 

THE  actual  strength  calculations  prepared  by  the  author  for  the 
Askelad  are  reproduced  in  the  Appendix.  For  the  purpose  of 
indicating  the  conditions  governing  the  design  of  the  structural 
members  these  calculations  are  discussed  in  the  following  pages, 
comments  being  made  on  each  item  in  the  calculations  in  turn. 

A  discussion  of  the  forces  acting  on  the  structure  of  a  ship 
is  outside  the  scope  of  this  book ;  so  is  a  lengthy  discussion  of 
the  stresses  in  reinforced  concrete  structures  whether  on  land 
or  afloat.  To  the  technical  reader,  well  versed  in  the  theory 
of  reinforced  concrete  construction,  who  desires  to  study  the 
problems  involved  in  the  consideration  of  the  strength  of  ships 
the  author  strongly  recommends  the  article  on  "  The  Theory 
and  Design  of  British  Shipbuilding,"  by  Mr.  A.  L.  Ayre,  published, 
in  British  Shipbuilding,  by  the  Syren  and  Shipping,  Limited, 
London.  In  seventeen  brief  chapters  Mr.  Ayre  has  condensed 
in  a  very  lucid  and  admirable  manner  all  the  essential  theories 
of  general  naval  architecture.  To  the  naval  architect  or  ship- 
builder who  desires  to  study  the  theory  of  reinforced  concrete 
construction  the  author  recommends  the  Concrete  Engineer's 
Handbook,  by  Hool  and  Johnson,  published  by  the  McGraw-Hill 
Book  Company,  Inc.,  of  New  York  and  London.  An  authorita- 
tive statement  on  the  theory  and  design  of  reinforced  concrete 
construction  is  the  "  Final  Report  of  the  Joint  Committee  on 
Concrete  and  Reinforced  Concrete,"  which  expresses  the  opinions 
of  the  affiliated  committees  of  the  American  Society  of  Civil 
Engineers  ;  American  Society  for  Testing  Materials  ;  American 
Railway  Engineering  Association  ;  Portland  Cement  Association  ; 
and  the  American  Concrete  Institute,  during  the  period  from 

150 


CONDITIONS   GOVEENING   STRUCTURAL   DESIGN     151 

1903  to  1916,  when  the  final  Report  was  adopted  by  the  Com- 
mittee. The  Report  is  published  in  the  Transactions  of  the 
American  Society  of  Civil  Engineers,  vol.  Ixxxi,  December  1917. 

On  the  special  subject  of  Shipbuilding  Concrete  there  is  no 
literature  so  far,  but  the  usual  theory  of  reinforced  concrete  is 
applied  with  working  stresses  modified  to  suit  the  materials  and 
conditions. 

Theory  of  Design.  —  The  flexure  formula  generally  used  for 
reinforced  concrete  beams  (slabs)  is  based  on  the  "  Straight 
Line  "  theory,  and  corresponds  with  the  accepted  theory  of  flexure 
as  applied  to  other  materials.  It  is  based  on  the  following 
assumptions  : 

1.  A  plane  section  before  bending  remains  plane  after  bending. 

2.  Adhesion    between    the    concrete    and    its    reinforcement    is 
perfect  ;    the  materials  are  therefore  stressed  in  compression  in 
proportion  to  their  moduli  of  elasticity. 

3.  The   modulus   of   elasticity  of   concrete   in   compression   is 
constant. 

4.  Tensile  stresses  in  the  concrete  are  neglected. 

5.  There  are  no  initial  stresses  in  the  materials. 

A.  RECTANGULAR  BEAMS  WITH  SINGLE  REINFORCEMENT 

Standard  notations,  see  Diagram  A. 

fs  —  tensile  unit  stress  in  steel  ; 

fc  =  compressive  unit  stress  in  concrete  ; 
Es  =  modulus  of  elasticity  of  steel  ; 
Ec  =  modulus  of  elasticity  of  concrete  ; 


M  =  moment  of  resistance,  or  bending  moment  in  general  ; 
A,  =  steel  area  ; 

b  =  breadth  of  beam  ; 

d  =  depth  of  beam  to  centre  of  steel  ; 

Jc  =  ratio  of  depth  to  neutral  axis  to  depth  d  ; 

z  =  depth  below  top  to  resultant  of  compressive  stresses  ; 

j  =  ratio  of  lever  arm  of  resisting  couple  to  depth  d  ; 
jd  =  d-z  =  arm  of  resisting  couple  ; 
A 

p  =  steel  ratio  =   -4- 


152       SEAGOING  AND   OTHER  CONCRETE   SHIPS 

The  total  compression  in  the  section  must  equal  the  total 

tension  ;  hence  : 

%fjcdb  =  pbdfs (1) 

According  to  the  first  assumption  above  : 

f°  = * .  (2) 

/        *»n        lf\  ' 

Is          n(L          K) 

Combining  (1)  and  (2)  gives  the  balanced  ratio  of  steel, 

;  or  :  p  =  J  -r-r^ ,  ...      (3) 


DIAGRAM  A.  —  ^Rectangular  Beams  with  Single  Reinforcement. 

Again  combining  equations  (1)  and  (2), 
±Jc*  =  n(l  —  k)p,  whence 


k  =  \/2pn 

The  stress  curve  being  a  straight  line,  the  resultant  of  the 
compressive  stresses  must  be  located  $lcd  above  the  neutral 
axis.  Therefore  the  arm  of  the  resisting  couple  is, 

7  =  1-P     .......     (5) 

Taking  moments  about  the  centre  of  tension  in  the  steel, 


2M 
jlcbd' 


(6) 
(7) 


CONDITIONS   GOVERNING   STRUCTURAL   DESIGN     153 

Taking   moments  about  the   centre   of  compression  in  the 
concrete, 

........     (8) 


jdA.       jd*bp 


(9) 


The  above  equations  express  all  relations  between  the 
stresses  in  beams  and  slabs  of  rectangular  section  with  single 
reinforcement. 

In  practical  design  the  equations  are  simplified  by  inserting 
the  values  of  n,  fs)  and  fc  which  have  been  found  by  tests  of 
the  materials.  They  determine  the  maximum  ratio  of  steel  and 
position  of  the  neutral  axis  (equations  (3)  and  (4)). 

For  example  : 

Maximum  working  stresses  shall  not  exceed  : 
/,  =  16,000  Ib.  per  sq.  in. 
fc  =  800  Ib.  per  sq.  in. 
n  =  15 


P  =  *  ,,—   /^ x   =  0-0107 (3) 

1) 


16000  /I 6000 


800     \800.15 


.  0-0107 .  15  -f-  (0-0107 .  15)2  —  0-0107  .  15  =  0-429 
j  =  1  —  i  .  0-429  ==  0-857 
M  =  0-857dAs16000  =  13712dAs      .......      (8) 

In  reinforced  concrete  design  the  problem  is  usually  to  find 
the  amount  of  steel  required  in  the  beam  or  slab,  and  for  this 
purpose  equation  (8)  is  the  most  practical,  with  one  important 
proviso  :  that  the  ratio  of  steel  must  not  exceed  the  value  determined 
by  equation  (3),  as  otherwise  higher  compressive  stresses  than  the 
permissible  maximum  will  occur  in  the  concrete.  That  is  to  say 
(continuing  the  previous  example)  : 

A 

p  =  ~  must  not  exceed  0-0107. 

In  other  words  :    A3  must  not  exceed  1-07  per  cent,  of  (bd). 

From  the  above  it  is  clear  that  the  moment  of  resistance  of 
the  beam  according  to  equation  (8)  depends  on  the  factor  j, 
depth  of  beam  d}  area  of  steel  As,  and  the  allowable  working 


154       SEAGOING  AND    OTHER   CONCRETE   SHIPS 

stress  in  the  steel  fs.  If  special  conditions  make  it  desirable 
to  find  the  moment  of  resistance  based  on  the  compression  of 
the  concrete,  equation  (6)  gives  the  following  value  (continuing 
the  same  example)  : 


M  _  j  .  =  Q857 

M  =  Ulbd2          ......      (6) 

By  equalizing  the  moments  of  resistance  calculated  from  the 
tension  in  the  steel  (8)  and  the  compression  in  the  concrete  (6), 
the  above-mentioned  steel  ratio  (0-0107)  appears  : 

=  13712dAs 

A   = 


For  all  lower  ratios  of  steel  the  values  of  the  factor  j  are 
greater.  It  is  therefore  a  very  safe  assumption  to  reduce  equa- 
tion (8)  to  the  simple  formula  M  =  13712dAs  in  the  example. 

B.  BEAMS  WITH  DOUBLE  REINFORCEMENT 

The  amount  of  steel  sometimes  required  in  the  top  of  isolated 
beams  to  help  the  concrete  in  compression  can  be  determined 
by  a  practical,  accurate,  and  simple  method,  which  obviates  the 
use  of  complicated  formulae. 

Assume  a  maximum,  allowable  stress  on  the  concrete  of 
800  Ib.  per  sq.  inch  as  in  the  previous  example. 

The  top  steel  must  be  covered  with  concrete,  and  is  placed, 
say,  1  inch  below  the  extreme  fibre.  Compression  here  is,  for 
instance,  700  Ib.  per  sq.  inch.  As  n  is  equal  to  15,  the  com- 
pression in  the  steel  will  be  about  15  .  700  =  10,500  Ib.  per 
sq.  inch. 

This  means  that  for  every  square  inch  of  tensile  steel  in 
excess  of  the  balanced  or  economic  ratio  (0-0107  or  1-07  per  cent.) 
there  must  in  isolated  beams  be  provided  about  1-5  sq.  in.  com- 

pressive  steel  in  the  top  (vrr^xx  =  1*51. 

As  this  steel  is  always  placed  above  the  resultant  of  com- 
pressive  stresses  in  the  simple  beam,  the  factor  /  tends  to 
increase,  and  equation  (8)  can  be  used  with  perfect  safety. 


CONDITIONS   GOVERNING   STRUCTURAL   DESIGN     155 


The  formulae  recommended  by  the  Joint  Committee  are 
A'  =  area  of  compressive  steel ; 
p'  =  steel  ratio  for  compressive  steel ; 
/',  =  compressive  unit  stress  in  steel ; 
C    =  total  compressive  stress  in  concrete  ; 
C'  =  total  compressive  stress  in  steel ; 
d'  =  depth  of  centre  of  compressive  steel ; 
z    =  depth  of  resultant  of  C  and  C'. 


DIAGRAM  B. — Beams  with  Double  Reinforcement. 

Position  of  neutral  axis, 


k  =  V  2n(p  +  p'^-j  +  n2(p  +  p')2  —  w(»  +  »') 
V  » / 

Position  of  resultant  compression, 


z  = 


Arm  of  resisting  couple, 

jd  =  d  —  z 

Fibre  stresses, 

6M 

Ic  — 


U* 


M 


Wnf*       d'\  /,       d'\\ 
kV  ~  d)  I1  "  j)J 


1°  ~  pjbd*  ~  n1* 

i.      d/ 
d 
f'8  =  nfc-j- 


1  -k 


.      (9) 

(10) 

(11) 
(12) 


156       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

C.  T-BEAMS 

b   =  width  of  flange  ; 
b'  =  width  of  stem  ; 
t  =  thickness  of  flange. 

K"  ~     D      *~  ~~       "~  — H  *          "H»  ** 


1 

*•• 

ft 

'  "  *    1  * 

lui  Vj 

i    *^      /f  (+ 

*-J 

>rx 

jd 

=—  LT 

o 

DIAGRAM  C. — T-Beams. 

Case  I.     When  the  neutral  axis  lies  in  the  flange,   use  the 
formulae  for  rectangular  beams. 

Case  II.     When  the  neutral  axis  lies  in  the  stem. 

The  following  formulae  neglect  the  compression  in  the  stem. 

Position  of  neutral  axis, 

2ndA8  +  bt* 


~  2nA8  +  2bt 

Position  of  resultant  compression, 

2t    t 


z  = 


2kd  —  t     3 
Arm  of  resisting  couple, 

jd  =  d  —  z    . 


Fibre  stresses, 


A,jd 


(15) 

(16) 

(17) 
(18) 


fc  = 


Wed 


bt  (led  -  JO  jd"  n    l—k 


(For  approximate  results,  the  formulae  for  rectangular  beams 
may  be  used.) 

The  following  formulae  take  into  account  the  compression  in 


CONDITIONS   GOVEKNING   STRUCTURAL   DESIGN     157 

the  stem  ;    they  are  recommended  where   the    flange   is    small 
compared  with  the  stem  : 
Position  of  neutral  axis, 


M=  v  -— •  ±2 - b )*  +  (nA*  +  <6 


-  b')t\* 
'~         / 


\        b' 

—  nAs  -f  (6  —  &')Z 


Position  of  resultant  compression, 

-  !O&  +  [(*d  —  ty(t  H 


*(2feJ  —  Q6  +  (JW  —  ^)26' 
Arm  of  resisting  couple, 

jd  =  d  —  z (22) 

Fibre  stresses, 

/8=A-^ (23) 

,    = 2MW ,2. 

'•      [(2M  -  t)bt  +  (kd-  t)'b'}jd 


D.  SHEAR,  BOND,  AND  WEB  REINFORCEMENT 

V  =  total  shear  ; 
V'  =  total  shear  producing  stress  in  reinforcement ; 

v  =  shearing  unit  stress  ; 
u  =  bond  stress  per  unit  area  of  bar  ; 

o  =  circumference  or  perimeter  of  bar  ; 
2o  =  sum  of  the  perimeters  of  all  bars  ; 
T  =  total  stress  in  single  reinforcing  member  ; 

s  =  horizontal  spacing  of  reinforcing  members. 

For  rectangular  beams, 


(26) 

(For  approximate  results  /  may  be  taken  at  J.) 
The  stresses  in  web  reinforcement  may  be  estimated  by  means 
of  the  following  formulae  : 

Vertical  web  reinforcement. 


T  =  (27) 


158       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

Bars  bent  up  at  angles  between  20  and  45  deg.,  with  the  hori- 
zontal and  web  members  inclined  at  45  deg., 

Ve 

T  =  i.~      .....    ..      (28) 

jd 

In  the  text  of  the  Joint  Committee's  Report  it  is  recom- 
mended that  two-thirds  of  the  external  vertical  shear  (total 
shear)  at  any  section  be  taken  as  the  amount  of  total  shear 
producing  stress  in  the  web  reinforcement.  V  therefore  equals 
two-thirds  of  V. 

The  same  formulae  apply  to  beams  reinforced  for  compression 
as  regards  shear  and  bond  stress  for  tensile  steel. 

For  T-beams, 


(30) 


(For  approximate  results  j  may  be  taken  at  J.) 


E.  COLUMNS 

A   =  total  net  area  ; 

A,  =  area  of  longitudinal  steel  ; 

Ac  =  area  of  concrete  ; 

P   =  total  safe  load. 

Total  safe  load, 

P=/.(A,  +  «AJ=/^[l+(»-l)Pl]       .     .     (31) 

Unit  stresses, 

p 

/c  =  A[l  +  (n-  l)p] 

fs  =  nfc        ........      (33) 

Side  Frames.  —  From  the  rules  of  the  Norwegian  Veritas  it 
was  found  that  for  a  ship  of  the  dimensions  of  the  Askdad  the 
frames  between  the  stern  post  and  20  per  cent,  of  the  length 
from  the  stern  would  be  1"  X  3"  X  0-44"  bulb  angles,  spaced 
23"  apart,  attached  to  a  shell  0-40"  thick.  The  arrangement  of 
a  frame  and  a  strip  of  shell  plating  one-frame  space  wide  is  shown 
on  p.  3  of  the  calculations.  For  this  frame  girder  the  moment 
of  inertia  was  calculated  as  shown,  and  it  was  found  that, 
assuming  a  working  stress  on  the  steel  of  15,000  Ib.  per  square 


CONDITIONS   GOVERNING   STRUCTURAL   DESIGN     159 

inch,  the  frame  girder  was  capable  of  resisting  a  bending  moment 
of  86,000  inch-lb.  per  foot  of  length  of  ship.  For  the  concrete 
ship  the  frames  were  to  be  spaced  4'  0"  apart,  whence  the  bending 
moment  would  be  344,000  inch-lb.  ;  adding  to  this  the  20  per 
cent,  required  by  the  Norwegian  Government  the  bending  moment 
to  be  resisted  by  the  concrete  frame  became  412,800  inch-lb. 
The  concrete  frame  varied  in  depth  from  17"  at  the  heel  to  13" 
near  the  deck,  and  the  "  effective  depth  "  was  taken  to  be  0-84 
of  the  actual  depth.  From  these  figures  and  the  bending  moment 
to  be  resisted  it  was  found  that,  assuming  a  working  stress  of 
15,000  Ib.  per  square  inch,  the  area  of  steel  required  was 
2-46  square  inches,  and  this  was  provided  by  two  1"  rib  bars  and 
one  f"  rib  bar. 

From  the  bending  moment  the  shearing  force  was  estimated 
in  the  manner  shown  in  the  calculations  ;  and  it  was  found  to 
amount  to  19,660  Ib.  The  average  section  of  the  concrete  frame 
measured  15"  X  6J",  whence  the  shear  stress  on  the  concrete 
was  found  to  be  195  Ib.  per  square  inch. 

The  frames  from  20  per  cent,  of  the  ship's  length  from  the 
stern  to  the  collision  bulkhead  in  as  teel  ship  to  Norwegian 
Veritas  rules  were  found  to  be  7J"  X  3"  X  0-44"  bulb  angles, 
23"  apart.  From  the  strength  of  such  a  frame,  and  making  the 
required  20  per  cent,  addition,  it  was  found  that  the  bending 
moment  to  be  resisted  by  the  concrete  frame  at  4'  0"  spacing  was 
456,000  inch-lb.  This  bending  moment  requires  2-50  square 
inches  of  steel  in  a  concrete  girder  whose  average  section  is 
16"  x  6J"  ;  and  the  required  amount  of  steel  was  provided  by 
the  adoption  of  the  same  reinforcement  as  in  the  other  side 
frames. 

Bottom  Frames. — For  this  type  of  steel  ship  built  to  Nor- 
wegian Veritas  rules  the  bottom  frames,  or  floors,  would  be 
0-38"  plate,  with  a  4J"  X  3"  X  0-38"  angle  at  top  and  bottom, 
and  a  0-42"  shell.  The  arrangement  of  the  material  is  shown 
on  p.  4  of  the  calculations.  For  this  girder  the  permissible 
bending  moment  per  foot  of  length  was  found  to  be  664,000 
inch-lb.,  whence  the  bending  moment  for  the  concrete  floors  at 
a  spacing  of  4'  0"  was  found  to  be  3,187,200  inch-lb. 

This  bending  moment  was  found  to  require  the  provision  of 
9  square  inches  of  steel  in  the  top  of  the  floor  beams,  which  were 
28"  deep  by  10"  broad  ;  the  necessary  material  was  provided 


160       SEAGOING  AND   OTHER  CONCRETE  SHIPS 

in  nine  I"  rib  bars.  The  compression  at  the  bottom  of  the 
floor  is  resisted  by  the  lower  part  of  the  concrete  beams  and  by 
the  concrete  shell  slab,  which  was  designed  to  be  4"  thick.  It 
was  found  that  the  sectional  area  of  concrete  provided  was 
capable  of  resisting  a  bending  moment  of  3,300,000  inch-lb., 
using  a  working  stress  of  800  Ib.  per  square  inch. 

The  foregoing  consideration  is  based  on  the  assumption  that 
the  bending  moment  on  the  floor  is  such  as  to  cause  tension  in 
the  upper  material.  But  this  is  not  always  the  case.  When 
there  is  a  full  load  of  cargo  in  the  holds  and  there  is  a  wave  trough 
at  the  midship  portion  of  the  ship  the  bending  moment  may  be 
such  as  to  cause  tension  in  the  bottom  of  the  floor.  This  possi- 
bility was  met  by  the  provision  of  about  4  square  inches  of 
steel  in  the  bottom  of  the  floor  ;  and  such  an  area  of  steel,  with 
the  depth  of  floor  adopted,  was  found  to  be  capable  of  resisting 
a  bending  moment  of  1,270,000  inch-lb.  A  bending  moment 
of  1,270,000  inch-lb.  would  be  set  up  by  a  pressure  of  about 
300  Ib.  per  square  foot  acting  downwards  on  the  bottom. 
When  the  holds  are  full  the  minimum  water- pressure  would  occur 
in  way  of  the  trough  of  a  wave,  and  would  amount  to  about 
700  Ib.  per  square  foot,  namely,  that  corresponding  to  about 
an  11  feet  "head."  Hence  to  produce  a  downward  pressure 
of  300  Ib.  per  square  foot  the  cargo  load  would  need  to  amount 
to  1,000  Ib.  per  square  foot ;  and  such  a  load  could  be  produced 
only  by  a  cargo  weighing  about  60  Ib.  per  cubic  foot.  But  the 
ship  would  be  immersed  to  her  load  draught  if  completely  filled 
with  a  cargo  weighing  about  50  Ib.  per  cubic  foot.  Hence  the 
downward  pressure  of  300  Ib.  per  square  foot  is  greater  than 
is  likely  to  be  found  in  practice,  and  so  the  floor  as  designed  is 
amply  strong. 

At  this  point  it  may  be  desirable  to  point  out  that  in  many 
elements  of  a  ship  structure  it  is  necessary  to  provide  material 
to  resist  tension  at  both  sides  of  the  cross-section  ;  the  tension 
sides  and  compression  sides  are  not  separate  and  distinct.  This 
fact  explains  in  great  measure  the  higher  percentage  of  steel 
used  in  the  construction  of  seagoing  concrete  ships  than  in 
construction  on  land. 

Centre  Keelson. — This  element  of  the  structure  was  treated 
in  exactly  the  manner  outlined  above  for  the  side  and  bottom 
frames,  and  so  comment  is  not  necessary. 


CONDITIONS   GOVERNING   STRUCTURAL   DESIGN     161 

Longitudinal  Strength. — As  far  as  the  strength  of  a  ship  as 
a  whole  is  concerned,  the  worst  possible  cases  occur  when  the 
ship  is  fully  loaded.  There  are  two  "  worst  possible  "  cases.  In 
both,  the  ship  is  assumed  to  be  sailing  at  right  angles  to  waves 
of  her  own  length.  In  one  case  there  is  a  crest  of  a  wave  at 
amidships  and  a  trough  at  each  end  ;  the  concentration  of 
support  amidships  and  the  diminution  of  support  at  the  ends 
cause  the  ends  of  the  ship  to  droop  relatively  to  the  middle 
portion  and  set  up  tension  in  the  deck.  The  ship  is  then  said 
to  be  "  hogging."  In  the  other  case  there  is  a  wave  crest  at 
each  end  and  a  wave  trough  amidships  ;  the  excess  of  support 
at  the  ends  and  the  defect  of  support  amidships  cause  the  middle 
portion  of  the  ship  to  droop  relatively  to  the  ends  and  set  up 
tension  in  the  bottom  shell.  The  ship  is  then  said  to  be  "  sagging." 
The  two  conditions  are  illustrated  on  pp.  205  and  206  of  the  calcu- 
lations in  the  Appendix. 

For  any  ship  the  distribution  of  total  weight  can  be  calcu- 
lated and  plotted  on  a  diagram.  Such  a  "  weight  "  curve  is 
best  plotted  as  the  summation  of  the  weight  curves  for  all  the 
different  elements  which  make  up  the  total  weight  ;  tor  example, 
hull,  machinery,  fittings,  etc.  Similarly  the  distribution  of 
support  can  be  plotted.  The  support  at  any  point  along  the 
length  of  the  ship  is  measured  by  the  immersed  cross-sectional 
area  of  the  ship  at  the  point.  If  the  curves  of  weight  and 
support  are  plotted  on  the  same  base-line  and  to  the  same  scale, 
there  will  be  at  practically  every  point  along  the  base-line  two 
ordinates,  one  representing  weight  and  one  representing  sup- 
port. The  difference  between  the  two  ordinates  at  any  point  is 
the  difference  between  weight  and  support,  and  represents 
the  unbalanced  force,  or  "  load,"  acting  at  the  point.  If  the 
differences  between  weight  and  support  are  plotted  with 
reference  to  a  straight  base-line  the  result  is  called  a  "  curve 
of  loads."  At  some  points  weight  is  in  excess  of  support,  and 
at  others  the  reverse  is  the  case  ;  accordingly  at  some  points 
the  "  load  "  is  downwards,  at  others  it  is  upwards.  Curves  of 
weight,  support,  and  loads  are  shown  on  pp.  205  and  206  of  the 
Appendix. 

Graphic  integration  of  the  curve  of  loads — in  other  words, 
graphic  integration  of  the  vertical  forces  acting  on  the  structure 
of  a  ship — gives  as  its  result  the  curve  of  shearing  for  the  structure 
11 


162       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

of  the  ship.  And  graphic  integration  of  a  curve  of  shearing 
force  gives  the  associated  curve  of  bending  moment. 

Curves  of  shearing  force  and  bending  moment  for  the  Askelad 
in  the  "  hogging  "  and  "  sagging  "  conditions  are  given  on  pp.  205 
and  206  of  the  Appendix.  The  maximum  values  of  the  bending 
moment  are,  respectively,  2,060  foot-tons  and  6,600  foot-tons. 
The  bending  moment  acting  on  a  ship  is,  of  course,  a  function 
of  displacement,  of  weight,  and  length  ;  and  it  is  often  expressed 

B.M.  =  4*± 
0 

where        A  =  displacement, 
L  =  length,    . 
C  =  a  coefficient  between  about    25    and    35  for 

ordinary  steel  merchant  ships  with  engines 

amidships. 

For  the  Askelad  the  bending  moments  as  calculated  were  found 

to  correspond  respectively  to  — -  —  and  — -  — .     Similar  cal- 

143  49 

culations  in  the  case  of  the  Namsenfjord  gave,  for  a  displacement 
of  340  tons,  bending  moments  of  140  foot-tons  and  715  foot-tons 
for  the  "hogging"  and  "sagging"  conditions  respectively; 

these  correspond  to  —  and  — — —  -  respectively. 

But  the  bending  moments  found  from  actual  calculations 
were  not  used  for  the  determination  of  the  amount  of  steel  in  the 
cross-section  of  the  Askelad.  This  was  due  to  the  fact  that  for 
a  ship  whose  design  was  prepared  previous  to  that  of  the  Askelad 
the  Norwegian  Veritas  had  suggested  as  the  standard  of  longi- 
tudinal strength  the  strength  of  a  steel  ship  of  equal  dimensions, 
assuming  a  working  stress  on  the  material  of  13  tons  per 

A      y     T 

square  inch  ;    but  a  bending  moment  expressed  by  J  was 

\.2i 

given  as  an  absolute  maximum.  In  the  case  of  the  Askelad  the 
maximum  bending  moment  referred  to  by  Norwegian  Veritas 
was  taken  as  the  standard  bending  moment  for  which  pro- 
vision had  to  be  made  ;  this  bending  moment  amounted  to 

1735  X  17°  .  24,570  foot-tons. 
12 

The  stress  calculations  for  the  midship  section  are  given  on 


CONDITIONS    GOVERNING    STRUCTURAL   DESIGN     163 

p.  204  of  the  Appendix  ;  and  it  is  shown  that  the  chosen  standard 
bending  moment  could  be  resisted  with  the  steel  stressed  to 
12-5  tons  per  square  inch,  that  is,  with  the  steel  working  at  a 
lower  stress  than  would  have  been  permitted  by  the  Norwegian 
Veritas. 

The  calculations  for  moments  of  inertia  of  cross-section  of 
ships  are  made  "  on  a  steel  basis  "  ;  in  other  words,  the  sectional 
areas  of  concrete-resisting  compression  are  expressed  in  equivalent 
areas  of  steel.  For  example,  consider  Item  1  in  the  calculations 
(p.  204  of  Appendix).  From  the  sketch  at  the  left  of  the  calcu- 
lations it  is  seen  that  Item  1  is  the  top  of  the  hatch  coaming. 
In  the  "  hogging  "  condition  the  material  at  the  top  of  the  hatch 
coaming  is  in  tension  ;  hence  in  the  calculation  for  "  hogging  " 
Item  1  is  represented  by  12  square  inches,  the  area  of  the  rein- 
forcement at  the  top  of  the  hatch  coaming.  In  the  "  sagging  " 
condition  the  material  at  the  top  of  the  hatch  coaming  is  in 
compression  ;  hence  in  this  case  the  concrete  must  also  be  taken 
into  account,  not  the  steel  alone.  The  area  of  the  steel  is  12 
square  inches.  The  gross  area  of  concrete  is  108  square  inches  ; 
hence  the  net  area  of  concrete  is  96  square  inches.  The  ratio 

modulus  of  elasticity  of  steel 
modulus  of  elasticity  of  concrete 

was  taken  to  be  15  ;  in  other  words,  for  a  given  strain  the 
stress  on  the  steel  was  taken  to  be  15  times  the  stress  on 
the  adjoining  concrete,  or  the  load  borne  by  the  steel  was 
15  times  the  load  borne  by  an  equal  area  of  concrete  at  the 
same  place.  On  this  basis  the  96  square  inches  of  concrete  is 
equivalent  to  6-4  square  inches  of  steel.  And  so  for  Item  1 
in  the  "  sagging  "  calculations  the  effective  area  is  6-4  square 
inches  for  the  concrete  expressed  in  its  equivalent  area  of  steel 
plus  12  square  inches  for  the  actual  steel,  making  18-4  square 
inches  in  all.  Items  1-4  in  the  "  sagging  "  calculations  and 
Items  5-9  in  the  "  hogging"  calculations  are  treated  in  this  way, 
the  net  areas  of  concrete  being  converted  to  equivalent  areas  of 
steel,  and  these  equivalent  areas  added  to  the  actual  areas  of 
steel. 

Strength  of  Shell  Slab. — In  designing  the  Askelad  the  rein- 
forcement in  the  bottom  slab  was  made  adequate  to  carry  the 
water- pressure  due  to  a  draught  of  15'  3"  when  stressed  to 


164       SEAGOING  AND   OTHER  CONCRETE   SHIPS 

5,400  Ib.  per  square  inch.  But  it  must  be  borne  in  mind  that 
there  is  a  tension  stress  in  the  reinforcement  in  the  bottom 
slabs  when  the  ship  is  "  sagging  "  ;  and  the  tension  stress  due  to 
"  sagging  "  must  be  added  to  the  tension  stress  due  to  water- 
pressure.  Hence  the  reason  for  the  low  working  stress  on  the 
bottom  reinforcement  when  considered  from  the  point  of  view 
of  water-pressure  only. 

The  reinforcement  in  the  side  slabs  was  provided  on  a  similar 
basis  to  that  in  the  bottom  slabs,  but  the  working  stress  on  the 
steel  was  increased  to  6,500  Ib.  per  square  inch.  The  increased 
working  stress  is  consistent  with  the  fact  that  the  stresses  due 
to  "  sagging  "  are  not  so  severe  in  sides  as  in  bottom. 

Watertight  Bulkheads.  — When  designing  the  Askelad  the 
peak  bulkheads  were  made  capable  of  withstanding  a  pressure 
due  to  a  "  head  "  of  water  to  the  load  line  at  working  stresses 
of  15,000  Ib.  per  square  inch  for  steel  and  800  Ib.  per  square 
inch  for  concrete  ;  for  the  other  bulkheads  the  same  "  head  "  of 
water  was  adopted,  but  the  working  stresses  were  increased  to 
29,000  Ib.  per  square  inch  and  1,600  Ib.  per  square  inch  respec- 
tively. In  designing  a  bulkhead  provision  must  be  made  against 
the  possibility  of  water-pressure  on  either  side.  Hence  there 
must  be  reinforcement  near  both  surfaces. 

Deck  Beams,  etc. — In  designing  the  deck  beams  the  method 
of  comparison  with  the  requirements  for  a  steel  ship  was  adopted  ; 
the  actual  calculations  were  made  in  exactly  the  manner  outlined 
above  for  the  side  frames.  When  designing  the  hatch  coamings 
it  was  assumed  that  the  load  from  the  deck  and  from  the  hatch 
covers  amounted  to  168  Ib.  per  square  foot.  In  the  case  of  the 
Namsenfjord  the  deck  beams  and  slabs  were  designed  to  with- 
stand a  loading  of  250  Ib.  per  square  foot. 

Norwegian  Government  Requirements.  — In  May  1916  the 
author's  firm  received  an  order  from  the  Sydvaranger  Mining 
Company  for  an  ore-carrying  ship  of  2,700  tons  deadweight 
capacity.  In  view  of  the  fact  that  the  author's  firm  had  only 
begun  the  construction  of  concrete  lighters  the  action  of  the 
Mining  Company  indicated  their  great  faith  in  the  new  method 
of  construction.  The  ship  was  not  completed,  various  causes 
having  led  to  the  suspension  of  the  contract.  But  in  virtue  of 
the  discussions  which  the  design  of  the  ship  called  for  with  the 
Director  of  Shipping,  with  the  Technical  Committee  appointed 


CONDITIONS    GOVERNING   STRUCTURAL    DESIGN     165 

by  the  Department  of  Shipping,  and  with  the  Norwegian  Veritas, 
the  design  contributed  appreciably  to  the  progress  of  concrete 
shipbuilding  in  Norway. 

The  preliminary  requirements  of  the  Technical  Committee 
were,  briefly  : 

The  strength  of  any  proposed  concrete  ship  must  be  calcu- 
lated relatively  to  that  of  a  steel  ship  of  the  same  dimensions. 
Calculations  of  strength  must  be  submitted  for  approval, 
together  with  detailed  plans  of  the  concrete  ship  and  of  the 
equivalent  steel  ship,  the  latter  having  been  submitted  to,  and 
approved  by,  the  Norwegian  Veritas  ;  the  calculations  of  strength 
for  the  steel  ship  must  also  be  submitted. 

It  may  be  assumed  that  a  steel  ship  can  stand  a  stress  of 
13  tons  per  square  inch  without  change  of  shape,  and  from  this 
assumption  the  bending  moments,  etc.,  on  the  elements  of  the 
structure  can  be  determined.  For  the  concrete  ship  the  appli- 
cations of  the  bending  moments,  etc.,  so  determined  must  not 
cause  tensile  stresses  beyond  the  elastic  limit  of  the  steel,  nor 
compressive  stresses  greater  than  55  per  cent,  of  the  crushing 
strength  of  the  concrete. 

The  bending  moments  at  amidships  as  determined  in  the 
manner  outlined  above  are  to  be  assumed  constant  over  40  per 
cent,  of  the  length  amidships,  and  are  then  to  be  uniformly 
reduced  to  zero  at  the  ends.  But  a  bending  moment  amounting 

A  x  L 

to  -  — - —  may  be  taken  to  be  the  maximum   possible    value, 
\.2i 

even  if  calculations  made  for  a  steel  ship  show  a  higher  value. 

The  shear  strength  of  elements  of  the  structure  of  a  concrete 
ship  must  be  equal  to  the  shear  strength  of  the  corresponding 
elements  of  the  structure  of  a  steel  ship.  For  example,  the 
shear  strength  of  the  shell  slabs  must  be  equal  to  the  shear 
strength  of  the  single  or  double-riveted  edge  landings  of  the 
equivalent  steel  ship.  Similarly  the  shear  strength  of  the 
joint  between  frame  and  shell  slab  must  be  equal  to  the  shear 
strength  of  the  rivets  joining  frame  and  shell  plating  in  a  steel 
ship,  allowance  being  made  for  the  larger  frame  spacing  in  the 
concrete  ship. 

The  maximum  bending  moments  found  for  frames  and  beams, 
etc.,  must  be  assumed  to  act  at  any  point  in  the  frame,  beam, 
etc  ,  and  in  either  direction. 


166       SEAGOING   AND    OTHER   CONCRETE   SHIPS 

There  were  requirements  also  in  regard  to  quality  of  steel 
and  cement  and  tests  of  concrete  ;  but  these  are  not  of  importance 
in  the  present  consideration.  The  requirements  correspond  in 
principle  to  the  author's  methods  of  calculating  seagoing  concrete 
ships  as  submitted  to  the  Director  of  Shipping  the  previous  year. 

Dsflection  Test  on  Lighter. — During  the  summer  of  1917  the 
author  decided  to  carry  out  a  deflection  test  on  a  concrete  lighter. 
The  experiment  was  made  just  about  a  fortnight  before  the 
Namsenfjord  was  launched,  and  was  carried  out  on  one  of  the 
standard  100-ton  lighters  built  by  the  author's  firm.  The 
lighter  was  practically  ready  for  launching  ;  the  concrete  in  the 
sides  was  30  days  old,  and  that  in  the  deck  50  days  old.  Over 
12  feet  of  the  length  from  each  end  the  lighter  was  carried  on 
supports  and  on  the  launching  cradle  ;  over  these  lengths  the 
hull  was  so  wedged  up  that  the  weight  was  practically  uniformly 
distributed.  Over  the  40  feet  of  length  between  the  supports 
the  launching  cradle  was  lowered  about  5  to  6  inches,  so  that 
it  would  be  quite  clear  of  the  hull. 

A  load  of  15  tons,  in  the  form  of  gravel  in  bags,  was  placed 
on  top  of  the  hatch,  and  a  further  ton,  made  up  by  13  men, 
was  also  placed  on  the  hatch.  Fig,  45  shows  the  lighter  under 
test. 

The  weight  of  the  lighter  was  about  58  tons,  and  it  was 
assumed  to  be  distributed  uniformly  along  the  length.  The 
additional  load  of  16  tons  was  assumed  to  be  distributed  uniformly 
over  the  40  feet  of  length  between  the  supports.  And  the 
support  was  assumed  to  be  uniformly  distributed  over  the  12  feet 
of  length  at  each  end.  On  these  assumptions,  which  are  obviously 
reasonable,  the  curves  of  shearing  force  and  bending  moment  in 
Fig.  46  were  determined. 

The  maximum  bending  moment  was  found  to  be  419  foot- 
tons.  Since  the  loaded  displacement  of  the  lighter  was  162  tons, 

this  bending  moment  corresponds  to  ,  which  is  not  less 

&G 

than  the  amount  to  be  expected  on  actual  service. 

The  deflection  of  the  hull  between  the  points  of  support  was 
very  carefully  measured,  and  was  found  to  amount  to  about 
1-5  mm. 

The  hull  was  inspected  by  a  representative  from  the  Depart- 
ment of  Shipping  and  by  a  surveyor  from  Norwegian  Veritas, 


I 


167 


168       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

TOTAL     DISPLACEMENT  (p)     ON     6'-O"    DRAFT  =   162.  TONS. 
LENGTH      B.P.      (L)    64.'-o" 

D  *  I-   =    IO36S     FOOTPOUNDS. 


16  TONS   LOAD    ON    4O1 


—  * 

58  TONS  OWN    WEIGHT    ON    64-' 


40'-0"- 


16  TONS 


f-~2 40*0,4=  I6TOI 


SUPPORT 


CURVE  OF   BENDING 
MOMENTS 

FIG.  46. — Deflection  Test  on  100- ton  Lighter,  Curves  of  Shearing  Force  and 

Bending  Moment. 

and  the  two  inspectors  gave  a  joint  certificate  to  the  effect  that 
the  lighter  showed  no  signs  of  weakness,  nor  even  any  sign  of 
cracks  in  the  cement  finish  on  the  shell. 


CHAPTER    XII 
GENERAL    METHOD    OF    CONSTRUCTION 

Preliminary  Work — Bottom  Floor  Prepared — Outside  Centring  Completed — 
Bottom  and  Side  Reinforcement  in  Place — Frame  Centring  and  Reinforcement 
in  Place — Deck  Centring  in  Place — Centring  and  Reinforcement  Completed — 
Concreting — Concreting  Finished — Cement  Finish — Cement-Gun  Concreting. 

THE  procedure  in  the  construction  of  the  ships  built  by  the 
author's  firm  was  as  described  in  the  following  paragraphs  ;  for 
all  ships  in  which  the  concrete  is  poured  in  situ  the  procedure 
is  similar. 

Preliminary  Work. — A  bottom  floor  was  prepared,  of  1J  inch 
tongued  and  grooved  boards  in  sheets  2'  6"  X  8'  0"  supported 
by  beams  6"  X  7"  spaced  18"  apart.  See  Fig.  47,  diagram  (a). 
Holes  about  12  inches  square  were  arranged  at  intervals  along 
the  centre  line  for  drainage  and  cleaning  purposes.  The  height 
of  the  platform  (indicated  by  a  in  Fig.  47)  was  made  sufficient 
to  permit  of  the  launching  ways  being  fitted.  See  Fig.  47, 
diagram  (6). 

The  mould  loft  floor  was  laid  down,  its  size  being  sufficient 
to  permit  of  the  half -sections  of  the  ship,  as  on  a  body  plan, 
being  drawn  full  size.  The  floor  was  of  f  inch  boards,  on 
stringers  24"  apart.  On  this  floor  the  frame  lines  were  drawn 
in,  or  carved  in,  with  a  knife. 

Templates,  of  2"  x  5"  planks,  were  made  in  accordance  with 
frame  lines  on  the  mould  loft  floor.  The  frame  lines  were  drawn 
actually  to  the  outside  of  the  shell.  Hence  the  centring  fitted 
inside  the  template  in  effect  reduced  the  size  of  the  ship  ;  but 
the  exterior  mortar  finish  was  the  thickness  of  the  centring 
boards  and  so  compensated  for  the  reduction  due  to  the  centring 
boards.  The  bottom  reinforcement  was  cut  and  bent,  rods 
above  J  inch  diameter  having  hooks  made  on  the  ends.  Stirrups 
for  keelsons,  frames,  etc.,  were  made. 

Bottom    Floor    Prepared. — The    outside   forms    were    erected, 

169 


//  T.SfG.  BOARDS 


(CL) 


6"x7 


-14^14 


(b) 


I8"O.C. 


Fia.   47. — Bottom  Floor  and  Launching  Ways. 
170 


GENERAL   METHOD   OF   CONSTRUCTION         171 

templates  made  from  the  mould  loft  floor  being  placed  every 
24  inches,  and  centring  of  }  inch  rough  boards  fitted  inside  the 
templates,  beginning  above  point  a  in  Fig.  48,  and  continuing 
upwards  and  inwards.  The  stem  and  stern  posts  were  erected 
and  thoroughly  braced  ;  these  formed  terminations  for  the 


FIG.   48.— Outside  Centring. 

centring.  Special  care  was  taken  that  the  stern  tube  was  lined 
up  correctly. 

The  exterior  reinforcement  in  frames  and  keelsons  was  bent 
according  to  the  lines  on  the  mould  loft  floor. 

Outside  Centring  Completed.  — Bottom  slab  reinforcement, 
lower  steel  in  keelsons  and  bottom  frames,  reinforcement  in 
sides  (slabs)  and  interior  steel  in  side  frames  was  placed.  Stirrups 
in  side  and  bottom  frames  and  keelsons  were  placed. 


172       SEAGOING   AND   OTHER   CONCRETE   SHIPS 

Forms  for  bottom  frames,  keelsons,  side  frames,  stringers, 
and  stanchions  were  prepared. 

Bottom  and  Side  Reinforcement  in  Place. — Bottom  centring 
(boxes)  were  placed  and  well  braced.  Side  forms  were  placed 
and  braced,  partly  from  the  bolts  embedded  for  nailing  strips 
for  the  inner  ceiling. 

Forms  for  stiffener  beams  and  one  side  of  slab  centring  for 
bulkheads  were  placed. 

Top  reinforcement  in  bottom  frames  and  keelsons  was  placed, 
and  the  stirrups  already  in  place  straightened  up  and  bent  over 
the  top  bars.  Steel  was  erected  in  the  stanchions  and  the  stiffener 
beams  in  the  bulkheads. 

Frame  Centring  and  Reinforcement  in  Place. — Reinforcement 
in  bulkhead  slabs,  in  deck,  hatch  coamings,  and  deckhouses  was 
cut  arid  bent. 

The  centring  for  the  deck  beams  was  erected  and  connected 
to  that  of  the  side  frames  and  the  deck  slab. 

Deck  Centring  in  Place. — The  steel  was  placed  in  deck  beams 
and  longitudinals,  a  few  J  inch  diameter  rods  4  inches  long  being 
placed  under  the  reinforcement  to  keep  it  clear  of  the  forms. 
The  steel  was  placed  in  the  deck  slabs,  hatch  coamings,  fore- 
castle deck,  and  bulwark  stiffeners. 

The  deck  beams,  longitudinals,  and  stanchions  were  braced 
and  supported  by  4"  X  4"  or  5"  diameter  posts,  well  braced  to 
each  other.  The  lower  15  inches  of  the  inside  slab  centring 
boards  were  placed  in  position  in  the  recesses  behind  the  cleats 
indicated  in  Fig.  49,  diagram  (a).  The  forms  for  coamings  were 
erected  (c)  and  the  anchor  bolts  for  deck  fittings  placed  in  position. 

Centring  and  Reinforcement  Completed.  — The  ship  was 
thoroughly  cleaned  inside  by  means  of  hoses,  so  that  all  dust, 
shavings,  scales,  etc.,  were  removed.  When  the  cleaning  was 
finished  and  inspected,  the  openings  left  in  the  bottom  centring 
were  closed. 

Concreting. — One  Smith  mixer,  capacity  20  cubic  yards  per 
hour,  was  sufficient  for  concreting  a  ship  of  the  1,000-ton  type  ; 
in  case  of  a  break-down  another  machine  was  always  available. 
The  concrete  was  transported  in  large  buckets  on  overhead 
rails  attached  to  the  roof  trusses  of  the  shed  covering  the  ways  ; 
and  sheet-iron  channels  about  2  feet  long,  of  tapering  shape, 
were  used  for  filling  the  frames  and  slabs. 


^^ 

0. 

0 

=  1- 

b 

__jj_ 

a 

z 

173 


174       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

Small  concrete  spades,  tampers  of  hardwood  6"  x  6"  x  2J" 
with  handles,  and  short  f  inch  steel  rods  were  used  for  tamping 
the  concrete. 

Concrete  carefully  inspected  and  made  according  to  specifi- 
cation was  filled  in  seven  or  eight  panels  of  the  bottom  slab, 
beginning  aft  ;  a  fairly  stiff  mixture  was  used,  which  was  thor- 
oughly rammed.  Then  the  bottom  frames,  keelsons,  and  bilges 
were  filled  about  half-way  up  with  a  fairly  soft  mixture.  After 
that  an  additional  seven  or  eight  panels  of  the  bottom  slab 
were  concreted  as  before,  working  forward.  Then,  going  back, 
the  bottom  frames,  etc.,  were  filled  up  to  the  top.  Next  the 
frames,  keelsons,  etc.,  adjoining  the  second  set  of  bottom  panels 
were  half  filled  ;  then  the  succeeding  panels  of  the  bottom  slab 
were  concreted,  and  so  on  until  the  stem  was  reached.  When 
the  bottom  was  completed,  the  concreting  of  the  side  slabs  and 
frames  was  started,  beginning  aft,  with  two  gangs,  one  on  each 
side.  A  layer  about  15  inches  deep  was  poured  all  round,  and 
the  boards  of  the  inside  centring  placed  in  position  for  the  next 
layer.  The  four  or  five  panels  furthest  aft  were  poured  one 
round  ahead  of  the  others  ;  the  concrete  was  thus  prevented 
from  running  downwards  (aft)  and  remained  where  it  was  placed. 
The  concreting  of  the  deck  beams  and  slabs  was  carried  out  in 
the  same  manner  as  the  floors  in  a  building  ;  the  surface  was 
left  rough  for  the  subsequent  finish,  and  was  covered  with  sacks 
or  sawdust  and  sprayed  regularly  with  water  for  four  or  five  days. 

Concreting  Finished.  —  The  exterior  side  centring  was  first 
removed  and  scaffolding  erected  around  the  ship.  When  the 
concrete  had  sufficiently  hardened  the  bottom  forms  were 
removed  in  sections,  not  more  than  30  feet  long,  corresponding 
to  the  length  of  one  log  of  the  centre  launching  way.  All  concrete 
was  then  carefully  inspected,  if  necessary  with  a  hammer  and 
chisel. 

The  outside  cement  mortar  finish  was  then  applied  ;  this 
finish  is  described  below.  The  bottom  was  finished  in  sections, 
as  the  outside  forms  were  removed. 

When  each  section  of  bottom  finish  was  completed,  the 
centre  launching  way  with  "sleigh"  timbers  —  see  Fig.  47, 
diagram  (&) — was  shifted  into  position.  When  the  centre  way 
was  in  position  the  two  sideways  were  blocked  up  in  place  ;  the 
three  launching  ways  were  greased  with  tallow  and  soft  soap. 


GENERAL  METHOD   OF  CONSTRUCTION  175 

To  start  the  ship  when  launching,  a  100-ton  hydraulic  jack  was 
placed  against  the  stem,  after  the  last  retaining  braces  had  been 
removed  ;  heavy  pulleys,  fixed  in  the  launching  "  sleigh  "  timbers 
and  the  concrete  foundations,  with  leads  to  an  electric  winch, 
could  also  be  used  if  needed.  With  a  slope  of  J  inch  to  the 
foot  no  difficulty  was  found  in  getting  the  ships  off. 

After  launching,  the  engines,  deckhouses,  equipment,  etc., 
were  installed,  and  this  work  was  very  similar  to  that  in  steel 
ships.  The  propeller  and  shaft  were  placed  in  the  stern  tube 
before  launching. 

The  most  economical  complement  of  workmen  for  each  ship 
of  the  1,000-ton  type  was  found  to  be  about 

10  to  12  men  placing  steel, 

12  to  15  carpenters  making  forms, 

20  to  25  men  (skilled  and  unskilled)  for  concreting. 

The  concreting  was  generally  accomplished  inside  of  two 
weeks,  working  16  hours  per  day  in  two  shifts  of  8  hours  each. 
For  the  outside  cement  finish,  3  expert  masons  with  helpers 
were  required  besides  the  attendants  at  the  mixer. 

Cement  Finish. — Doubts  have  been  expressed  as  to  the  advisa- 
bility of  plastering  outside  finish  on  concrete  ships.  It  was 
feared  that  the  outside  finish  would  drop  off  ;  and  it  has  been 
considered  safer  to  depend  on  the  monolithic  concrete  surface, 
presumably  moulded  in  extra  well  made  forms  of  planed  boards. 
But  two  objections  should  be  raised  against  these  doubts.  In 
the  first  place,  the  finish,  when  carried  out  strictly  in  accordance 
with  the  following  specification,  will  not  come  off,  but  will  stay 
on  indefinitely  ;  and  it  will  thoroughly  waterproof  and  protect 
the  steel  and  concrete.  In  the  second  place,  the  natural  surface 
of  poured  concrete  is  never  entirely  free  from  slight  irregularities, 
especially  cavities  due  to  air  bubbles  and  water  not  chemically 
bound  ;  and  these  will  appear  even  when  steel  forms  are  used 
and  the  utmost  care  is  taken  in  mixing  and  placing  the  concrete. 
On  land  structures  these  irregularities  and  cavities  do  not  matter, 
but  on  ships,  in  salt  water  particularly,  they  do  matter  ;  the  skin 
friction  is  largely  increased,  the  concrete  may  be  affected  by 
salt  water  penetrating  through  these  porous  "  blow-holes,"  and 
there  may  even  be  corrosion  of  the  reinforcement.  To  some 
extent  these  troubles  can  be  avoided  by  painting  the  surface 


176       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

with   a   plastic   composition  ;    but   the   rational,  lasting  method 
is  to  use  cement  mortar  finish. 

Materials. — First-class  Portland  Cement  and  clean,  well- 
graded  sand  up  to  No.  10  size  (passing  a  screen  with  10  meshes 
per  linear  inch)  ;  proportions  1  :  2J.  The  cement  and  sand 
were  very  thoroughly  mixed  in  a  machine  mixer  with  fresh 
water  to  consistencies  as  described  below  ;  hand-mixing  is  not 
satisfactory. 

The  surfaces  to  be  finished  were  made  scrupulously  clean, 
free  from  dust,  and  should  preferably  be  rather  rough,  as  from 
undressed  boards  with  plain  edges.  On  the  afternoon  before 
the  cement  finishing  was  started  the  surfaces  to  be  treated  were 
well  wetted  by  spraying  with  a  hose. 

The  surfaces  were  splashed  with  plain  water,  or  water  mixed 
with  a  special  waterproofing  compound,  by  means  of  an  ordinary 
large  paint-brush.  While  the  surfaces  were  moist  the  first  layer 
of  thin  mortar  was  thrown  forcibly  on  by  the  trowel ;  this  layer 
was  made  as  thin  as  possible,  since  it  acted  as  a  binder  for  the 
next  coat. 

The  second  layer  of  rather  stiff  mortar  (the  same  proportions 
otherwise)  was  first  thrown  on  by  steel  trowel  and  afterwards 
evened  off  and  pressed  together  with  a  wood  float  (or  trowel). 
It  was  applied  about  J  inch  thicker  than  the  completed  finish 
was  to  be,  and  was  placed  before  the  first  layer  had  set.  Before 
the  mortar  had  set  hard  the  surface  was  gauged  or  screeded  to 
the  ship's  true  form  with  a  board  template  and  the  trowel.  This 
coat  was  made  regular,  but  not  smooth  in  the  surface. 

The  third  layer,  about  J  inch  thick,  consisted  of  mortar  pro- 
portioned 1  :  2J  as  before,  but  made  with  finer  sand,  up  to,  say, 
TV  inch  size.  It  formed  the  "  backing  "  of  the  surface  finish, 
and  was  thrown  on  with  the  trowel  and  hand-floated  in  the 
usual  manner,  but  care  was  taken  that  only  limited  areas  were 
plastered  at  one  time,  because  the  following  surface  coat  had  to 
be  placed  before  the  "  backing  "  was  dry. 

The  fourth,  and  last,  layer  was  applied  while  the  third  was 
still  moist.  In  general  three  or  four  men  started  throwing  on 
the  mortar.  When  about  2,000  square  feet  had  been  covered 
one  of  the  men  commenced  hand-floating ;  and  when  the 
floated  part  began  to  dry,  another  man  followed  with  the 
surface  finish. 


GENERAL  METHOD    OF   CONSTRUCTION         177 

The  surface  finish  may  be  carried  out  by  two  different 
methods  : 

(a)  Brush  Finish. — Mortar  of  mixture  1  :  1-5,  with  fine  sand, 
is  plastered  on  in  a  very  thin  layer,  either  with  a  steel  trowel 
or  a  steel  float  and  worked  into  the  "  backing."     The  surface  is 
then  brushed  with  a  fine  hair- brush  about  3  inches  in  diameter, 
with  hairs  2J  to  3  inches  long.     If  necessary  the  brush  may  be 
slightly  moistened  with  clean  water. 

(b)  /Smooth  or  Polished  Finish. — A  thin  mortar,   of  mixture 
1:0-5  (fine  sand),  of  a  consistency  like  thick  soup,    is   plastered 
on  with  a  steel  float  and  pressed  or  worked  into  the  backing 
until  the  surface  appears  hard  and  polished.     In  order  to  secure 
this  more  rapidly,  it  is  customary  to  throw  some  dry  cement  on 
by  hand  during  the  trowelling,  and  no  ill  effects  from  this  practice 
have  been  observed  in  the  outside  finish  of  ships. 

Notes. — The  polished  finish  gives  the  smoothest  surface,  but 
is  more  expensive  in  materials  and  labour.  It  is  also  more  apt 
to  develop  hair- cracks. 

The  mortar  must  be  used  right  away  when  it  is  mixed.  If 
it  stands  more  than  1  to  1|  hours  it  will  not  adhere  to  curved 
or  overhanging  surfaces. 

No  layer  of  finish  should  be  placed  without  first  moistening 
and  thoroughly  cleaning  the  surface  on  which  it  is  to  be 
plastered. 

The  Deck  Finish  was  placed  after  all  fittings,  deck  machinery, 
etc.,  had  been  mounted.  It  was  made  f  inch  thick  and 
trowelled  to  a  polished  finish.  It  is  exposed  to  wear,  large 
temperature  changes,  and  injuries  in  the  same  manner  as  a 
floor  finish  on  land,  and  is  therefore  likely  to  need  repairs.  The 
outside  finish  of  the  hull,  on  the  other  hand,  works  under  almost 
ideal  conditions  of  even  temperature,  uniform  pressure  against 
the  concrete,  and  no  wear,  except  from  the  water-friction,  and 
this  shows  no  effect  up  to  date  after  four  years  of  service. 

In  conclusion,  the  author  desires  to  emphasize  that  to  achieve 
a  good  finish  is  difficult  work,  requiring  expert  workmen  who  are 
particularly  skilled  in  such  work.  But  if  carried  out  strictly  as 
described  above,  by  skilled  men  using  good  materials,  the  finish 
will  be  entirely  satisfactory.  After  the  finish  has  hardened  for 
at  least  a  week,  it  should  be  inspected  by  going  over  the  entire 
surface  of  the  ship  with  a  heavy  hammer,  hitting  moderate 
12 


178        SEAGOING  AND   OTHER   CONCRETE   SHIPS 

blows  to  sound  for  possible  crevices  ;  should  any  place  be 
doubtful,  it  must  be  cut  open  with  chisels  and  finished  properly. 
Cement-Gun  Concreting. — The  concrete  oil  carriers  built  for 
the  Standard  Oil  Co.  were  constructed  partly  by  use  of  the 
Cement- Gun.  Wood  forms  were  erected  on  one  side  only, 
against  which  the  concrete  was  "  shot  "  around  the  steel.  Interior 
bulkheads  were  concreted  in  this  manner,  and  also  the  transverse 
frames  of  the  canal  boats,  which  were  shot  on  the  reinforcement 
as  shown  in  Fig.  50.  The  concrete  was  smoothed  off  to  regular 
shape  and  surface  by  hand  trowelling. 

The  cement-gun  was  also  used  in  connexion  with  a  method 
of  oilproofing  concrete.  Since  the  machine  is  comparatively 
unknown  in  most  countries  at  present,  a  brief  description  and 
some  figures  from  its  practical  use  are  of  interest.  The  type 
presently  described  is  a  proprietary  machine  developed  and 
manufactured  by  the  Cement -Gun  Company,  of  Allentown, 
U.S.A.,  who  have  experimented  for  years  on  the  subject.  It  is 
not  a  concrete  mixer,  but  a  tool  for  placing  the  previously 
mixed  concrete  (or  mortar)  in  position. 

Cement  and  fine  aggregate  are  thoroughly  mixed  together 
dry  in  any  practical  way  in  the  proportions  chosen.  It  should 
be  noted  that  a  considerable  portion  of  the  sand  jumps  out  by 
rebound  when  the  concrete  is  shot  against  the  forms,  steel  or 
concrete  surface,  and  so  the  original  mixture  is  materially 
altered  before  being  in  place.  Experience  has  shown  that  a 
mixture  in  the  machine  of  1  part  cement  to  3J  parts  sand  will 
ultimately  yield  1  part  cement  to  2|  parts  sand  in  the  finished 
product.  The  dry  mixture  is  placed  in  a  conical  hopper  on  top, 
and  falls  by  the  release  of  an  airtight  bottom  valve  into  a  cone- 
shaped  chamber.  From  there  it  drops  by  the  release  of  a  bottom 
valve  into  another  chamber,  also  of  conical  shape.  The  double 
conical  chambers  form  airlocks  and  permit  a  continuous  supply 
of  materials  ;  by  alternately  opening  the  upper  and  lower  valves 
the  air  can  be  let  out  of  the  upper  chamber  without  appreciably 
reducing  the  pressure  in  the  lower  chamber.  In  the  lower 
chamber  a  feed  wheel  supplies  the  mixture  (still  dry)  to  a  1 J  inch 
reinforced  rubber  hose  through  an  outlet  provided  with  a  special 
valve.  Compressed  air  is  supplied  from  a  separate  air  compressor. 
The  dry  materials  are  shot  through  the  hose,  and  water  is 
supplied  through  another  hose  which  connects  with  the  first  at 


GENERAL  METHOD   OF  CONSTRUCTION         179 

the  nozzle  and  hydrates  the  materials  as  these  are  being  shot 
out.  The  manufacturers  recommend  the  use  of  an  air-pressure 
of  35  to  45  Ib.  per  square  inch  or  higher,  and  a  water- pressure 
about  20  Ib.  higher  than  the  air-pressure.  The  author's  experi- 
ence indicates  that  pressures  of  18  to  20  Ib.  per  square  inch  for 


FIG.   50. — Shooting  Concrete  in  Place  with  the  Cement-Gun  on  Oil  Carrier 

Socony  201. 


the  smaller  machines  and  28  to  30  Ib.  per  square  inch  for  the 
larger  machines  are  better  ;  the  former  pressures  require  150  to 
175  cubic  feet  of  free  air  per  minute  and  the  latter  250  cubic 
feet  per  minute. 

The  capacity  of  the  smaller  gun  is  about  150  cubic  feet  of 
concrete  per  eight-hour  day  and  of  the  larger  about  200  cubic 
feet,  placed  in  a  layer  about  2  inches  thick.  A  minimum  crew 


180       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

of  three  men  is  needed  to  work  each  gun,  apart  from  the  men 
required  to  work  the  power  plant.  The  machine  is  made  of 
steel,  weighs  1,200  lb.,  and  is  mounted  on  two  wheels  like  a 
cart.  The  maximum  efficient  length  of  hose  was  found  to  be 
about  100  feet. 

The  advantages  of  placing  concrete  with  the  cement-gun 
depend  on  the  type  of  work  and  the  local  labour  conditions. 
Concrete  shot  through  the  gun  is  very  dense  and  hard,  sets 
rapidly,  and  can  be  placed  in  colder  weather  than  ordinary 
concrete.  For  fireproofing  steel  work,  concreting  thin  walls, 
and  repairing  or  placing  concrete  linings  in  shafts,  tunnels,  etc., 
where  a  smooth  finish  is  not  required,  the  machine  is  very  useful, 
but  in  its  present  development  the  method  has  several  drawbacks 
in  concrete  shipbuilding.  The  rebound  of  sand  is  serious,  as  it 
may  cause  sand  pockets  around  the  reinforcement  and  uneven 
quality  of  the  concrete  in  corners  where  straight  shooting  is 
difficult.  Fine  sand  is  uneconomical,  as  the  rebound  with  its 
use  is  excessive.  Coarse  sand  is  much  preferable  not  only  from 
the  standpoint  of  economy,  but  on  account  of  the  better  quality 
of  the  concrete.  The  machines  are  at  present  complicated  and 
require  experts  to  operate  both  the  nozzle  and  the  filling.  Some 
parts,  especially  the  rubber  lining  of  the  nozzle,  wear  out  rapidly 
and  must  be  frequently  replaced.  In  cold  weather  moisture  in 
the  air- lines  freezes  at  the  joints  and  bends,  causing  trouble. 

For  straight  work  easily  accessible,  such  as  floor  slabs,  it  is 
doubtful  whether  any  saving  can  be  made  in  time  or  cost  by 
using  the  cement-gun  ;  but  the  method  undoubtedly  contains 
great  possibilities  and  will  probably  be  perfected  and  simplified. 


CHAPTER    XIII 

SOME     SPECIAL    METHODS     OF    CONSTRUCTION    AND 
PARTICULAR    SHIPS 

M.S.  R.  P.  Durham — M.S.  Linnea — "  Pre-Cast  "  Systems — S.S.  Armistice — 
S.S.  Bartds — Present  Tonnage  of  Concrete  Ships — Author's  Recommendations. 

THE  feverish  activity  of  shipbuilding  displayed  in  all  shipping 
countries  during  the  war  naturally  brought  forth  a  large  number 
of  suggestions  and  schemes  of  construction.  This  was  particu- 
larly noticeable  in  concrete  shipbuilding,  after  it  was  proved 
that  seagoing  ships  of  this  material  were  a  practical  proposition. 
Space  does  not  permit  the  detailed  consideration  or  even  the 
enumeration  of  all  the  propositions  which  appeared  in  the  press, 
as  patent  applications  or  mere  suggestions  to  concrete  ship- 
builders. If  the  originators  of  these  schemes  had  stated  the  plain 
truth,  that  their  ideas  had  not  yet  been  tried  out,  or  if  they  had 
refrained  from  writing  until  they  had  reliable  data  to  put  forward, 
much  confusion  would  have  been  avoided  and  many  exaggerated 
or  entirely  unfounded  statements  would  never  have  appeared. 
Unfortunately  for  the  development  of  concrete  ships  the  authors 
of  the  proposals  rarely  disclosed  that  they  possessed  no  actual 
experience  ;  yet  they  did  not  hesitate  to  publish  in  leading 
technical  journals  on  both  sides  of  the  Atlantic  all  sorts  of  fic- 
titious data  purporting  to  be  facts  ascertained  from  personal 
experience. 

But  some  special  methods  of  construction  were  actually  tried 
out,  and  a  few  examples  are  described  below. 

M.S.  "R.  P.  Durham." — The  Engineering  News-Record,  1920, 
p.  388,  describes  the  construction  of  a  2,000-tons  oil-tanker  of 
concrete,  which  was  built  in  sections  on  end.  The  dimensions 
of  the  ship,  which  was  named  R.  P.  Durham,  are  298'  X  33'  9"  X 
21'  10",  and  the  capacity  was  estimated  at  14,000  barrels  of 
medium  oil.  The  design  and  method  of  construction  are  unusual. 
The  cross-section  of  the  ship  consists  of  two  complete  circular 

181 


182       SEAGOING  AND    OTHER   CONCRETE   SHIPS 

frames  of  21  feet  in  diameter,  with  their  centres  13  feet  apart. 
A  central  chamber  6  feet  wide  inside  is  formed  by  the  circular 
sections  cutting  each  other.  This  is  used  for  a  passage-way, 
and  for  piping,  etc.  ;  and  bulk  oil  is  carried  in  the  remaining 
space  in  the  two  cylindrical  holds,  divided  by  bulkheads  every 
30  feet.  No  transverse  or  longitudinal  frames  are  used,  but 
the  shell  is  extra  heavy,  7  inches  at  the  top  and  10  inches  near 
the  bottom.  The  total  length  of  the  ship  is  made  up  of  seven 
intermediate  sections  (length  30  feet)  and  the  bow  and  stern 
portions,  which  were  built  on  ways  in  the  usual  manner.  The 
seven  sections  were  constructed  on  end,  one  at  a  time,  using 
sliding  forms  lifted  by  jacks  as  the  concreting  went  up.  After 
hardening,  each  section  was  moved  on  rollers  to  a  special  crane, 
which  tipped  it  into  horizontal  position,  and  it  was  now  trans- 
ported (on  rollers  by  winch  and  tackle)  to  the  launching  ways, 
where  all  were  spliced  together.  Each  section  had  reinforce- 
ment protruding  about  38  inches  from  each  end,  and  this  was 
overlapped  by  steel  from  the  next  section.  Concreting  of  the 
open  spaces  was  done  by  spraying  the  end  faces  of  each  section 
with  mortar  from  a  cement-gun  and  filling  in  the  gaps  with 
ordinary  concrete  in  forms. 

The  bow  section  is  provided  with  a  forecastle  deck  and 
bulwarks  ;  the  stern  contains  engine-room,  fuel  tanks,  etc.  A 
high  deckhouse  with  bridge  amidships  provides  rooms  for  navi- 
gation and  cabins  for  officers  and  crew.  Two  Bolinder  crude  oil 
motors  of  160  B.H.P.  each  are  installed. 

The  R.  P.  Durham  and  a  sister  ship  were  constructed  at 
Aransas  Pass,  Texas,  for  the  France  and  Canada  Oil  Transport 
Co..  New  York,  by  the  Macdonald  Engineering  Co.  of  Chicago, 
who  proposed  the  scheme.  The  concrete  was  composed  of  1  part 
cement  to  1  part  crushed  coke  up  to  \  inch  size.  It  is  stated  to 
have  shown  a  crushing  strength  of  3,500  to  4,000  Ib.  per  square 
inch  after  60  days  and  to  weigh  110  Ib.  per  cubic  foot  excluding 
reinforcement,  which  is  lighter  than  the  Shipping  Board's  light- 
weight concrete  (120  Ib.  per  cubic  foot).  The  R.  P.  Durham 
was  launched  sidewise  on  24th  July  1920  ;  nothing  is  known 
about  her  subsequent  experience  or  behaviour  in  service.  The 
construction  was  delayed  by  a  tornado  which  flooded  the  ship- 
yard and  destroyed  the  records  of  cost  and  time  of  construction. 
It  is  claimed  that  the  ship  was  built  considerably  cheaper  than 


SPECIAL  METHODS   OF   CONSTRUCTION 


183 


a  steel  tanker  of  the  same  size.  The  ship  seems  very  long  in 
proportion  to  her  beam  and  depth,  but  extra  longitudinal  strength 
is  gained  by  the  internal  walls  of  the  central  compartments. 

The  design  is  unique  and  results  from  actual  service  will  be 
very  interesting.  The  author  believes  that  the  type  will  be 
difficult  to  handle  in  rough  weather,  as  the  seagoing  qualities 
are  those  of  a  submarine  rather  than  of  a  merchant  ship.  It  is 
probable  that  the  construction  would  be  improved  by  the  ship 
being  built  on  ways  in  one  continuous  central  section  ;  sliding 
steel  forms  could  still  be  used,  especially  for  the  interior  centring. 


FIG.   51. — M.S.  Linnea  after  launching. 

M.S.  "  Linnea." — The  first  engine- driven,  concrete  ship 
built  in  Sweden  is  the  M.S.  Linnea,  launched  in  December  1918  at 
the  yard  of  A.  B.  Betonverket,  Malmo.  The  ship  is  owned  by 
A.  B.  Betongelt,  Malmo,  and  the  design  as  well  as  the  method 
of  construction  are  very  unusual.  Briefly,  the  torpedo  shape 
of  hull  is  adopted  with  a  small  forecastle  deck  and  a  deckhouse 
aft  of  the  hatches,  as  seen  in  Fig.  51.  The  length  is  138  feet 
overall,  the  cross-section  is  elliptical  with  maximum  breadth 
and  depth  amidships  about  32  and  22  feet  respectively.  The 
total  displacement  is  1,000  tons  and  the  deadweight  capacity 


184       SEAGOING    AND    OTHER   CONCRETE   SHIPS 

calculated  at  700  tons,  which  seems  high  and  has  not  been  con- 
firmed after  completion.  The  ship  is  built  of  a  combination  of 
reinforced  concrete  and  wood.  Throughout  the  entire  shell 
3"  X  3"  strips  of  lumber  about  4  inches  apart  are  embedded 
permanently  in  the  central  section  of  the  concrete  slab,  which 
is  reinforced  with  steel  rods  near  both  faces  and  has  a  total 
thickness  of  5J  inches. 

The  launching  arrangement  was  also  unique,  since  the  ship 
was  built  on  a  platform  suspended  in  the  air  from  hangers  resting 
on  pile-clusters  on  both  sides.  When  the  concreting  was 
finished,  the  platform  was  lowered  into  the  water  and  the  hull 
floated  off.  In  the  Swedish  engineering  journal  Teknisk  Tidskrift, 
26th  March  1919,  an  article  by  the  builder  describes  the  Linnea, 
which  had  been  launched  three  months  before.  Various  infor- 
mation of  interest  is  lacking,  such  as  the  type  and  size  of  engines, 
exact  weight  and  cubic  space  of  the  hull,  watertightness,  interior 
flooring,  hatches,  etc.,  and  cost  of  construction.  Nor  has  any- 
thing later  been  published  about  actual  experience  with  the 
vessel  in  service,  so  far  as  the  author  is  aware. 

"  Pre-Cast "  Systems. — Several  systems  of  building  concrete 
lighters  from  pre-cast  units  were  tried  in  Great  Britain  during 
the  war.  Such  systems  of  construction  enable  a  saving  to  be 
made  in  the  expenditure  on  centring  ;  but  the  saving  which 
can  be  made  on  this  item  is  not  very  great.  The  cost  of  lumber 
materials  (without  labour)  used  for  centring  in  the  ships  built 
by  the  author's  firm  amounted  to  less  than  ten  per  cent,  of  the 
total  cost  of  the  reinforced  concrete  in  the  hulls.  With  "  pre- 
cast "  systems  the  labour  required  erecting  forms  is  reduced, 
but  the  labour  required  for  handling  and  placing  the  heavy 
pre-cast  units  probably  more  than  makes  up  for  this,  and  would 
for  seagoing  ships  of  fair  size  involve  the  provision  of  cranes  not 
otherwise  necessary  in  concrete  shipbuilding. 

A  lighter  (shown  during  construction  in  Fig.  52)  was  built 
according  to  a  pre-cast  unit  system  patented  by  H.  C.  Ritchie 
and  described  in  a  paper  before  the  Liverpool  Engineering 
Society  reported  in  the  Journal  of  Commerce,  30th  January  1919. 
The  main  features  are  pre-cast  transverse  units  comprising 
portions  of  the  shell  slabs  about  two  feet  long  with  half  of  a 
transverse  frame  at  each  end  of  each  unit ;  each  unit  is  thus 
of  "  channel  "  section.  Abutting  flanges  of  adjacent  units  form 


PRE-CAST   CONSTRUCTION 


185 


frame  members,  which  have  openings  for  longitudinal  and 
diagonal  steel  bars  to  pass  through.  The  frames  are  spliced  at 
the  bilges  and  centre  keelson  by  steel  loops  embedded  in  .each 
pre-cast  section.  The  joints  between  the  flanges  of  the  frame 
units  are  filled  with  mortar  ;  the  deck  slab  is  concreted  in  situ. 


FIG.   52. — Concrete    Lighter    being    constructed    by    Concrete    Seacraft,    Ltd., 
Liverpool,  on  H.   C.   Ritchie's  system  of  pre-cast  units. 

Another  system  on  similar  lines,  but  simpler,  as  it  avoids 
joints  and  splices  of  the  unit  frames,  was  devised  by  Captain 
J.  H.  Waller,  R.E.  The  frames  are  reinforced  and  concreted 
in  place  as  usual.  So  are  also  the  longitudinal  members,  keelsons, 
bilge  girders,  and  gunwale  girders.  The  side  and  bottom  slabs 
are  pre-cast  in  units  reaching  from  gunwale  to  bilge  and  from 
the  bilge  to  centre  keelson.  Side  joints  are  formed  at  successive 


186       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

transverse  frames,  where  reinforcing  rods  projecting  from  all 
sides  of  the  pre-cast  plates  are  hooked  down  around  the  rein- 
forcement in  frames  before  the  latter  are  poured.  A  cross- 
section  in  Fig.  53  shows  the  arrangement.  Forms  were  used 
only  for  the  frame  members.  The  first  ship  built  according  to 
Waller's  system  was  a  barge  187'  6"  x  32'  10"  X  19'  0"  for  the 
British  Government.  An  article  in  the  London  Engineering 
during  1919  describes  the  yard  and  details  of  construction. 


paneled 

where.  _ 

Shear  **« 

Stresses 

permit 


Sectjon  through    Frames         Section  between  Frames 


FIG.   53. — Cross-section  of  Barge  built  for  the  British  Government  to  the  design 
of  Captain  J.   H.  Waller. 

A  third  method  of  building  pre-cast  concrete  vessels  was 
introduced  by  B.  N.  Stroyer  in  the  construction  of  ten  lighters 
for  the  British  Admiralty  by  the  firm  of  Christian!  &  Nielsen, 
London.  Fig.  54  shows  five  of  the  ships,  delivered  in  March 
1919.  The  lighters  are  equipped  with  steam  capstans  and 
winches  for  handling  coal  and  are  built  to  the  approval  of  Lloyd's 
Register.  Their  dimensions  are  185'  X  35'  X  18',  and  the 
deadweight  carrying  capacity  is  probably  between  800  and  900 
tons.  The  bottom,  deck,  stem  and  stern  parts  were  concreted 
in  situ,  but  the  sides  were  pre-cast  in  large  sections  horizontally 


BRITISH   CONCRETE   S.S.    ARMISTICE  187 

and  afterwards  raised  in  place  by  cranes,  before  the  bottom  and 
deck  were  concreted.  In  executing  a  large  order  for  ships  of 
exactly  the  same  type  and  size,  and  where  it  is  possible  to  use 
a  dry  dock  for  the  construction,  the  system  may  save  time  and 
possibly  cost.  But  under  ordinary  conditions,  particularly  in 
constructing  larger  ships,  it  is  doubtful  whether  such  advantages 
would  be  gained.  The  side  sections  would  be  very  heavy  and 
awkward  to  place  in  position  on  the  launching  ways,  unless  each 
section  was  made  quite  narrow,  and  this  would  mean  more  joints 
with  expensive  or  weak  connexions. 


FIG.   54. — Concrete  Lighters  with  pre-cast  sides,  built  for  the  British  Admiralty 
at  Tilbury,  by  Messrs.   Christiani  &  Nielsen. 

S.S.  "Armistice." — The  first  seagoing,  engine-driven  concrete 
ship  built  in  Great  Britain  was  the  cargo  carrier  S.S.  Armistice, 
built  by  the  Ferro- Concrete  Ship  Construction  Co.  at  Barrow-in- 
Furness.  The  dimensions  of  the  ship  are  :  length  b.p.  205  ft., 
breadth  32  ft.,  depth  19  ft.  6  in.,  with  steam-engine  of  400  I.H.P. 
The  deadweight  capacity  is  said  to  be  1,150  tons.  On  her 
maiden  voyage,  from  Londonderry  to  London  in  February  1919, 
the  Armistice  carried  1,000  tons  of  oats  in  bulk.  The  ship  has 
been  described  in  papers  by  Mr.  Owens  Thurston,  Managing 
Director  of  the  Ferro- Concrete  Ship  Construction  Co.,  before 
the  Institution  of  Naval  Architects,  and  by  Mr.  De  Vesian,  of 
the  firm  Mouchel  &  Partners  (who  prepared  the  reinforced 


188       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

concrete  design)  before  the  British  Concrete  Institute  on  27th 
March  1919.     Fig.  55  shows  the  launching  of  the  ship. 

The  Armistice  was  built  to  class  in  Lloyd's  Register.  The 
concrete  proportioned  about  1  :  1-3  :  2-7  and  was  placed  mono- 
lithically  in  wood  forms  around  the  reinforcement  ;  steel  centring 
was  tried  also  for  the  sides.  The  transverse  frames  are  3  feet 
apart  with  heavy  longitudinal  stringers  at  the  bilges  and  gun- 
wales. The  hull  seems  to  be  considerably  heavier  than  necessary. 
The  actual  deadweight  capacity  is  not  known,  but  assuming  that 


FIG.   55. — Launch  of  S.S.  Armistice,  built  by  the  Ferro-Concrete  Ship  Construc- 
tion Co.   at  Barrow-in-Furness. 


it  is  equal  to  the  estimate  of  1,150  tons,  it  is  only  49  per  cent, 
of  the  total  displacement  of  2,350  tons.  The  designers  may 
not  have  had  free  hands  in  the  matter,  since  the  ship  was  built 
to  class  ;  but  had  the  Armistice  been  constructed  on  the  lines, 
for  example,  of  the  author's  design  in  the  Askelad,  the  ratio  of 
deadweight  to  total  displacement  would  have  been  54-9  per 
cent.,  giving  a  deadweight  of  about  1,290  tons,  or  12  per  cent, 
increased  cargo  capacity.  Some  saving  could  have  been  made 
on  the  steel  reinforcement,  which  is  said  to  be  190  tons  or  about 
16 J  per  cent,  of  the  deadweight.  In  the  Askelad  9f  per  cent. 


DANISH   CONCRETE   S.S.   BARTELS  189 

steel  was  used,  which  for  a  vessel  of  1,290  tons  deadweight  would 
equal  126  tons,  or  64  tons  less  than  used  in  the  Armistice.  The 
merits  of  the  respective  designs  are  best  seen,  however,  by  com- 
paring the  steel  per  ton  deadweight  actually  constructed,  which 
means  16|-  per  cent,  against  9|,  or  nearly  70  per  cent,  more  steel 
per  ton  deadweight  in  the  Armistice  design.  The  ship  is  reported 
to  be  seaworthy  and  watertight.  But  the  author  is  of  the 
opinion  that  the  concrete  used  (1  part  cement  to  4  parts  aggre- 
gate) was  not  rich  enough.  Practical  experience  has  shown 
that  the  plasticity  and  certainty  of  watertightness  so  vitally 
important  in  concrete  ships  can  be  assured  only  by  reducing 
the  amount  of  aggregate,  especially  of  the  coarse  type,  con- 
siderably beyond  what  laboratory  investigations  may  indicate  ; 
and  the  mixture  ought  not  to  be  less  rich  than  about  1  part 
Portland  Cement  to  2J  parts  well- graded  aggregate  (up  to  J  inch 
size).  The  additional  cost  of  cement  is  a  trifling  matter  compared 
to  the  total  cost  of  a  seagoing  ship. 

It  has  been  said  that  the  Armistice  after  her  first  trials 
developed  some  cracks  in  the  deck  near  the  hatches,  but  the 
matter  has  evidently  not  been  of  serious  importance  as  the  ship 
has  given  good  service.  In  the  Financier.,  3rd  August  1920, 
there  is  a  statement  by  Messrs.  Leopold  Walford,  Ltd.  (London), 
as  to  their  twelve  months  charter  of  the  ship.  The  Managers 
say  that  she  has  been  running  since  March  1919  like  a  clock, 
causing  no  trouble,  disappointment,  delay,  or  difficulty.  She 
has  proved  thoroughly  seaworthy,  and  costs  in  upkeep  only 
about  a  fifth  of  the  average  cost  of  steel  ships  working  under 
similar  conditions. 

It  is  understood  that  the  first  cost  of  constructing  the  Armistice 
was  very  high,  but  it  would  not  be  fair  to  assume  from  this 
regrettable  fact  that  subsequent  ships  would  be  as  expensive. 
Experience  would  undoubtedly  have  enabled  her  designers  and 
builders  to  reduce  costs  very  much  on  later  ships  if  the  termination 
of  hostilities  had  not  brought  an  almost  immediate  stop  to 
shipbuilding  activities  on  the  new  and  untried  concrete  con- 
struction. 

S.S.  "Bartels." — The  largest  concrete  ship  built  in  Europe 
up  to  date  is  the  S.S.  Bartels,  constructed  in  Denmark  by  the 
N.  H.  &  I.  Cyclone  A.S.  in  co-operation  with  the  Kjobenhavns 
Flytedok  &  Skibsvaerft  at  Fredriksholm.  The  ship  was  com- 


190 


DANISH   CONCRETE   S.S.   BART  ELS 


191 


pleted  in  June  1920,  and  after  a  successful  trial  placed  in  the 
coal  trade  to  England,  where  she  seems  to  have  given  satis- 
factory service. 


ffO 


FIG.   57.— S.S.   Bartels,  Midship  Section. 

The  dimensions  of  the  Bartels  are  :  length  230  ft.  10  in., 
breadth  36  ft.  8  in.,  depth  from  turret  deck  25  ft.  5  in.,  draught 
loaded  17  ft.  7  in.  The  total  displacement  is  3,300  tons,  made 
up  by  1,500  tons  weight  of  the  ship  and  1,800  tons  deadweight. 


192       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

The  deadweight  is  equal  to  54-5  per  cent,  of  the  total  displace- 
ment, and  makes  the  S.S.  Bartels  together  with  the  Askelad  and 
Faith  the  three  lightest  concrete  ships  so  far  constructed.  The 
Bartels  is  built  to  class  in  the  Norwegian  Veritas.  Her  light 
weight  of  hull  might  seem  to  show  that  the  author's  criticism 
of  classed  concrete  ships  as  being  too  heavy  is  not  justified  ; 
but  the  light  hull  of  S.S.  Bartels  is  due  to  a  special  type  of  con- 
struction, which  may  or  may  not  be  advantageous. 

From  a  technical  point  of  view  the  system  adopted  in  the 
construction  of  the  Bartels  is  sound  ;  but  as  regards  certain 
practical  considerations  of  importance,  the  writer  doubts  whether 
the  type  is  an  improvement  on  the  ordinary  method.  The  design 
of  the  bottom  was  suggested  by  the  late  Mr.  Bartels  and  by 
Mr.  K.  Hoigaard,  who  has  described  the  ship  in  a  paper  presented 
before  the  Danish  Engineering  Society  (Dansk  Ingeniorforening) 
on  the  18th  February  1920.  The  turret  or  trunk  deck  gives 
increased  depth  of  construction  against  longitudinal  strains ; 
it  also  makes  the  vessel  "  self-trimming,"  in  a  measure,  for  coal 
and  similar  cargo  in  bulk.  On  the  other  hand,  the  deck  con- 
struction is  complicated  and  expensive.  The  ship  does  not 
gain  in  seaworthiness,  but  is  apt  to  work  heavily  in  a  rough 
sea,  and  she  has  much  less  buoyancy  above  the  harbour  deck 
than  the  ordinary  ship.  The  turret  type  for  steel  ships  is  no 
longer  popular  among  shipowners,  and  has  practically  gone 
out  of  use.  With  the  turret  deck  construction  the  main  section 
of  longitudinal  deck  reinforcement  becomes  too  concentrated 
near  the  hatches,  instead  of  at  the  gunwales,  where  it  is  more 
effective. 

The  bottom  construction  of  the  Bartels  is  radically  different 
from  that  of  ordinary  types.  Figs.  57  and  58  show  the  arrange- 
ment, which  consists  of  a  large  number  of  slanting  struts  between 
an  outer  and  inner  slab.  Shallow  longitudinal  beams  connect 
the  struts,  which  slope  both  ways,  thereby  tying  the  construction 
together  in  a  kind  of  truss  system.  The  slabs  are  very  light, 
3J-3J  inches  thick  ;  the  beams  are  10  X  10  inches  ;  and  the 
struts  are  6x6  inches  ;  all  are  heavily  reinforced,  there  being 
no  less  than  eight  £  inch  round  rods  in  each  strut.  The  amount 
of  steel  in  the  Bartels  has  not  been  published,  but  the  writer 
believes  it  must  be  very  considerable,  judging  from  the  plans 
and  photographs  during  construction.  The  labour  required  to 


DANISH   CONCRETE   S.S.   BART  ELS 


193 


erect  the  unusually  complicated  reinforcement  and  forms  for  the 
bottom  and  deck  must  also  have  amounted  to  much  above  that 


for  ships  of  ordinary  form  ;    but  cost  data  on  these  interesting 
items  have  not  been  available.     The  period  of  construction  was 
nearly  two  years,   but  the  builders  no  doubt  met  initial   diffi- 
culties which  would  not  occur  on  later  ships. 
13 


194       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

The  double  bottom  is  of  questionable  value  ;  it  reduces  the 
cubic  space  of  the  hold,  necessitates  extra  pipe  lines  with  pumping 
arrangement,  and  there  is  no  need  for  water  ballast  tanks  in 
concrete  ships,  except  fore  and  aft  for  trimming.  Usually  the 
inner  bottom  adds  extra  weight  to  the  hull,  but  this  may  not 
be  the  case  in  the  S.S.  Bartels,  where  the  inner  bottom  is  an 
integral  part  of  the  truss  supporting  the  outer  bottom.  The 
author  would  prefer  a  massive  outside  bottom  slab  of  double 
thickness  (6  or  7  inches),  which  would  not  be  excessive  for  a 
ship  of  this  size.  The  Bartels  grounded  some  time  ago,  and 
the  inner  bottom  proved  valuable  as  it  kept  the  water  out ;  but 
it  might  be  argued  that  perhaps  no  leak  would  have  occurred 
if  the  outer  bottom  had  been  much  stronger. 

Present  Tonnage  of  Concrete  Ships.  — In  dealing  with  the 
foregoing  examples  the  intention  has  been  to  demonstrate  different 
methods  of  construction  and  types  of  ships  in  order  to  show 
what  ideas  have  been  tried  in  concrete  shipbuilding  up  to  date. 
Many  other  ships  have  been  built  in  the  countries  mentioned, 
as  well  as  in  France,  Italy,  Spain,  China,  India,  and  other 
countries  ;  but  the  vast  majority  of  these  have  contributed 
nothing  new  or  of  special  interest  to  the  development  of  the 
art.  The  largest  programme  for  the  construction  of  concrete 
ships,  apart  from  that  of  the  U.S.  Shipping  Board,  was  started 
in  Great  Britain  during  1918  by  the  Ministry  of  Shipping.  It 
originally  embodied  the  construction  of  about  150,000  tons 
deadweight,  but  it  was  at  the  Armistice  almost  abandoned.  Of 
ships  completed  in  different  yards  may  be  mentioned  a  dozen 
seagoing  tugs  of  general  dimensions  125'  0"  X  21'  6"  X  14'  9", 
mean  draught  12'  0",  triple  expansion  engine  of  750  I.H.P.  ;  and 
about  fifty  seagoing  lighters  180'  0"  X  31'  6"  x  19'  6".  It  is 
estimated  that  in  all  countries  together  about  one  hundred 
seagoing  concrete  ships  with  an  aggregate  tonnage  of  approxi- 
mately 150,000  deadweight  tons  have  actually  been  completed 
up  to  the  present.  In  addition  to  this  several  hundred  lighters 
and  other  small  craft  for  enclosed  waters  have  also  been  con- 
structed. 

From  these  figures  it  would  seem  that  ample  material  is 
available  to  determine  by  practical  experience  the  merits  of 
concrete  ships.  This  is  true  only  in  a  certain  measure,  which 
applies  to  the  elementary  though  most  important  points  such 


AUTHOR'S  RECOMMENDATIONS  195 

as  strength,  watertightness,  and  seaworthiness.  In  regard  to 
practical  considerations  of  equal  importance,  such  as  First  Cost, 
Cargo  Capacity,  Speed,  Running  Expenses,  etc.,  not  to  mention 
details  and  time  of  construction,  the  existing  tonnage  is  not 
able  to  offer  definite  information,  since  it  consists  only  of  experi- 
mental ships,  built  as  a  rule  by  people  who  neither  had  a  yard 
nor  any  previous  shipbuilding  experience,  and  whose  activities 
were  stopped  before  they  even  had  a  chance  to  build  a  second 
vessel. 

Author's  Recommendations. — Having  considered  briefly  the 
ideas  and  methods  proposed  by  other  engineers,  the  author 
desires  to  mention  that  he  has  himself  discarded  as  unpractical, 
or  too  expensive,  several  of  his  own  ideas  on  which  patents  were 
granted,  and  numerous  others  which  through  practical  experience 
were  found  unsuitable  in  the  construction  of  seagoing  ships. 
The  methods  of  design  and  construction  which  so  far  have  given 
the  best  results  are  fully  described  in  previous  chapters,  but  the 
author  admits  that  they  are  far  from  perfect,  and  will  in  the 
course  of  further  development  no  doubt  be  much  modified  or 
perhaps  radically  changed. 

Whatever  the  future  brings  in  the  way  of  improvements, 
there  are  at  present  some  fundamental  facts  which  may  be  set 
down  almost  with  certainty  as  recommendations  for  concrete 
shipbuilders  : 

Exterior  Shape.— There  is  no  reason  for,  nor  advantage  to  be 
gained  by,  building  seagoing  concrete  ships  different  in  outside 
shape  or  proportions  from  the  best  practice  among  naval  archi- 
tects for  steel  ships  of  all  types.  "  Simplified  "  lines  do  not 
appreciably  reduce  the  cost  of  outside  centring  ;  extra  depth  is 
not  needed  to  secure  sufficient  longitudinal  strength,  and  super- 
structures on  deck  are  required  for  just  the  same  reasons  as  on 
steel  ships. 

Details. — There  is  considerable  scope  for  the  ambitious 
designer  to  improve  details  of  the  hull,  which  differ  greatly 
from  those  of  the  steel  ship  on  account  of  the  nature  of  concrete. 
It  is  certain  that  it  is  not  economical  to  place  frames  as  close 
together  as  in  steel  ships.  It  is  not  advisable  to  construct  sides 
or  bottom  of  cellular  types  with  very  thin  double  walls.  The 
shell  should  be  as  massive  and  thick  as  possible  without  unduly 
increasing  the  weight ;  this  facilitates  the  placing  and  utilization 


196       SEAGOING  AND   OTHER   CONCRETE   SHIPS 

of  the  reinforcement,  and  cheapens  the  construction.  All 
accidents  to  concrete  ships  have  shown  relatively  greater  weak- 
ness of  shell  than  of  frames. 

When  a  really  satisfactory  light  concrete  is  developed  it  is 
not  unlikely  that  the  shell  thickness  will  be  greatly  increased, 
and  that  frames  between  bulkheads  will  be  nearly  dispensed 
with.  Whether  transverse  or  longitudinal  frames  are  most 
economical  is  an  open  question,  and  the  weight  of  the  hull  comes 
out  practically  the  same  in  either  case.  For  transverse  frames 
a  minimum  spacing  of  about  4  feet  is  generally  to  be  recommended. 

Construction  and  Launching. — In  the  author's  opinion  concrete 
ships  should  be  monolithically  constructed  and  the  concreting 
done  in  one  continuous  operation  as  far  as  possible  within 
reasonable  and  practical  limits  ;  this  is  in  keeping  with  the 
character  of  the  material.  The  exterior  centring  is  erected  first 
and  the  steel  must  of  course  be  in  place.  At  present  it  is  difficult 
to  see  any  better  way,  but  when  special  types  of  reinforcement 
are  manufactured  for  concrete  shipbuilding  and  the  industry 
has  been  firmly  established,  improvements  in  construction  will 
naturally  occur.  There  is  certainly  no  need  of  any  spectacular 
methods  of  building  or  launching  concrete  ships  in  any  other 
position  than  that  which  hundreds  of  years  have  shown  to  be 
best  for  ships  of  wood  and  steel. 


ADDENDUM 

Note  to  paragraph  on  p.  189,  S.S.  "  Bartels."  — What  is 
now  presumably  the  largest  concrete  ship  constructed  in  Europe 
is  reported  to  have  just  been  launched  at  Lavagna  in  Italy. 
Designed  by  Signor  Galliquani,  this  vessel  is  named  the  Persi- 
voranza,  is  said  to  be  of  4,700  tons  displacement  and  3,000  tons 
burden,  and  is  fitted  with  two  motors  to  give  a  speed  of  8  knots 
per  hour. 


[App.  p.   1] 


APPENDIX 
CALCULATIONS    FOR    THE    TRIAL    SHIP   ASKELAD 

1,000  tons  D.W.  Cargo  Vessel,  propelled  by  two  160  H.P.  Bolinder 
crude  oil  engines. 

Material  :    Portland  Cement  Concrete  reinforced  with  steel  rods. 

Hull  No.  21. 

Designed  and  built  by  Fougners  Staal-Beton  Skibsbygningscompani 
A.S.,  Shipyard  at  Jeloen,  Moss. 

Note. — These  calculations  are  presented  just  as  they  were  made 
in  the  office.  They  may  be  crude  in  some  respects,  and  the  design 
could  of  course  be  considerably  improved  with  our  present  experi- 
ence ;  but  it  should  be  remembered  that  when  they  were  made,  the 
only  seagoing  concrete  ship  in  the  world  was  the  little  Namsenfjord. 


197 


198  [App.  p.  2]  APPENDIX 


.  -  0" 


i 

i,  L.  1 

* 

.  -LJ 

l( 


To 


To 


SHIP. 


To    Tv^.  PO\\AT 


TTN.. 


"To 


TSL 


CALCULATIONS   FOR   THE   ASKELAD     |_App.  p.   3]  199 


tVL  TooT 
-x  \\x  Vo. 


To 


A-x 


*^ « 


(t-\"H\^&^W.S 
x-V* 


=      %.1.lOO     -  ^*    *%«>«nt  *»ooo  a         \°iji^0   \\je-, 


^^^^«.\H^«bTKt«o«b    TI  ^>^V°     _   N^^    \Ws/ft. 

5>*xMS 


200  [App.  p.  4]  APPENDIX 


^.0%  ov  THE.  VE.co<\)^.\-<b  \_^-n<i»rrH  VRQVX  'bT^-VN  To 


R.  A'-o" 


1.\aO 


H 


YY*- 


fc«    •»•%»*  «      '^W  00 

\«  %••%  s         % t>o 


To 


Pt-H   roo-T    \_t-n.^TV\    OV    "ovkvP 

^Vka  ^.>\°>.ooc>^q»a  ^a^«».oOo    t  \b« 
V^ 

F\T 


*•      V 


'-  10" 


t¥>i  IV 


CALCULATIONS   FOR   THE   ASKELAD     [App.  p.  5]  201 


f  \_o 


H*.o  To 


K1% 


1.      \Vio 


't.O.oo 


T   ToR. 


$*  i    •    T=  * 

.000  A  \S>X    =      \6r.\oes  \b-b 


202  [App.  p.   6]  APPENDIX 


NATE. 
uiou^L  \-\*VF_ 


Tvvt 


V 


-  tt-t. 


jgf 


T 


p  - 


ill    F  RO  ^ 
I  T  T  T  T  M  T  T  T  I    wt  FV 


FRO* 


*       O.V%     l/PvXnY 


CALCULATIONS   FOR   THE   ASKELAD     [App.  p.  7]  203 


^HX.^^n^av    Vr*.Va*       \tS    **.*.\.«aon  •=•       *T.^^QO     _    -^-^  Q'V 

\\u~b  o 


7. 


W 


y\- 
\t. 


0V 


To 


\«o 


UY  To      o       V<T 


WE.  V<.^.^.^> 


^       i 


\\> «»/,.. 


s     \\.\oo 


OV        W\_ 


\\ 


Wu  .         \XVan\XO, 
^O  ^«> 


204  [App.  p.   8] 


APPENDIX 


'f  I* 


N 

f 

I- 

i 

a 

• 

0 
f 

\      ! 

i 

/ 

<^ 

if* 

\          ii^ 

> 

1, 

'o                                 > 

\     ••? 

<0 

^0                   " 

CALCULATIONS   FOR   THE   A8KELAD     [App.  p.  9]  205 


\ 


A 


206  [App.  p.   10]  APPENDIX 


\-.*.t\«TH  «r  WV/v  »  \*Vtl-tf 
>M\^X,T  «T   v^Ky^.  »      Ci-V" 


CALCULATIONS  FOR  THE  ASKELAD     [App.  p.   11]  207 


FOR 


To    e»S_     y^o  07 


Vttl-o"    WttD 


OF 


FROM 


To     00  R 


We. 


OUR 

J>0       Q     «      -*»^° 
V>          fe^eo 

V\7W*_'.          <^*-S^A_  %       oR 

•F    "t 
OF 


«    \°i^  Ton«o. 


FoR 


OF        X         To 


OF 


Mb. 


208  [App.  p.   12]  APPENDIX 


.    SJ — 
&< 


Va^o 

\Vooo  X\- IT*. 


O  VVi 
O    \  V 

o.w 


"tSfoVoH 

e>o 

\^o  \y>«. 


CALCULATIONS  FOR  THE  A8KELAD     [App.  p.   13]  209 


KT 


\_OOW    ^t.^^     a 


A-d 


P.  H 

0.0%  »^% 


.  oo  o  \ 

\ 


*  T*    \V»  fc"  WT  To 
\t9>o     -      *--  \ 


S     •j.'.^o 
\  fc.o^ 


\*>.ooo      «V^ 


14 


210  [App.  p.   14]  APPENDIX 


II  \*\  I  I  I  I    I  I  I  I  I  IT 


CALCULATIONS  FOR  THE  ASKELAD     [App.  p.  15]  211 


its 


^  C  •  X  .  t)      d  - 


OR 


\i.««- 


5i«"»A 


t,oo 

>     caTtt\.  TI.I 
Vaoo*   \>O«B. 


\«o  W\ 
T  «.t\« 


INDEX 


Aaron  Mariby,  S.S.,  1 

Abrams,  Prof.  Duff  A.,  129 

Action  of  sea-water,  138-9 

Admiralty  lighters,  British,  187 

Aggregates,  113-24 

— ,  percentages  of  voids  in,  122 

Agriculture,  U.S.  Dept.  of,  Bull.  No. 

235,  125 
American   Concrete   Institute,   46,   72, 

78,  82,  85,  118,  150 

—  ships,  45-9 

—  Fuel  Oil  and  Transportation  Co.,  78 

—  Railway   Engineering    Association, 
150 

—  Society  for  Testing  Materials,  111, 
147,   150 

—  of  Civil  Engineers,  111,  150,  151 
Andrews,  H.  B.,  85 

Armistice,  S.S.,  187-9 
Askelad,  M.S.,  ashore  on  French  coast, 
86-90 

—  calculations  for,  197-211 

—  carrying  capacity,  38 

—  constructional  details,  28-33 

—  cost  data,  39 

—  —  of  repairs,  90 

—  first  North  Sea  trip,  35 

—  main  particulars,  27-8 

—  negotiations  for  construction,    19- 
20 

— ,  seagoing  service  to   present    date, 

36-8 

— ,  trials  and  inspection,  33 
Aspdin,  Joseph,  108-9 
Atlantus,  S.S.,76 
Ayre,  A.  L.,  150 


Baker,  G.  S.,  100 
Bartds,  S.S.,  189-94 
Beams,  deck,  etc.,  164 
— ,  double  reinforcement,  154-7 
— ,  single  reinforcement,  151-4 
Betongelt,  A.  B.,  183 
Betonverket,  A.  B.,  183 
Bond  strength,  132-3 
Bottom  floor  prepared,  169-71 

—  frames,  159-60 

—  reinforcement  in  place,  and  side,  172 


British    Admiralty,    concrete    lighters 

for,  186 

—  concrete  ships  and  lighters,  184-9 
Bruhn,  Dr.  J.,  9 
Brunei,  I.  K.,  2 
Bryde,  Mr.,  20,  56 

Bulkheads,  design  of  watertight,  164 
Buoys,  concrete  mooring,  65 
Bureau  of  Standards,  U.S.,  140 
Bush,  A.  L.,  78 


Calculations  for  M.S.  Askelad,  197-211 

—  M.S.  Namsenfjord,  10-1 

—  M.S.  Stier,  strength,  21-2 
—  in  theory  of  design,  151-8 

Cape  Fear,  S.S.,  carrying  capacity,  46 

— ,  cost  data,  49 

— ,  dimensions,  76 

Cargo  carriers,  American  concrete,  45-9 

Carrying    capacities    of    S.SS.    Selma, 

Latham,  Cape  Fear,  Sapona,  and  M.  S. 

Askelad  compared,  47 

—  of  trial  (M.SS.  Stier  and  Askelad) 
and  classed  (M.SS.  Patent  and  Con- 
crete) ships  compared,  43 

Cement  finish,  general  method  of,  175-8 

— ,  Portland,  108-12 

Cement-gun,  concreting  by,  178-80 

Centre  keelson,  160 

Centring  and  reinforcement  completed, 

172 
Chemical      properties      of      Portland 

cement,  110 

Christiani  and  Nielsen,  Messrs.,  186 
City  of  Atlanta,  S.S.,  77 
Civil  Engineers,  American  Society  of, 

111,  150,  151 

— ,  Institution  of,  138 
Classification    societies    and    concrete 

ships,  41-2 

Clyde  Steamship  Co.,  78 
Coefficient  of  elongation  of  steel,  148 
Comparative  values  of  cargo  carriers, 

43-5 
Compressive  strength  of  shipbuilding 

concrete,  130-1 
Comyn,  W.   L.,  68,  70 
Concrete,  M.S.,  cost  data,  43 
Concrete  floating  dock,  the  first,  56-60 
—  Institute,  188 


212 


INDEX 


213 


Concrete  Institute,  American,  72,  78 

—  lighters,  American,  79-82 
— ,  British,  184-7 

—  compared  with  wood  and  steel, 
67 
— ,  Norwegian,  65—6 

—  lightship,  Jldjernsflu,  60-2 

—  mooring  buoys,  65 

—  oil-tankers,  79-82 

—  Seacraft,  Ltd.,  185 

—  Ship  Section,  U.S.  Shipping  Board, 
72 

— ,  shipbuilding,  108 
— ,  — ,  elasticity  of,   133-4 
— ,  — ,  oilproofing  of,   141 
— ,  — ,  percentage  of  voids  in    aggre- 
gate, 122 
— ,  — ,  Portland  cement  for,  108-12 

—  ships,  American,  45-9 
— ,  British,  186-9 

— ,  comparative  cost  data  for  steel 
and,  96-100 
— ,  Danish,  189-94 
— ,  first  classified,  41 
— ,  future  of,  5-6,  104-6 
— ,  present  tonnage  of,  194-5 
— ,  running  expenses,  etc.,  102-4 
— ,  speed  of,  100-2 
— ,  Swedish,  183-4 

—  tug,  the  first,  50-6 

—  v.  steel  for  ship  construction,  4-6 

—  water-carrier,   the  first,    62-3 
— ,  watertightness  of,  134-5 
Concreting  by  cement-gun,  178-80 

-  finished,  174-5 
— ,  general  method  of,  172-4 
Construction,  general  method  of,   169 
— ,  special  methods  of,  181 
Contraction  and  expansion,  135-6 
Cost    data,    comparative,    for    similar 
steel  and  concrete  ships,  96-100 

— ,  M.S.  Concrete,  43 

— ,  repairs  to  M.S.  Askelad,  90 

—  — .  —  to  M.S.  Nicanor,  90-1 
— ,  —  to  M.S.  Stier,  92 

— ,  S.SS.  Selma,  Latham,  Cape  Fear, 
Sapona,  and  M.S.  Askelad,  compara- 
tive, 49 

— ,  trial  and  classed  ships,  43-5 
— ,  —  ships  Askelad  and  Stier,  39 
Cuyamaca,  S.S.,  dimensions,  76 
Cyclone,  A.  S.,  N.  H.  and  I.,  189 

D 

Danish  concrete  ship,    189-94 

—  Engineering  Society,  192 
Deck  beams,  etc.,  164 

— ,  cement  finish  for,  177 

— ,  centring  in  place,  172 

Deflection  test  on  lighter,  166-8 

Design,  centre  keelson,  160 

— ,  deck  beams,  etc.,  164 

— ,  longitudinal  strength  in,  161-3 

— ,  side  frames,  158-9 


Design,  theory  of  structural,  151-8 
— ,  watertight  bulkheads,   164 
Dinsmore,  S.S.,  dimensions,  76 
Dock,    dimensions   and   particulars   of 

concrete  floating,  57-8 
Durham,  R.  P.,  M.S.,  181-3 

E 

Elasticity  of  concrete,  133-4 
Engineering,   186 
-  News-Record,  94,  118,  181 
Engineering  Society,  Danish,  192 

— ,  Liverpool,  184 
Engineers,  American  Society  of  Civil, 

111,  150,  151 

— ,  Institution  of  Civil,  138 
Equipment    of   concrete   ships,     14-5, 

17-8 
Expansion  and  contraction,  135-6 


Faith,  S.S.,  68-71 

Ferguson,  L.  R.,  94 

Ferro-Concrete  Ship  Construction  Co., 
187 

Financier,  The,  189 

Finish,  general  method  of  cement, 
175-8 

Finished,  concreting,  174-5 

Fire-resistance  of  concrete,  144-5 

Floating  dock,  first  concrete,  56-60 

Fougner  Concrete  Shipbuilding  Co. 
(New  York),  76,  79 

— ,  Hermann,  71,   141 

Frame  centring  and  reinforcement  in 
place,  172 

Frames,  bottom,   159-60 

— ,  side,  design  of,  158-9 

France  and  Canada  Oil  Transporta- 
tion Co.,  78,  182 

Freeboard  in  concrete  ships,  47 

Freezing  of  shipbuilding  concrete, 
128-9 

Future  of  concrete  ships,  5-6,  104-6 

G 

Garry  Owen,  S.S.,  2 
Glaettli,  J.,  jun.,  78 
Great  Britain,  S.S.,  2 

H 

Hardening  of  Portland  cement,  109-12 
High-carbon  steel  reinforcement,  148-9 
Hogging,  161 
Hoigaard,  K.,   192 
Hool  and  Johnson,  150 
Hurley,  E.  N.,  72 


Ice-breaker,  first  concrete  (tug),  53 
Ildjernsflu,  concrete  lightship,  60-2 
Impurities  in  aggregate,  115-6 


214 


INDEX 


Institute,  Concrete,  188 

— ,  — ,  American,  78 

Institution  of  Civil  Engineers,  138 

—  of     Engineers     and     Shipbuilders, 
North- East  Coast,  100 

—  of  Naval  Architects,  187 
Iron  ships,  development  of,  1-4 


Journal  of  Commerce,  184 

K 

Keelson,  design  of  centre,  160 
Kjobenhavns  Flytedok  and  Skibsvaerft, 
189 


Labour,  cost  and  amount  of,  97,  99- 

100 

Latham,  S.S.,  carrying  capacity,  46 
— ,  cost  data,  48-9 
— ,  dimensions,  76 
Lighter,  deflection  test  on,  166-8 
Lighters,  concrete,  American,  79-82 
— ,  — ,  British,  184-7 
— ,  — ,  Norwegian,  65-6 
Lightship,  first  concrete,  60-2 
Lightweight  aggregate,    117-8 
Linnea,  M.S.,  183-4 
Literature    on    concrete    construction, 

150-1 
Lloyd's  Register  of  Shipping,  4,    147, 

188 

Longitudinal  strength,  161-3 
Lord,  J.  W.,  85 

M 

MacDonald,  Allan,  68 
—  Engineering  Co.,    182 
Maritim,  A.   S.,  56 
Material  per  ton,  units  of,  96 
Materials,  American  Society  for  Test- 
ing, 111,  147,  150 
Michaellis,  Dr.  W.,  138 
Mills,  Prof.  A.  P.,  135 
Mixing  shipbuilding  concrete,  124-6 
Mixture  for  shipbuilding  concrete,  pro- 
portions of,  118-24 
Moffit,  S.S.,  dimensions,  76 
Mortars,  trass,  136-7 
Mouchel  and  Partners,  187 

N 

Namsenfjord,  M.S.,  assumption  for  cal- 
culations,   10-1 
— ,  cementing,  14 
— ,  engine  foundations,  12-4 
— ,  equipment,  14-5 
— ,  first  seagoing  concrete  ship,  7-18 
— ,  Government  permit  obtained,  9-10 
— ,  inspection  after  trials,  16-7 
— ,  launching,    15 
— ,  experience  gained  from,  17-8 


Namsenfjord,  M.S.,  main  particulars,  10 
— ,  method  of  construction,  11-5 
— ,  preliminary  considerations,  7-9 
— ,  stern  post,  14 
— ,  trials,  15-6 

Naval  Architects,  Institution  of,  187 
Nicanor,  M.S.,  90-1 
Norske  Veritas  (see  Norwegian  Veritas) 
North-East  Coast  Institution  of  Engin- 
eers and  Shipbuilders,  100 
Norwegian    Department  of    Shipping, 
7-9,  15-6,  19,  27 

—  Government  requirements?,  7-9,  19, 
21,  164-6 

-Veritas,  21,  147,  162,  165,  166,  192 


Oil  carriers,  concrete,  79 

—  proofing  of  concrete,  141 

—  storage  afloat  and  ashore,  concrete 
for,  82-4 

—  tankers,  carrying  capacities,  76 
— ,  cost  per  ton  deadweight,  49 

Oils,  etc.,  action  of,  139 

Outside  centring  completed,  171-2 


Palo  Alto,  S.S.,  dimensions,  76 
Patent,  M.S.,  carrying  capacity,  43 
Pearson,  J.  C.,  and  J.  A.  Smith,  85 
Peralta,  S.S.,  dimensions,  76 
Physical  properties  of  Portland  cement, 

110-11 

Placing  and  curing  shipbuilding  con- 
crete,  126-8 

Polias,  S.S.,  dimensions,  76 
— ,  on  Cilley  Ledge,  92-5 
Portland  cement,  108-12 

— ,  setting  and  hardening,  109-12 

— ,  specification,  110-12 

—  Cement  Association,  150 
Poss,  Victor,   68 
Pre-cast  construction,  184-7 
Proportions  of  mixture  in  shipbuilding 

concrete,  118-24 

Q 

Quality  of  steel  reinforcement,  147-8 

R 

R.  P.  Durham,  M.S.,  181-3 

Register  of  Shipping,  Lloyd's,  4,  147, 

188 
Reinforcement,       high-carbon       steel, 

148-9 

— ,  quality  of,  147-8 
— ,  specifications  for,  148-9 
— ,  types  of,  146-7 
Repairs,  cost  of,  M.S.  Askelad,  90 
— ,  _,  M.S.  Nicanor,  90-1 
— ,  — ,  M.S.  Stier,  92 

—  to  shipbuilding  concrete,  142-4 


INDEX 


215 


Ritchie,  H.  C.,  184 
Running    expenses,    etc.,    of    concrete 
ships,   102-4 


S 

Sagging,  161 

St.    Valery-sur-Somme,    M.S.    Askelad 

ashore  near,  86—7 

San  Francisco  Shipbuilding  Co.,  68 
San  Pasqual,  S.S.,  dimensions,  76 
Sand,  116-7 

Sapona,  S.S.,  carrying  capacity,  46 
— ,  cost  data,  49 
— ,  dimensions,  76 
Sea- water  in  rich  mixtures  permissible, 

112 

—  on  concrete,  action  of,  138-9 
Selma,  S.S.,  carrying  capacity,  46 
— ,  cost  data,  49 
— ,  dimensions,  76 
Setting    and    hardening    of    Portland 

cement,  109-12 
Shear  strength,   131-2 
Shell  slab,  strength  of,  163-4 
Shipbuilding  concrete,   107 
Shipping    Board,  U.S.,    investigations 

by,  71-2 

— -,  Lloyd's  Register  of,  4,  147,  188 
— ,    Norwegian    Department    of,    7-9, 

15-6,  19,  27 

Side  frames,  design  of,  158-9 
Slater,  W.  A.,  72 
Smith,  G.  A.,  85 
Society,  Danish  Engineering,  192 

—  for  Testing  Materials,  American,  111, 
147,    150 

—  of  Civil  Engineers,  American,  111, 
150,  151 

Socony  200,  201,  and  50,  oil  carriers,  79 

Sorensen,  Thygo,  103 

Specific   gravitv   of   Portland   cement, 

110 
Specification  for  Portland  cement,  110- 

12 

—  for  steel  reinforcement,  147 
Speed  of  concrete  ships,   100-2 
Staal-beton  19,  first  concrete  tug,  50-6 
— ,  main  particulars,  54 

Standard  concrete  ship,  U.S.,   72-3 
-  Oil  Co.,  99 

Standards,  U.S.  Bureau  of,  140 
Steam    curing    shipbuilding    concrete, 

128 
Steel  reinforcement,  high-carbon,  148-9 

— ,  quality  of,  147-8 

— ,  specifications  for,  147 

— ,  types  of,  146-7 

—  ships,  cost  of,  97-100 

— ,  development  of,  3-4 
—  v.  concrete  ships,  4-6 

—  v. ,  comparative  costs,  96—100 

Stern  construction,  concrete  and  steel, 

14,  28,  30 


Stier,   M.S.,   accident  and  cost   of  re- 
pairs, 92 

—  carrying  capacity,  43 

—  constructional  details,  22-6 

—  cost  data,  39 

—  main  particulars,  20 

— :  method  of  construction,   26-7 

—  negotiations  for  construction,  19-20 

—  strength  calculations,  21-2 

—  trials  and  inspection,  27 
Storage  of  Portland  cement,  111 
Strength,  bond,   132-3 

— ,  longitudinal,  161-3 

-  of    shipbuilding     concrete,     com- 
pressive,    130-1 

—  of     shipbuilding     concrete,     shear, 
131-2 

— ,  shell  slab,  163-4 
Stroyer,  R.  N.,  186 
Structural  design,  theory  of,  151-8 

-  Materials    Research    Lab.,    Lewis 
Inst.,    Chicago,    129 

Swedish  concrete  ships,  183-4 
Sydvaranger  Mining  Co.,  164 


Tables  : 

Adhesion  between  steel  and  concrete, 
132 

Average  compressive  values  of  vari- 
ous mixtures,  121 

Compressive  strength,    132 

—  after  28  days,  126 

—  of  trass  mortars,  137 

Effect  of  curing  mortar  under  steam 

pressure,  128 

Elasticity  of  concrete  in  compres- 
sion, 133 

—  of  concrete  in  tension,  1 34 
Percentage    of    voids    in    sand    and 
gravel  corresponding  to  different 
weights  per  cu.  ft.,  123 
Shearing  strength,  132 
Teknisk  Tidskrift,  184 
Tensile  strength  of  Portland  cement, 

111 

Test  on  lighter,  deflection,  166-8 
Testing    Materials,    American    Society 

for,  111,  147,  150 
Theory  of  design,  151-8 
Thurston,   Owens,   187 
Tonnage    of    concrete    ships,    present, 

194-5 

Trass  mortars,  136-7 
Trial  ships   Askelad  and   Stier,   main 
particulars  and  details  of  construc- 
tion, 20-33 

,  negotiations  for,  19-20 

,  summary     of    results, 

38-40 

Tug,  the  first  concrete,  50-6 
Turret  ship,  concrete,  190 
Twin  screws,  concrete  stern  construc- 
tion for,  28,  30 


216 


INDEX 


u 

U.S.  Bureau  of  Standards,  140 

—  Department  of  Agriculture,  125 

—  Shipping  Board,  concrete  ships  com- 
pleted by,  75-8 

— ,  investigations  by,  71-2 
— ,    report    and    projected    pro- 
gramme for  concrete  ships,  72 

—  standard  concrete  ships,  73-4 
Units  of  labour  per  ton,  96-7 

—  of  material  per  ton,  96-7 


Vesian,  de,  187 

Vibration,  pressure,  etc.,  of  shipbuild- 
ing concrete,  129-30 


Vicat,  108 

Voids  in  aggregate,  percentage  of,  122 


W 

Walford,  Leopold,  Messrs.,  103,  189 
Waller,  Capt.  J.  H.,  185,  186 
Water  carrier,  first  concrete,  62-3 

—  mixture  for  Portland  cement,  112-3 
Watertight  bulkheads,   164 
Watertightnets  of  concrete,  134-5,  142, 

143 

—  of  concrete  ships,  16,  27 
White,  Prof.  A.  H.,  135 
Wig,  R.  J.,  48,  78 
Wood  ships,  1-3,  32 


RETURN  TO  the  circulation  desk  of  any 
University  of  California  Library 
or  to  the 

NORTHERN  REGIONAL  LIBRARY  FACILITY 
Bldg.  400,  Richmond  Field  Station 
University  of  California 
Richmond,  CA  94804-4698 

ALL  BOOKS  MAY  BE  RECALLED  AFTER  7  DAYS 
2-month  loans  may  be  renewed  by  calling 

(415)642-6233 
1-year  loans  may  be  recharged  by  bringing  books 

to  NRLF 
Renewals  and  recharges  may  be  made  4  days 